Palm Bay Towers Corporation v. Crain & Crouse, Inc.

303 So. 2d 380, 1974 Fla. App. LEXIS 9040
CourtDistrict Court of Appeal of Florida
DecidedOctober 29, 1974
Docket74-300, 74-333
StatusPublished
Cited by2 cases

This text of 303 So. 2d 380 (Palm Bay Towers Corporation v. Crain & Crouse, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palm Bay Towers Corporation v. Crain & Crouse, Inc., 303 So. 2d 380, 1974 Fla. App. LEXIS 9040 (Fla. Ct. App. 1974).

Opinion

303 So.2d 380 (1974)

PALM BAY TOWERS CORPORATION, Appellant,
v.
CRAIN & CROUSE, INC., Appellee.
McCLOSKEY & CO., INC., Appellant,
v.
CRAIN & CROUSE, INC., Appellee.

Nos. 74-300, 74-333.

District Court of Appeal of Florida, Third District.

October 29, 1974.
Rehearing Denied December 9, 1974.

*381 Katz & Rosen, Coconut Grove, for Palm Bay Towers Corp.

Frates, Floyd, Pearson, Stewart, Proenza & Richman and Alan G. Greer, Miami, Wolf, Block, Schorr & Solis-Cohen, Philadelphia, for McCloskey & Co., appellants.

Knight, Peters, Hoeveler, Pickle, Niemoeller & Flynn, Miami, Richard H.W. Maloy, Coral Gables, for appellee.

Before BARKDULL, C.J., and HENDRY and NATHAN, JJ.

PER CURIAM.

This is a consolidated appeal from a final judgment in favor of the defendant-appellees which followed a non-jury trial.

The appellants are the owner and general contractor of the Palm Bay Towers condominium apartment project, a highrise luxury condominium located east of Biscayne Boulevard at N.E. 67th Street in the *382 City of Miami. The appellee, Crain & Crouse, Inc. [hereinafter Crain], was engaged as the structural engineer of the piling and foundation system for the Palm Bay Towers. Appellee, Continental Casualty Company, was joined in the complaint as Crain's liability insurer.

Appellants filed a complaint alleging negligence by Crain in the design, inspection and supervision of the construction of the piling and foundation system. It was alleged that as a result of Crain's negligence the piling and foundation system of the structure was defective, requiring substantial corrective work and resulting in a delay of the building's completion date as well as substantial expense to the appellants.

The trial of this cause was directed solely to the question of liability raised by the complaint. The issues before the court were complex and technical in nature, and the trial lasted some eight days. The transcript of testimony consumes almost 1,500 pages, and the record includes numerous trial exhibits, depositions and other documents.

In the final judgment, the trial judge specifically found no negligence on the part of Crain, no breach of duty owed to either of the appellants and no act or omission on the part of Crain's representatives which proximately caused the damage alleged by the appellants.

In reaching this determination, the court rendered certain factual findings based upon its interpretation of the evidence. First, the court noted that negligence was asserted against Crain based on the engineers' redesign of piling under "pile caps" in the foundation system. The redesign eliminated certain steel reinforcing cages and casings from the piles.

However, the court found that the alteration was reasonable in light of subsurface information provided to the engineers by the general contractor, directly and through subcontractors, and upon which the engineers relied.

From the evidence adduced in the record, this subsurface information pertained to the level of a shelf of oolitic limestone. Initial soil borings which Crain caused to be made by another engineering firm, Ardaman & Associates, indicated that the rock formation was farther beneath the surface than was ultimately indicated to Crain following jobsite excavations.

Based in part on the initial soil findings, Crain devised plans and specifications for the building to rest on four "pile caps" which would be supported by several hundred piles.[1] The piles were originally designed to be reinforced by the steel casings and cages which were intended to provide lateral support for the piles from the force exerted by the superstructure as well as during the time in which further excavation was undertaken around the piles so that the pile caps could be constructed.

The appellee subsequently redesigned the plans to remove the steel reinforcing from the piles when the initial jobsite excavations undertaken by a subcontractor indicated that the limestone shelf was at a higher elevation than originally discovered by Ardaman's soil borings. Therefore, it was determined by Crain that the steel could be removed as a cost savings factor because the pilings would receive the necessary lateral support from the rock which previously was believed to be too low to provide support.

The evidence indicates further that in April, 1969, after Crain had redesigned the piling and foundation system and after the subcontractor had experienced excavation problems on the site, Ardaman was requested to make additional soil borings to determine the level of the rock. These *383 borings confirmed what was discovered by the first soil borings.

One of the main issues at trial was whether or not the engineers should have relied primarily on the soil borings or upon the information conveyed by the contractor and subcontractor concerning the rock level encountered during the excavations.

The trial court found that the engineers could reasonably rely upon the jobsite information, and that the evidence indicated that one of the reasons for the defective condition of the pilings was the over-excavation of the subsurface area by a subcontractor.

Further, the court found that the over-excavation, which rendered Crain's redesign ineffective, was not communicated to the engineers nor was the condition readily observable to Crain due to the presence of water in the foundation site.

After a review of the record, briefs and arguments of counsel in this case, it is our conclusion that the evidence supports the trial court's determination that Crain's alleged negligence was not the proximate cause of damage to the general contractor, appellant McCloskey & Co., Inc.

For purposes of this appeal, McCloskey has conceded that the court made a correct finding that the pile-cap areas had been over-excavated by one of its subcontractors causing the defective condition. Therefore, it is our conclusion that the general contractor has failed to prove negligence by Crain in relying upon the information furnished by the contractor, where the latter also did not communicate satisfactorily to the engineers that the pile-cap areas in question had been over-excavated.

We have considered all four points raised by the appellant McCloskey in its brief in light of controlling legal principles, and have concluded that no reversible error has been demonstrated by the general contractor. We find greater difficulty, however, with regard to the trial court's findings affecting the appellant-owner, Palm Bay Towers Corporation.

As a general rule, an engineer, like an architect, owes his employer a duty to exercise and apply his professional skill, ability and judgment in a manner which is reasonable and without neglect. Bayshore Development Co. v. Bonfoey, Fla. 1918, 75 Fla. 455, 78 So. 507; Pittman Construction Co. v. City of New Orleans, 178 So.2d 312 (La. App. 1965); Cf., A.R. Moyer, Inc. v. Graham, Fla. 1973, 285 So.2d 397.

In our view, the trial court in the case at bar reached an incorrect legal conclusion based upon the evidence in the record. Our review of the record convinces us that the engineers were negligent in several respects in the design, inspection and supervision of the construction of the piling and foundation system.

First, the record is clear that the City of Miami building department required full-time engineering control at the project site. Mr. Robert E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shepard v. City of Palatka
414 So. 2d 1077 (District Court of Appeal of Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
303 So. 2d 380, 1974 Fla. App. LEXIS 9040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palm-bay-towers-corporation-v-crain-crouse-inc-fladistctapp-1974.