Palmer v. Quinn

2013 MT 378N
CourtMontana Supreme Court
DecidedDecember 31, 2013
Docket13-0132
StatusPublished

This text of 2013 MT 378N (Palmer v. Quinn) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer v. Quinn, 2013 MT 378N (Mo. 2013).

Opinion

December 31 2013

DA 13-0132

IN THE SUPREME COURT OF THE STATE OF MONTANA 2013 MT 378N

M. STACEY PALMER, M. STACEY PALMER TRUST,

Plaintiff and Appellant,

v.

ROBERT QUINN, AMF CONTRACTING, SHAWN JOHNSTON, STEVE JOHNSTON, and GARY PERREN and CITY OF THREE FORKS, MAYOR GENE TOWNSEND, RAY NOBLE and C & H ENGINEERING & SURVEYING, INC. MARK CHANDLER, MATT COTTERMAN AND JOHN DOES 1 THROUGH 20,

Defendants and Appellees.

APPEAL FROM: District Court of the Eighteenth Judicial District, In and For the County of Gallatin, Cause No. DV-09-1211B Honorable Wm. Nels Swandal, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

M. Stacey Palmer, self-represented; San Pedro, California

For Appellees:

Jason T. Cutts; Attorney at Law; Belgrade, Montana (for Gary Perren)

Robert J. Quinn; Attorney at Law; Bozeman, Montana (for AFM Contracting, Shawn Johnston, and Steven Johnston)

Alexander L. Roots, J. Robert Planalp; Landoe, Brown, Planalp & Reida, PC; Bozeman, Montana (for City of Three Forks, Mayor Gene Townsend, and Ray Noble) Neil G. Westesen, Brad J. Brown; Crowley Fleck PLLP; Bozeman, Montana (for C&H Engineering & Surveying, Inc., Mark Chandler, and Matt Cotterman)

Submitted on Briefs: November 20, 2013 Decided: December 31, 2013

Filed:

__________________________________________ Clerk

2 Justice Beth Baker delivered the Opinion of the Court.

¶1 Pursuant to Section I, Paragraph 3(d), Montana Supreme Court Internal Operating

Rules, this case is decided by memorandum opinion and shall not be cited and does not

serve as precedent. Its case title, cause number, and disposition shall be included in this

Court’s quarterly list of noncitable cases published in the Pacific Reporter and Montana

Reports.

¶2 This case arises from a project to develop and subdivide a piece of real property

owned by M. Stacey Palmer (Palmer) near Three Forks, Montana. Palmer and her

business partner, Gary Perren (Perren), hired C&H Engineering & Surveying, Inc. to be

the project engineer and AFM Contracting for construction of underground infrastructure

work.

¶3 The project failed in June 2001 after Palmer could not obtain sufficient financing.

Having completed considerable work, AFM filed a construction lien and a foreclosure

action. We upheld the validity of the construction lien in a 2007 appeal. Johnston v.

Palmer, 2007 MT 99, 337 Mont. 101, 158 P.3d 998.

¶4 The City of Three Forks owned a parcel in Palmer’s subdivision that had been

reserved for future use as a city street (Kentucky Street). Palmer submitted a petition for

the City to vacate the parcel, and the City Council voted to approve the petition on

June 12, 2001. The city took no further action concerning the Kentucky Street parcel

3 until 2009, when Palmer informed the City that her property was sold at a Sheriff’s sale

in December 2008 and requested that the City record the 2001 decision to vacate the

Kentucky Street parcel. The City filed a resolution with the Gallatin County Clerk and

Recorder’s Office on February 27, 2009, recognizing the approved 2001 petition.

¶5 On December 18, 2009, Palmer filed a complaint in the District Court alleging

negligence and contract claims against C&H Engineering and Surveying, Inc., and its

owners Mark Chandler and Matt Cotterman (C&H Defendants); the City of Three Forks,

Mayor Gene Townsend, and city clerk Ray Noble (Three Forks Defendants); AFM

Contracting, its owners Shawn Johnston and Steven Johnston, and their lawyer Robert

Quinn (AFM Defendants); and Perren.

¶6 The District Court granted the C&H Defendants’, Three Forks Defendants’, and

AFM Defendants’ motions for summary judgment on April 8, 2011, December 19, 2011,

and November 21, 2012, respectively. Each was granted for primarily the same reason—

expiration of the time allowed by the statutes of limitation for commencement of an

action.

¶7 The allegations against Perren proceeded to a bench trial on December 5, 2012.

On December 26, 2012, the court issued findings of fact, conclusions of law, and a

judgment in favor of Perren. The court dismissed the majority of Palmer’s claims against

Perren because they were time-barred under the relevant statutes of limitation. The court

determined that the only possible allegation that was not time-barred was the claim for a

4 breach of a written obligation based on a document signed by Perren. The court

concluded, however, that the testimony established that the document was intended only

to help Palmer secure financing and that, because there was no consideration given in

exchange for Perren’s signature on the document, it was not an enforceable contract.

¶8 Palmer appeals the judgments entered by the District Court. We review a district

court’s grant of summary judgment de novo, using the same criteria applied by the

district court under M. R. Civ. P. 56. Draggin’ Y Cattle Co. v. Addink, 2013 MT 319,

¶ 16, 372 Mont. 334, 312 P.3d 451. Summary judgment is appropriate when “the

pleadings, the discovery and disclosure materials on file, and any affidavits show that

there is no genuine issue as to any material fact and that the movant is entitled to

judgment as a matter of law.” M. R. Civ. P. 56(c). We review a district court’s findings

of fact to determine if they are clearly erroneous and its conclusions of law to determine

whether they are correct. Byrum v. Andren, 2007 MT 107, ¶ 14, 337 Mont. 167, 159 P.3d

1062.

¶9 A statute of limitations begins to run “when the claim or cause of action accrues.”

Section 27-2-102(2), MCA. A claim accrues “when all elements of the claim or cause

exist or have occurred, the right to maintain an action on the claim or cause is complete,

and a court or other agency is authorized to accept jurisdiction of the action.” Section

27-2-102(1)(a), MCA.

5 ¶10 Palmer’s claims against all defendants were based generally upon negligence and

breach of contract theories arising out of the failed real estate development project. A

negligence action accrues “when the negligent act or omission occurs.” Bekkedahl v.

McKittrick, 2002 MT 250, ¶ 20, 312 Mont. 156, 58 P.3d 175 (citing N. Mont. Hosp. v.

Knight, 248 Mont. 310, 315, 811 P.2d 1276, 1279 (1991)). Negligence claims are

governed by a three-year statute of limitations. Section 27-2-204(1), MCA. A breach of

contract action accrues at the time of breach, no matter when a party suffers damages.

Textana, Inc. v. Klabzuba Oil & Gas, 2009 MT 401, ¶ 35, 353 Mont. 442, 222 P.3d 580.

Breach of contract claims based on a written instrument must be brought within eight

years, while claims based upon an oral agreement are limited to five years. Section 27-2-

202, MCA. The applicable limitations period for “an action against a municipality

arising from a decision of the municipality relating to a land use, construction, or

development project” is six months. Section 27-2-209(5), MCA.

¶11 On appeal, Palmer argues that the ten-year statute of repose, § 27-2-208, MCA,

should apply to her claims. Because Palmer raises this argument for the first time on

appeal, we decline to address it. Brookins v. Mote, 2012 MT 283, ¶ 24, 367 Mont. 193,

292 P.3d 347. We note, however, that the statute of repose cannot revive a claim that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Montana Hospital v. Knight
811 P.2d 1276 (Montana Supreme Court, 1991)
Bekkedahl v. McKittrick
2002 MT 250 (Montana Supreme Court, 2002)
Murphy Homes, Inc. v. Muller
2007 MT 140 (Montana Supreme Court, 2007)
Byrum v. Andren
2007 MT 107 (Montana Supreme Court, 2007)
Johnston v. Palmer
2007 MT 99 (Montana Supreme Court, 2007)
Textana, Inc. v. Klabzuba Oil & Gas
2009 MT 401 (Montana Supreme Court, 2009)
Brookins Ex Rel. Gotcher v. Mote
2012 MT 283 (Montana Supreme Court, 2012)
Burley v. Burlington Northern & Santa Fe Railway Co.
2012 MT 28 (Montana Supreme Court, 2012)
Draggin' Y Cattle Co. v. Addink
2013 MT 319 (Montana Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2013 MT 378N, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-v-quinn-mont-2013.