Palladino v. Mayor of New York

10 N.Y.S. 66, 63 N.Y. Sup. Ct. 565, 31 N.Y. St. Rep. 775, 56 Hun 565, 1890 N.Y. Misc. LEXIS 1962
CourtNew York Supreme Court
DecidedMay 9, 1890
StatusPublished
Cited by1 cases

This text of 10 N.Y.S. 66 (Palladino v. Mayor of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palladino v. Mayor of New York, 10 N.Y.S. 66, 63 N.Y. Sup. Ct. 565, 31 N.Y. St. Rep. 775, 56 Hun 565, 1890 N.Y. Misc. LEXIS 1962 (N.Y. Super. Ct. 1890).

Opinion

Daniels, J.

The action was brought to recover the amount claimed to be unpaid for regulating and grading Fort George avenue from Tenth to Eleventh avenues, and setting curb-stones and flagging sidewalks therein. The work was let by a contract executed by the commissioner of public works and James H. Sullivan on or about the 17th of August, 1886; and after it had been in part performed, the contract was assigned to the plaintiff, who completed the work. His claim • consisted of two items. The first was for money retained by the city from the contract price, amounting to the sum of $432.02, and the other was for the value or cost of the material used for filling on the avenue to bring it up to the grade adopted for the improvement. It was claimed on behalf of the defendant that it was entitled still to re[67]*67tain the balance remaining unpaid upon the contract price of the work, because of proceedings taken to establish a lien against the contractor by other persons. But the evidence tended so directly to prove that this lien had been satisfied as to leave no substantial reason for doubting the right of the plaintiff to recover the amount of this balance; and accordingly the verdict of the jury in his favor for that sum, together with the interest upon it, should not lie unnecessarily disturbed.

But the claim made by the plaintiff for filling furnished by him to raise the street to the grade prescribed stands upon different grounds; for, by the terms of the proposals for the contract, no material of this description was included, or required to be furnished. But the entire work, as proposals were invited for it, consisted of earth and rock to be excavated, curb-stones to be furnished and set, and flagging stones to be furnished and laid. The amount of this work and materials was included in the published proposals; but no material for filling was mentioned, nor required to be estimated, which should be obtained or supplied by the person whose proposals should be accepted for the performance of the work. The work was ordered by a resolution adopted by the aldermen on the 11th, and approved by the mayor on the 18th, of May, 1885; and this work was directed to be done under the action of the commissioner of public works; and sealed estimates for this work were invited by a notice published, as the charter required that to be done, in the early part of July, 1886. When the resolution was approved by the mayor, the earth included within the line of the avenue to be regulated and graded had not been disturbed or removed. But after that, and in the year 1885, a large part of the earth in the avenue, which was capable of being used to fill the lower portions of it up to the prescribed grade, had been taken and carried away. This was alleged to have been done through the act, default, and neglect of the defendant, its officers and agents; and the plaintiff, as the assignee of the contract afterwards entered into for the grading and improvement of the avenue, insisted that the city was responsible to him for the removal of this earth. But it appeared by the evidence that it was not sore-moved by any person acting in its employment or under its authority, or even with its knowledge, but the persons who removed it were trespassers, having no right whatever to take it, and themselves alone liable for the wrong in this manner committed. Upon these facts, therefore, no right of compensation for the earth removed within the lines of the avenue existed against the defendant.

It was further insisted on behalf of the plaintiff that he was entitled under the contract to recover the value of the earth obtained and used by himself from other localities in filling the avenue up to its requisite grade. This claim proceeded upon the ground that it was mentioned in the specifications, which were inserted in the contract, that the “street which is above the grade line is to be excavated, and such and so much of the material excavated as may be fit for the purpose, and as may be necessary, shall be filled in those parts of the street which are below the grade lines, in the manner hereinafter provided. The material excavated not so used for filling shall be removed from the street. If the amount of material excavated that is fit for filling shall not be sufficient to regulate the street, the contractor shall furnish and supply material of proper kind and quality sufficient for the purpose; but only the difference between the total quantity of filling to finish grade and line as shown in cross-section, and the total quantity of excavation to the finished grade and line as shown in cross-section, with slopes in each case as herein described, will be considered as filling to be furnished, and as such to be paid for.” And the contract itself declared that, “for any work, the price of which is not specified in this contract, the provisions herein contained in relation to work not provided for in this contract shall apply.” But no other provision appears to have been inserted in the contract relating to this sub[68]*68ject, beyond that which was made a part of the specification; and, while the difference in the quantity of filling exceeding that supplied by the earth taken from the avenue itself is stated to be considered as filling to be furnished, and as such to be paid for, there is yet no provision in the contract binding the defendant to make such payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palladino v. Mayor of New York
12 N.Y.S. 955 (New York Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
10 N.Y.S. 66, 63 N.Y. Sup. Ct. 565, 31 N.Y. St. Rep. 775, 56 Hun 565, 1890 N.Y. Misc. LEXIS 1962, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palladino-v-mayor-of-new-york-nysupct-1890.