FRIEDMAN, Judge.
Carmen Paliotta, an individual t/d/b/a Carmen Paliotta Contracting Company (Paliotta) appeals from an order of the Board of Claims (Board) finding in favor of Paliotta and against the Department of Transportation (Department) in the amount of $144,105.86 with six per cent interest from May 10, 1998. The Department has filed a cross appeal.
On or about May 23, 1991, the Department sought bids for a contract to improve a section of State Route 30 in Beaver County (the Project). In a letter dated June 27, 1991, the Department declared Paliotta the lowest responsive bidder. Pa-liotta was to begin work on the Project on July 29, 1991 and was to complete the Project ninety-two calendar days later on October 28, 1991. (Findings of Fact, Nos. 8-9,12.)
The start of the Project was delayed because the state budget for the 1991-1992 fiscal year was not signed into law until August 4, 1991. Because of this delay, the Department did not officially award the contract to Paliotta until August 7,1991. The parties executed the contract in the weeks following August 7, 1991, and the Department held a pre-construction conference on August 30, 1991. On September 4, 1991, the Department issued a revised work schedule, increasing the duration of the Project from ninety-two calendar days to 268 calendar days because of a “winter shutdown.” (Findings of Fact, Nos. 14,16-19, 21.)
The Department gave Paliotta a “notice to proceed date” of September 16, 1991. Hoping to complete the Project as quickly as possible, Paliotta began site preparation work on'September 9, 1991. On September 11, 1991, Paliotta realized that the Project could not be built as planned because of a design defect. The Department modified the design to correct the problem, thereby causing Paliotta to incur unanticipated construction costs. (Findings of Fact, Nos. 40 41, 50-71.)
Another problem arose later in the fall of 1991. The Department had represented to Paliotta that Duquesne Light Company would relocate its utility poles so that Pali-otta could widen the road pursuant to the Project’s work schedule. However, Du-quesne Light Company had not performed the work. When Paliotta proposed that he move ahead with the widening of the road by constructing the concrete curb gutter behind the existing utility poles, the Department rejected the proposal. As a result, Paliotta was not able to begin widening the road and constructing the concrete curb gutter until May 1992. (Findings of Fact, Nos. 72-73, 76, 82, 84.)
Upon completion of the Project, Paliotta filed a complaint with the Board seeking damages from the Department for increased construction costs caused by the delays and design flaw. The Board held hearings and, based on the evidence pre
sented, awarded Paliotta damages in the amount of $144,105.86 with six per cent interest from May 10,1993.
I. Paliotta’s Appeal
A. Extended Home Office Overhead
On appeal to this court, Paliotta first argues that, based on the Eichleay formula,
he is entitled to additional damages for extended home office overhead for the period of time beyond the original ninety-two days duration of the Project.
We disagree.
Section 111.02 of the Department’s Publication 408, which governs delay claims against the Department,
states that home office overhead “cannot be‘included in any delay claim against the Department.” Section 111.04(d) of Publication 408 (emphasis added) states:
Only expenses for extra non-salaried labor, material, and equipment costs will be considered by the Department in the event it is determined that operations were delayed by the Department.
To these costs will be added 10% to cover allocable home office overhead.
Likewise, in the event a delay claim is filed with the Board of Claims, only the foregoing expenses may be claimed.
Thus, Paliotta may recover delay damages for home office overhead
only
as ten per cent of his extra costs for non-salaried labor, material and equipment.
That is
not
what Paliotta seeks here. Rather, Pa-liotta seeks additional damages for home office overhead based on the Eichleay formula. Such a claim is prohibited by section 111.02 of Publication 408.
Accordingly, we affirm the Board’s denial of Paliotta’s extended home office overhead claim.
B. Extended Equipment Costs
Next, Paliotta argues that he is entitled to additional damages in the amount of $56,636.61 for equipment “standby” costs for the period of time beyond the original ninety-two-day duration of the Project. Paliotta maintains that the Board should have accepted his estimate of $56,636.61 as a reasonable substitute for evidence of his actual equipment costs. We disagree.
The final paragraph of section 111.04(d) of Publication 408 (emphasis added) states as follows:
When measuring additional equipment expenses (i.e. ownership expenses) arising as a direct result of a delay caused by the Department,
do not use in any way the Blue Book
or any other rental rate book similar thereto.
Use actual records
kept in the usual course of business, and measure increased ownership expenses pursuant to generally accepted accounting principles.
Paliotta’s expert, Mark M. Gleason, C.P.A., testified that, in calculating the extended equipment costs claim, he intended to “quantify Paliotta’s loss of value on [his] equipment.” (R.R. at 198a; N.T. at 659.) Gleason explained that, because the equipment was idle, Paliotta could not generate revenue to recover the depreciation of the equipment.
(R.R. at 199a; N.T. at 661.) Inasmuch as Paliotta’s extended equipment costs claim involves a recovery of depreciation, it involves an “ownership expense.”
Thus, section 111.04(d) of Publication 408 applies here.
Although section 111.04(d) requires that contractors use actual business records to support their claims for equipment ownership expenses, the Board found that Paliot-ta could not provide with any degree of reasonable accuracy his actual equipment costs for the period of the delay. (Findings of Fact, No. 178.) Paliotta does not dispute that finding. Paliotta merely asserts that he “did not maintain [his] accounting records in such a manner that [his actual equipment costs were] ... retrievable.” (Paliotta’s brief at 26.) Thus, in presenting his claim for extended equipment costs, Paliotta failed to comply with section 111.04(d) of Publication 408.
Accordingly, we affirm the Board’s denial of damages for extended equipment costs.
C. Curb Gutters
Free access — add to your briefcase to read the full text and ask questions with AI
FRIEDMAN, Judge.
Carmen Paliotta, an individual t/d/b/a Carmen Paliotta Contracting Company (Paliotta) appeals from an order of the Board of Claims (Board) finding in favor of Paliotta and against the Department of Transportation (Department) in the amount of $144,105.86 with six per cent interest from May 10, 1998. The Department has filed a cross appeal.
On or about May 23, 1991, the Department sought bids for a contract to improve a section of State Route 30 in Beaver County (the Project). In a letter dated June 27, 1991, the Department declared Paliotta the lowest responsive bidder. Pa-liotta was to begin work on the Project on July 29, 1991 and was to complete the Project ninety-two calendar days later on October 28, 1991. (Findings of Fact, Nos. 8-9,12.)
The start of the Project was delayed because the state budget for the 1991-1992 fiscal year was not signed into law until August 4, 1991. Because of this delay, the Department did not officially award the contract to Paliotta until August 7,1991. The parties executed the contract in the weeks following August 7, 1991, and the Department held a pre-construction conference on August 30, 1991. On September 4, 1991, the Department issued a revised work schedule, increasing the duration of the Project from ninety-two calendar days to 268 calendar days because of a “winter shutdown.” (Findings of Fact, Nos. 14,16-19, 21.)
The Department gave Paliotta a “notice to proceed date” of September 16, 1991. Hoping to complete the Project as quickly as possible, Paliotta began site preparation work on'September 9, 1991. On September 11, 1991, Paliotta realized that the Project could not be built as planned because of a design defect. The Department modified the design to correct the problem, thereby causing Paliotta to incur unanticipated construction costs. (Findings of Fact, Nos. 40 41, 50-71.)
Another problem arose later in the fall of 1991. The Department had represented to Paliotta that Duquesne Light Company would relocate its utility poles so that Pali-otta could widen the road pursuant to the Project’s work schedule. However, Du-quesne Light Company had not performed the work. When Paliotta proposed that he move ahead with the widening of the road by constructing the concrete curb gutter behind the existing utility poles, the Department rejected the proposal. As a result, Paliotta was not able to begin widening the road and constructing the concrete curb gutter until May 1992. (Findings of Fact, Nos. 72-73, 76, 82, 84.)
Upon completion of the Project, Paliotta filed a complaint with the Board seeking damages from the Department for increased construction costs caused by the delays and design flaw. The Board held hearings and, based on the evidence pre
sented, awarded Paliotta damages in the amount of $144,105.86 with six per cent interest from May 10,1993.
I. Paliotta’s Appeal
A. Extended Home Office Overhead
On appeal to this court, Paliotta first argues that, based on the Eichleay formula,
he is entitled to additional damages for extended home office overhead for the period of time beyond the original ninety-two days duration of the Project.
We disagree.
Section 111.02 of the Department’s Publication 408, which governs delay claims against the Department,
states that home office overhead “cannot be‘included in any delay claim against the Department.” Section 111.04(d) of Publication 408 (emphasis added) states:
Only expenses for extra non-salaried labor, material, and equipment costs will be considered by the Department in the event it is determined that operations were delayed by the Department.
To these costs will be added 10% to cover allocable home office overhead.
Likewise, in the event a delay claim is filed with the Board of Claims, only the foregoing expenses may be claimed.
Thus, Paliotta may recover delay damages for home office overhead
only
as ten per cent of his extra costs for non-salaried labor, material and equipment.
That is
not
what Paliotta seeks here. Rather, Pa-liotta seeks additional damages for home office overhead based on the Eichleay formula. Such a claim is prohibited by section 111.02 of Publication 408.
Accordingly, we affirm the Board’s denial of Paliotta’s extended home office overhead claim.
B. Extended Equipment Costs
Next, Paliotta argues that he is entitled to additional damages in the amount of $56,636.61 for equipment “standby” costs for the period of time beyond the original ninety-two-day duration of the Project. Paliotta maintains that the Board should have accepted his estimate of $56,636.61 as a reasonable substitute for evidence of his actual equipment costs. We disagree.
The final paragraph of section 111.04(d) of Publication 408 (emphasis added) states as follows:
When measuring additional equipment expenses (i.e. ownership expenses) arising as a direct result of a delay caused by the Department,
do not use in any way the Blue Book
or any other rental rate book similar thereto.
Use actual records
kept in the usual course of business, and measure increased ownership expenses pursuant to generally accepted accounting principles.
Paliotta’s expert, Mark M. Gleason, C.P.A., testified that, in calculating the extended equipment costs claim, he intended to “quantify Paliotta’s loss of value on [his] equipment.” (R.R. at 198a; N.T. at 659.) Gleason explained that, because the equipment was idle, Paliotta could not generate revenue to recover the depreciation of the equipment.
(R.R. at 199a; N.T. at 661.) Inasmuch as Paliotta’s extended equipment costs claim involves a recovery of depreciation, it involves an “ownership expense.”
Thus, section 111.04(d) of Publication 408 applies here.
Although section 111.04(d) requires that contractors use actual business records to support their claims for equipment ownership expenses, the Board found that Paliot-ta could not provide with any degree of reasonable accuracy his actual equipment costs for the period of the delay. (Findings of Fact, No. 178.) Paliotta does not dispute that finding. Paliotta merely asserts that he “did not maintain [his] accounting records in such a manner that [his actual equipment costs were] ... retrievable.” (Paliotta’s brief at 26.) Thus, in presenting his claim for extended equipment costs, Paliotta failed to comply with section 111.04(d) of Publication 408.
Accordingly, we affirm the Board’s denial of damages for extended equipment costs.
C. Curb Gutters
Paliotta also argues that he is entitled to additional damages in the amount of $32,949.53 for the Department’s interference with his construction of the curb and gutters in the fall of 1991. In this regard, the Board made the following relevant findings:
77. Paliotta testified that he originally bid to do most of the curb gutter, 95% of it, utilizing a slip form subcontractor.[
] Mr. Tribuzio [
] testified that they were looking into slip forming the curb gutter and [that they] contacted Highway Pav
ing by phone early in the job [to discuss the matter].... (N.T. 90-93, 270, 307-312)
78. In the [fall] of 1991, Paliotta proposed starting the curb gutters in late [fall] 1991 and completing [them] in the [spring] of 1992... .[
]
79. The Department rejected this idea....
86. At the time of the bid, Mr. Payne [
] opined that Paliotta’s estimate of constructing 225 feet of curb gutter per day was reasonable[
] and was based on Paliotta’s using hand-forming construction methodology.[
] (N.T. 382-383)
87. Based on his review of both Paliot-ta’s and the Department’s Project diaries, Payne concluded that as a result of using the methodology required by the Department,[
] Paliotta poured concrete for curb gutter construction on
26 days during the Project
.... (N.T. 388-390)
110. This [curb gutter] claim is based on a supposed production rate of ... 225 linear feet per day. (N.T. 382, 536)
111. Mr. Tribuzio established that Pali-otta purchased only 300 linear feet (L.F.) of forms for the curb gutter construction. He admitted on cross that the sequence they planned was [to] set 200 L.F. for a pour in the morning.[
] In the afternoon they could set 100 L.F. of forms plus what could be stripped on hot days[] from the [morning] pour. Mr. Tribuzio, on cross, admitted that 225 L.F. per day when you set 200 L.F. of forms was a speculative number which didn’t happen all the time. Depending on [conditions] it could be more or less.
A lot of times you got less [than] 225 L.F. (N.T. 308-309)
113. Based on Mr. Payne’s opinion and using 225 L.F. as planned production, Mr. Gleason compared the 12.3 days of concrete crew labor which would have been required using Paliotta’s planned methodology[
] and compared it to the 26 actual days of concrete crew work which was actually required. (N.T. 535-538; Exhibit P-Demo 12)
116. The cost analysis presented at trial did not establish what all the cost would have been if the Department had allowed Paliotta to build the curb gutter in the fall of 1991.[
] There was no bidding documentation that the [hoped] for 225 L.F. per day was used at the time of bid,[
] no slipform quotes[
] and Mr. Tribuzio could not establish with any degree of certainty that 225 L.F. of curb gutter could be achieved using 300 L.F. of forms. The Board finds that the damages of $32,949.53 are not supported by any reasonable degree of certainty by the facts presented at trial. (Record)
(Findings of Fact, Nos. 77-79, 86-87, 110-11, 113, 116.) (Emphasis in original.) Having made these findings, the Board made the following relevant conclusions of law:
6. In [the] absence of countervailing expert testimony[
] the Board should accept as true the expert testimony of Mr. Payne and Mr. Gleason.
10. The Department owes Paliotta inefficiency damages resulting from its improper interference with Paliotta’s selection of means and methods of the curb gutters....
11. Mr. Gleason used a reasonably reliable methodology in determining Paliot-ta’s damages regarding [element 6] of the claim.
(Conclusions of Law, Nos. 6, 10-11.) (Citation omitted.) Element six of Paliotta’s claim is the concrete curb gutter portion of the claim. (Findings of Fact, No. 174.)
After making the above findings of fact and conclusions of law, the Board held that Paliotta was entitled to compensation from the Department for interference with Pali-otta’s means and method of construction. However, the Board did
not
award damages to Paliotta for the Department’s interference with curb gutter construction in the fall of 1991. The Board explained that Paliotta failed to present sufficient evidence to show that his “original plan for the curb gutter construction could have
been achieved at the initial desired rate using the planned equipment.” (Board’s op. at 27.) We disagree with the Board.
Paliotta’s “original plan” was to construct nearly all of the curb gutters in one phase using a “slip form machine.” According to the credible expert testimony of Payne, a “slip form machine” could have produced much more than 225 linear feet of curb gutter per day. Payne also testified credibly that a production rate of 225 linear feet per day was reasonable even in situations where the curb gutters would be “hand formed.” Thus, Paliotta presented sufficient evidence to show that he could have constructed 225 linear feet of curb gutter per day in the fall of 1991.
This means that the record and the facts support Gleason’s $32,949.53 estimate for curb gutter damages.
Accordingly, we reverse the Board’s denial of damages for the Department’s interference with Paliotta’s construction of the curb gutters.
D. Interest
Finally, Paliotta argues that he is entitled to interest on the total amount of damages from April 6,1993, the date when Paliotta filed a detailed accounting of the claim with the Department.
“Interest is awarded from the date on which the obligation to pay the amount due under the contract arises, usually the date when the contract is fully performed.”
Department of Transportation v. Anjo Construction Co.,
666 A.2d 753, 760 (Pa.Cmwlth.1995). “Hence, the date from which interest on an award must be calculated is the date on which the Commonwealth’s duty to pay arises, not the date the complaint is filed with the Board.”
Id.
Interest is properly awarded from the date the contractor presents its claim to the Department.
Id.
There is no dispute here that Paliotta filed a detailed accounting of the claim with the Department on April 6, 1993; thus, under
Anjo,
Paliotta should receive interest from that date. Accordingly, we modify the Board’s award to allow interest on the total amount of damages from April 6,1993.
II. Department’s Appeal
The Department argues that the Board erred in awarding damages for extended “maintenance and protection of traffic” costs based on a pro rata formula instead of Paliotta’s actual costs. We disagree.
The Board found that a subcontractor, Marlane Maintenance, Inc. (Marlane), provided for the maintenance and protection of traffic during the period of construction. (Findings of Fact, No. 128.) Marlane had agreed to provide its services for ninety-two days; however, Marlane actually provided services for 368 days. (Findings of Fact, Nos. 129-30.) At the conclusion of the Project, Marlane sought extra compensation from Paliotta. On April 6, 1992, the Department agreed to compensate Paliotta for extended maintenance and protection of traffic on a pro rata basis in accordance with the terms of the contract. (Findings of Fact, No. 133.) On November 12, 1996,
Marlane settled its claim against Paliotta for $22,958.47. (Findings of Fact, No. 131.) Gleason testified that the settlement did not represent the entire cost to Paliot-ta for extended maintenance and protection of traffic. (Findings of Fact, No. 132.) Therefore, Paliotta sought $41,238.00 in damages from the Department, a figure that Gleason calculated on a pro rata basis. (Findings of Fact, No. 134.) The Board found that this figure was proper under the contract and awarded that amount in damages. (Findings of Fact, No. 135.)
The Department’s argument is that, under the original contract, the Department is hable only for the actual costs incurred by the contractor for a delay caused by the Department, and, here, Paliotta’s actual costs were only $22,958.47. However, the Department
modified
the original contract when it agreed to compensate Paliotta for extended traffic control on a pro rata basis, and the Board found that $22,958.47 does
not
represent Paliotta’s actual cost for extended traffic control. Thus, the Board did not err in basing its award on Gleason’s pro rata calculation.
Accordingly, we affirm the Board’s award of damages for extended maintenance and protection of traffic on a pro rata basis.
ORDER
AND NOW, this 22 nd day of December, 1999, that portion of the Board of Claim’s (Board) order denying damages to Carmen Paliotta, an individual t/d/b/a Carmen Pali-otta Contracting Company (Paliotta), for interference with the construction of curb gutters is reversed. That portion of the Board’s order awarding interest on damages from May 10, 1993 is modified to allow interest on damages from April 6, 1993. In all other respects, the Board’s order is affirmed.