Hoosier Construction Co. v. National Bank of Commerce

73 N.E. 1006, 35 Ind. App. 270, 1905 Ind. App. LEXIS 85
CourtIndiana Court of Appeals
DecidedApril 7, 1905
DocketNo. 4,875
StatusPublished
Cited by6 cases

This text of 73 N.E. 1006 (Hoosier Construction Co. v. National Bank of Commerce) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoosier Construction Co. v. National Bank of Commerce, 73 N.E. 1006, 35 Ind. App. 270, 1905 Ind. App. LEXIS 85 (Ind. Ct. App. 1905).

Opinion

Wiley, J.

Appellee was plaintiff below, and recovered a judgment against appellant for $988.13. The issues were [271]*271joined on the complaint and answer, hut, as no question is presented under the assignment questioning the sufficiency of the pleadings, they will only be referred to in the course of the opinion so far as it is necessary to determine the nature of the action.

It is earnestly contended by appellant that this is a suit in equity, and hence triable by the court,'while on the other hand it is insisted that it is a suit at law, and triable by a jury, if a jury had been demanded. We will first determine the question upon which these contentions are made. It ought not to be difficult to determine from a complaint whether it seeks legal or equitable relief, or both, and therefore we must look to the complaint in this case to determine its character. On the 19th day of January, 1896, the appellant entered into a written contract with the Atlas Lumber Company, and the basis of this action arises under that contract. Under said contract the Atlas Lumber Company agreed to furnish to the appellant a large quantity of cedar blocks for paving streets fin the city of Indianapolis; and it is shown by the averments of the complaint that it carried out its contract, so far as it was carried out, during the year 1896, and in about two years after the completion of the contract on its part it assigned its account growing out of the contract against appellant to appellee. It would seem, from a fair construction of the instrument of assignment, that the contract itself was not assigned, for it is stated in the complaint that the Atlas Lumber Company “does hereby sell, assign, transfer and set over unto said National Bank of Commerce of Seattle, its successors and assigns, all claim and demand of said Atlas Lumber Company against the Hoosier Construction Company of Indianapolis, Indiana, for paving blocks sold and contracted to be sold by said Atlas Lumber Company to said Hoosier Construction Company, and all claim and demand of every kind and nature which said Atlas Lumber Company has against said Hoosier Construction Company, arising out of, or in any [272]*272way connected with, that certain contract between said Atlas Lumber Company and said Hoosier Construction Company, relating to the sale of paving blocks, which said contract is dated January 19, 1896, and all other claim or demand of every nature which said Atlas Lumber Company has against said Hoosier Construction Company.” Both the original contract and the assignment thereunder are made exhibits to the complaint. The allegations of the complaint relative to this assignment are in harmony with the terms of the assignment itself.

1. So far as the character of the action is concerned, it can make little, if any, difference whether the action is upon the contract or on the account due appellee by virtue of the assignment, for in either event it seeks to recover a balance due to the assignee, and such an action is triable on the law side of the court, and therefore triable by a jury, if a demand for one is made, unless the complaint by specific allegation injects into the action some matter or matters of which a court of equity has exclusive jurisdiction. The complaint, as we construe it, seeks to recover from the appellant a balance of $5,000 alleged to be due under the contract since October, 1896', for a large quantity of cedar blocks sold to tire appellant under the contract exhibited with the complaint. This contract provided the manner in which payments should be made by tire appellant. A part of the contract price was to be paid through drafts accompanying the several bills of lading. Appellant was to pay the freight at this end of the line, and was to be given credit upon its account for the several amounts of freight thus paid. The complaint shows the total amount of the contract price of the blocks furnished to appellant, and also gives in detail the amount of payments made by appellant on the contract, and for which it has credit. After stating the whole indebtedness covered by the contract, the complaint contains tire following allegations: “Against which said defendant is entitled to credit for $21,065.65, being the aggregate amount [273]*273of all drafts honored and paid by said defendant, as provided in the contract aforesaid, and for some further sum paid by said defendant for freight upon blocks aforesaid, which sum can not be stated, because it is unknowu to plaintiff or its officers, and is known to defendant and its officers, and which sum can be ascertained only by and with the aid of this honorable court. And defendant asserts other counterclaims and setoffs, the particulars of which pretenses are unknown to plaintiff; and plaintiff denies that there are any other set-offs or counterclaims, and alleges that after malting all deductions, and allowing all credits, counterclaims and set-offs, proper to be made and allowed, there is owing to plaintiff from defendant a balance amounting to about $5,000, which became due October 1, 1896, when said defendant completed work upon the payments [pavements] aforesaid, which is now wholly unpaid, and payment of which has been unreasonably delayed.” The prayer of the complaint is as follows: ■ “Wherefore plaintiff prays that an accounting of the matters herein set forth be taken for judgment against defendant for $6,000, and all other proper relief.”

As above stated, appellant contends that this is. a suit in equity, and under section eight of the act of March 9, 1903 (Acts 1903, p. 338), if required by the assignment of error, it is the duty of the court to weigh and consider the evidence. So much of that section as is necessary to present the question now under consideration is as follows: “In all cases not now or hereafter triable by a jury, the Supreme and Appellate courts shall, if required by the assignment of errors, carefully consider and weigh the evidence and admissions heard on the trial when the same is made to appear by a bill of exceptions setting forth all the evidence given in the cause, and if on such appeal it appears from all the evidence and admissions that the judgment appealed from is not fairly supported by, or is clearly against the weight of [274]*274the evidence, it shall be the duty of such court to award judgment according to the clear weight of the evidence,” etc.

The only error assigned is the overruling of appellant’s motion for a new trial, and one of the reasons assigned for a new trial is that the decision of the court is not sustained by sufficient evidence.

2. Eeferring to the action as made by the complaint, counsel for appellant say: “The action is clearly, by every allegation and prayer, one 'for an accounting. Such an action is an equitable proceeding, and is not triable by a jury. In truth, every action for an accounting must, in the nature of things, be founded upon some right in the nature of an account, claim or contract in which money is due, and it is the prayer and demand for an accounting that takes it out of the law and into equity.” As contrary to this view, counsel for appellee assert that the complaint simply makes a plain action at law to recover a balance due under the contract, and that it does not possess any element of equitable relief. The rule in this State is that the nature of an action must be determined from the general character and scope of the pleading, disregarding isolated and detached allegations not essential to the support of its main theory. Monnett v. Turpie (1892), 132 Ind. 482.

.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartlep v. Murphy
150 N.E. 312 (Indiana Supreme Court, 1926)
Lupton v. Horn
139 N.E. 177 (Indiana Supreme Court, 1923)
Lesh v. Bailey
95 N.E. 341 (Indiana Court of Appeals, 1911)
City of Tipton v. Freeman
90 N.E. 101 (Indiana Court of Appeals, 1909)
United States Board & Paper Co. v. Moore
72 N.E. 487 (Indiana Court of Appeals, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
73 N.E. 1006, 35 Ind. App. 270, 1905 Ind. App. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoosier-construction-co-v-national-bank-of-commerce-indctapp-1905.