Pall Corporation v. Cleanspace Modular, LLC

District Court, S.D. New York·Decided November 9, 2023·No. 1:23-cv-02082·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK PALL CORPORATION, Plaintiff, -against- Case No. 1:23-cv-02082 CLEANSPACE MODULAR, LLC, OPINION AND ORDER Defendant.

JENNIFER L. ROCHON, United States District Judge: Plaintiff Pall Corporation (“Plaintiff” or “Pall”) filed this action against Defendant CleanSpace Modular, LLC (“Defendant” or “CleanSpace”) alleging negligent misrepresentation (“Count I”), breach of contract (“Count II”), breach of the implied covenant of good faith and fair dealing (“Count III”), and unjust enrichment (“Count IV”). ECF No. 1 (“Compl.”) ¶¶ 44-70. Plaintiff “demands a trial by jury on all issues triable by a jury as a matter of right.” Id. at 9. Defendant now moves under Federal Rule of Civil Procedure (“Rule”) 12(b)(6) to dismiss Counts I, III, and IV of the Complaint. ECF No. 20 (“Dismiss Br.”). Defendant also moves under Rule 39(a) to strike Plaintiff’s jury demand. ECF No. 22 (“Strike Br.”). Plaintiff opposes both motions. ECF Nos. 26 (“Strike Opp.”), 27 (“Dismiss Opp.”). Plaintiff also requests leave to amend if the Court dismisses any of its claims. Dismiss Opp. at 11. For the reasons given below, the Court GRANTS Defendant’s motion to dismiss Counts I and Count III, DENIES Defendant’s motion to dismiss Count IV, DENIES Defendant’s motion to strike Plaintiff’s jury demand without prejudice, and GRANTS Plaintiff’s request for leave to amend. BACKGROUND The following facts are taken from the Complaint, the Master Services Agreement (the “MSA”), and the Statement of Work (the “SOW”); the latter two documents are attached to the Complaint. See Goel v. Bunge, Ltd., 820 F.3d 554, 559 (2d Cir. 2016) (on a motion to dismiss, a court may consider documents appended to the complaint). The Court assumes the Complaint’s allegations to be true for the purpose of deciding Defendant’s motion and

construes them in the light most favorable to Plaintiff. See Grullon v. City of New Haven, 720 F.3d 133, 139 (2d Cir. 2013). On December 17, 2020, Plaintiff and Defendant entered into the MSA. Compl. ¶ 6; see ECF No. 1-1 (“MSA”). The MSA says that the services provided by Defendant “will be described in a statement of work substantially in the form attached” to the MSA. MSA § 1.2. Plaintiff and Defendant executed the SOW on May 4, 2021. Compl. ¶ 8; see ECF No. 1-2 (“SOW”). The parties treat the MSA and the SOW as a single “Timonium Contract,” and the Court will do the same. See Compl. ¶ 10; Dismiss Br. at 2. The parties agree that the Timonium Contract is valid and binding. See Compl. ¶ 10; Dismiss Br. at 10 n.2. The Timonium Contract provided for the construction of two “cleanroom[s],” SOW

§ 1.2, which are “room[s] or enclosure[s] in which dust, microorganisms, and other contaminants are eliminated or reduced to very low levels, esp[ecially] for the purpose of manufacturing electronic components and some types of medical equipment,” Clean room, Oxford English Dictionary, https://www.oed.com/dictionary/clean-room_n (last visited Oct. 28, 2023). Defendant agreed “to design, procure materials for, and construct two cleanrooms in accordance with [Plaintiff’s] guidelines, specifications, and requirements, specifically the temperatures of the two cleanrooms.” Compl. ¶ 12. In exchange, Plaintiff promised to pay Defendant $2,650,000. Id. ¶ 13. The agreed-upon deadline for completion was May 7, 2021. Id. ¶ 14. The MSA also contained the following clause: 16.17. Waiver of Jury Trial. EACH PARTY HEREBY IRREVOCABLY WAIVES ALL RIGHT TO TRIAL BY JURY IN ANY ACTION, PROCEEDING OR COUNTERCLAIM ARISING OUT OF OR RELATING TO THIS AGREEMENT. MSA § 16.17. Defendant “failed to construct the two cleanrooms, as required by the Timonium Contract.” Compl. ¶ 15. Plaintiff attributes this failure to Defendant’s “poor project management,” “failure to obtain the proper permits required for the cleanrooms,” and “failure to pay its vendors.” Id. ¶ 16. Defendant also installed faulty heating, ventilation, and air condition (“HVAC”) systems in both cleanrooms, which “interfered with both cleanrooms’ respective temperature regulation.” Id. ¶ 17. Plaintiff “attempted to mitigate the respective damages for both inoperable cleanrooms,” id. ¶ 20, at a total cost exceeding $420,000, id. ¶ 21. Defective cleanrooms are not the only asserted source of frustration for Plaintiff. Defendant “placed numerous charges wholly unrelated to the Timonium Contract on [Plaintiff’s] credit card.” Id. ¶ 22. On September 22, 2021, Defendant “charged [Plaintiff’s] credit card numerous times” for a total of $1,045,000. Id. ¶ 25. Plaintiff says that it cannot reconcile these charges (the “Credit-Card Charges”) with any valid charges related to the Timonium Contract. Id. ¶ 26. Further, on November 24, 2021, Defendant “informed [Plaintiff] that it had received invoices from EquipmentShare, a third-party vendor that provided chilling equipment which was being used to construct the two cleanrooms.” Id. ¶ 27. The total amount due on the invoices was $79,734.28. Id. ¶ 28. Despite Plaintiff telling Defendant that Plaintiff would pay EquipmentShare directly, Defendant submitted the invoices to Plaintiff. See id. ¶¶ 29-30. Plaintiff paid Defendant for the full amount of the invoices (the “Erroneous Reimbursement”). Id. ¶ 31. When EquipmentShare submitted the same invoices to Plaintiff, Plaintiff also paid EquipmentShare. Id. ¶¶ 32-33. When Plaintiff realized its mistake, it asked Defendant to return the Erroneous Reimbursement. Id. ¶ 34. Defendant initially told Plaintiff that it had transferred the money to EquipmentShare. Id. ¶ 35. Months later, Defendant claimed that the

Credit-Card Charges and the Erroneous Reimbursement “resulted from valid project costs associated with the Timonium Contract.” Id. ¶ 40. Defendant has not returned this money to Plaintiff. See id. ¶¶ 37, 39. On May 21, 2022, Plaintiff sent Defendant a Notice of Breach and Reservation of Rights. Id. ¶ 41. Defendant acknowledged receipt two days later. Id. ¶ 43. Plaintiff initiated this lawsuit on March 10, 2023. See generally id. Defendant filed its partial motion to dismiss and its motion to strike on May 12, 2023. Dismiss Br.; Strike Br. Plaintiff filed its oppositions to both motions on May 25, 2023. Dismiss Opp.; Strike Opp. Defendant did not submit a reply brief in support of either of its motions.

LEGAL STANDARD “[F]ederal courts sitting in diversity apply state substantive law and federal procedural law.” Gasperini v. Ctr. for Humans., Inc., 518 U.S. 415, 427 (1996); accord Sarkees v. E.I. Dupont De Nemours & Co., 15 F.4th 584, 588 (2d Cir. 2021). The parties agree that New York provides the applicable state substantive law. See Dismiss Br. at 4; Strike Opp. at 4. With respect to procedure, to survive a motion to dismiss under Rule 12(b)(6), “a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)); accord Buon v. Spindler, 65 F.4th 64, 76 (2d Cir. 2023). The Court accepts all well-pleaded factual allegations as true and draws all reasonable inferences in favor of the plaintiff. See Grullon, 720 F.3d at 139. Still, a complaint must allege “more than a sheer possibility that a defendant has acted unlawfully” and more than “facts that are ‘merely consistent with’ a defendant’s liability.” Iqbal, 556 U.S. at 678 (quoting Twombly, 550 U.S. at 557).

Free access — add to your briefcase to read the full text and ask questions with AI

Pall Corporation v. Cleanspace Modular, LLC, (S.D.N.Y. 2023).

Pall Corporation v. Cleanspace Modular, LLC (Pall Corporation v. Cleanspace Modular, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Williams v. Citigroup Inc.
659 F.3d 208 (Second Circuit, 2011)
Celia Henry v. Daytop Village, Inc.
42 F.3d 89 (Second Circuit, 1994)
Grullon v. City of New Haven
720 F.3d 133 (Second Circuit, 2013)
Cruz v. FXDirectDealer, LLC
720 F.3d 115 (Second Circuit, 2013)
J.A.O. Acquisition Corp. v. Stavitsky
863 N.E.2d 585 (New York Court of Appeals, 2007)
511 West 232nd Owners Corp. v. Jennifer Realty Co.
773 N.E.2d 496 (New York Court of Appeals, 2002)
Fadem v. Ford Motor Co.
352 F. Supp. 2d 501 (S.D. New York, 2005)
Corsello v. Verizon New York, Inc.
967 N.E.2d 1177 (New York Court of Appeals, 2012)
L-7 Designs, Inc. v. Old Navy, LLC
647 F.3d 419 (Second Circuit, 2011)
Gasperini v. Center for Humanities, Inc.
518 U.S. 415 (Supreme Court, 1996)
IDT Corp. v. Morgan Stanley Dean Witter & Co.
907 N.E.2d 268 (New York Court of Appeals, 2009)
Board of Managers of Beacon Tower Condominium v. 85 Adams Street, LLC
136 A.D.3d 680 (Appellate Division of the Supreme Court of New York, 2016)
Ball v. . Shepard
95 N.E. 719 (New York Court of Appeals, 1911)
TJJK Props., LLC v. A.E.Y. Eng'g, D.P.C.
2020 NY Slip Op 4683 (Appellate Division of the Supreme Court of New York, 2020)