Palmer Steel & Iron Co. v. Heat, Light & Power Co.

66 N.E. 690, 160 Ind. 232, 1903 Ind. LEXIS 63
CourtIndiana Supreme Court
DecidedMarch 12, 1903
DocketNo. 20,031
StatusPublished
Cited by4 cases

This text of 66 N.E. 690 (Palmer Steel & Iron Co. v. Heat, Light & Power Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer Steel & Iron Co. v. Heat, Light & Power Co., 66 N.E. 690, 160 Ind. 232, 1903 Ind. LEXIS 63 (Ind. 1903).

Opinion

Hadley, C. J.

Suit by'appellee to recover on account for natural gas sold and delivered to appellant on a written contract. The written contract relied upon is in these words: “Agreement made and concluded August 7, 1899, by and between the Heat, Light & Power Company of first part, and the Palmer Steel & Iron Company of second part, all of Muncie, Indiana, withesseth: That for and in consideration of the payments and rentals to be paid by the second part, as hereinafter mentioned, and in the time and manner hereinafter stated, the first part agrees to allow second part to make connections to first part’s high-pressure city lines at the corner of Willard and-streets, and use gas therefrom for heating, lighting, and manufacturing purposes in the second part’s iron mill located at -street in the southeastern part of the city, at the rate of seven cents per thousand feet discharge from first part’s line where said connections are made, viz., at Willard and-streets; the gas to be used by meter [234]*234measurements, both, parties being allowed to read the meter, and the second party also to pay a rental per month based as follows: $2 per month to be paid to first part for the use of meter or meters, viz., at the rate of $2 per month for each $50 invested in said meter or meters, the second part, however, having the privilege to purchase meters and use the same, and thus avoid payment of the rental above mentioned ; but the first part shall at all times have the privilege of testing such meters as may be furnished by second part, and receive pay therefor at the said above rate per thousand feet for the corrected measurement as made by first part. And it is further agreed by the parties that until such time as the said meters are procured and set for the measurement of said gas the said second party shall pay semimonthly for the gas used, $30 per day, payable on the 15th of the month in which the gas is used, and for the last half of the month between the 1st and the 5th of the following month, with the further understanding that after the meters have been set, if the reading of the same show the value of gas to be more than the said $30 per day then the second part shall at once pay for the difference from the time the gas was first turned into, the mill up to the date of setting said meters, and if, on the other hand, the payment of the said $30 per day by the reading of the meters would show the amount so paid to be in.excess of that due the first part, then the first part shall allow second part a credit for said excessive payment. This arrangement to be in force and effect so long as the first part desires to furnish the gas, not to exceed November 1, 1899, but that no liability on the part of the first part in case of shortage of gas by leakage of lines or otherwise. And second party can terminate this agreement at any time by the payment of all rentals and gas used up to date, they giving notice and having gas turned off. In witness,” etc. '(Signed) “Heat, Light & Power Company, by II. C. Zeig[235]*235ler, P. Palmer Steel & Iron Company, by I. D. Briggs, V. P.”

It is alleged in the complaint that it was the intention and agreement of the parties to the contract that the plaintiff the Heat, Light & Power Company was to, and did, obligate itself to supply gas to three puddling furnaces located on the north side of the defendant’s mill, and no others, but by mutual mistake of the parties and the scrivener who wrote the contract, a provision that gas should he furnished only to said three north furnaces was, by mistake and inadvertence, wholly omitted 4from the contract as written, and the writing was accepted and signed by the parties as expressing.the contract, believing that said provision was incorporated therein; that the plaintiff did attach the defendant’s system of mill pipes with the plaintiff’s high-pressure gas-main, so that gas could be supplied to said three north furnaces; that the defendant had three puddling furnaces located on the east side of its mill building, which were also connected with its system of gas-pipes about said mill, and when gas flowed into the mill pipes the only way to exclude it from said three east furnaces was by closing a stopcock set in one of the pipes, anil which said stopcock, under said contract, was to he closed and kept closed during the continuance of the contract; that on the-day of August, 1899, the plaintiff turned gas into the mill pipes, and the said stopcock was secretly opened, and the gas flowed to, and supplied, said three east furnaces as well as the three north furnaces, thereby supplying six of the defendant’s furnaces, instead of three as provided by the contract, for forty-three days in August and September, 1899; that under the contract the plaintiff was to receive $30 for each and every day gas was furnished to said three north furnaces, and the gas so obtained by the defendant for use in said three east furnaces was reasonably worth $i20 per day for each day so used (a bill of [236]*236particulars thereof is filed, marked A), and that none of the gas so furnished the defendant, and used by it, was measured by meter, and no gas-meter was furnished or used in or about the measuring of said gas, and the plaintiff is wholly unable to state the number of feet of gas furnished the defendant as aforesaid; and that there is a balato.ee due and unpaid on said account of $1,355. Prayer for reformation of the contract, and judgment for $1,500.

Exhibit A sets forth in detail the account sued on, and contains an item of $9.95 for making the connection between the defendant’s mill pipes, and the plaintiff’s gas-main, and forty-three per diem items, stated thus:

August 9. To gas for one day for three furnaces on north side of mill as per contract . ..................i.....$30.00

To gas taken to east side of mill... . $20.00

-- $50.00

August 10. To gas for one day for three furnaces in north side of mill as per contract.................. $30.00'

To gas taken to east side of mill. ... $20.00

- $50.00

Etc., etc., making total of......... $2,154.95

Credited by payments..................... $199.95

Leaving the balance due and unpaid..........$1,355.00

The defendant answered by a general denial and payment. Trial by the court. Special finding, conclusions of law, and judgment in favor of the plaintiff for $591.59.

The sufficiency of the complaint, the action of the court in overruling appellant’s motion for a new trial, in overruling its exceptions to the conclusions of law, and in overruling its motion in arrest of judgment, are properly assigned as error.

The substance of the special finding is as follows: The plaintiff is an Indiana, and defendant an Illinois, cor[237]*237poration; the latter having an office and an iron mill in the city of Muncie, Indiana; in August, 1899, the plaintiff and defendant entered into and executed the written contract set out at the beginning of this opinion; the defendant made connection with the plaintiff’s gas line referred to in said contract, and on the 7th day of August, 1899, began to take and use gas from- such line for heating, lighting, and manufacturing purposes at its iron mill, and continued from the last preceding date until the 19th day of September, 1899, to use, at said mill, natural gas, intermittingly from said line for said purposes; during the period the defendant used gas for all or parts of thirty-two days, and dxiring these thirty-two days gas was burned by.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cripe Et Ux v. Coates Et Ux
116 N.E.2d 642 (Indiana Court of Appeals, 1954)
Lesh v. Bailey
95 N.E. 341 (Indiana Court of Appeals, 1911)
Hoosier Construction Co. v. National Bank of Commerce
73 N.E. 1006 (Indiana Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
66 N.E. 690, 160 Ind. 232, 1903 Ind. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-steel-iron-co-v-heat-light-power-co-ind-1903.