Paliotta v. Department of Transportation

750 A.2d 388
CourtCommonwealth Court of Pennsylvania
DecidedApril 14, 2000
StatusPublished

This text of 750 A.2d 388 (Paliotta v. Department of Transportation) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paliotta v. Department of Transportation, 750 A.2d 388 (Pa. Ct. App. 2000).

Opinion

FRIEDMAN, Judge.

Carmen Paliotta, an individual t/d/b/a Carmen Paliotta Contracting Company (Paliotta) appeals from an order of the Board of Claims (Board) finding in favor of Paliotta and against the Department of Transportation (Department) in the amount of $144,105.86 with six per cent interest from May 10, 1998. The Department has filed a cross appeal.

On or about May 23, 1991, the Department sought bids for a contract to improve a section of State Route 30 in Beaver County (the Project). In a letter dated June 27, 1991, the Department declared Paliotta the lowest responsive bidder. Pa-liotta was to begin work on the Project on July 29, 1991 and was to complete the Project ninety-two calendar days later on October 28, 1991. (Findings of Fact, Nos. 8-9,12.)

The start of the Project was delayed because the state budget for the 1991-1992 fiscal year was not signed into law until August 4, 1991. Because of this delay, the Department did not officially award the contract to Paliotta until August 7,1991. The parties executed the contract in the weeks following August 7, 1991, and the Department held a pre-construction conference on August 30, 1991. On September 4, 1991, the Department issued a revised work schedule, increasing the duration of the Project from ninety-two calendar days to 268 calendar days because of a “winter shutdown.” (Findings of Fact, Nos. 14,16-19, 21.)

The Department gave Paliotta a “notice to proceed date” of September 16, 1991. Hoping to complete the Project as quickly as possible, Paliotta began site preparation work on'September 9, 1991. On September 11, 1991, Paliotta realized that the Project could not be built as planned because of a design defect. The Department modified the design to correct the problem, thereby causing Paliotta to incur unanticipated construction costs. (Findings of Fact, Nos. 40 41, 50-71.)

Another problem arose later in the fall of 1991. The Department had represented to Paliotta that Duquesne Light Company would relocate its utility poles so that Pali-otta could widen the road pursuant to the Project’s work schedule. However, Du-quesne Light Company had not performed the work. When Paliotta proposed that he move ahead with the widening of the road by constructing the concrete curb gutter behind the existing utility poles, the Department rejected the proposal. As a result, Paliotta was not able to begin widening the road and constructing the concrete curb gutter until May 1992. (Findings of Fact, Nos. 72-73, 76, 82, 84.)

Upon completion of the Project, Paliotta filed a complaint with the Board seeking damages from the Department for increased construction costs caused by the delays and design flaw. The Board held hearings and, based on the evidence pre *390 sented, awarded Paliotta damages in the amount of $144,105.86 with six per cent interest from May 10,1993.

I. Paliotta’s Appeal

A. Extended Home Office Overhead

On appeal to this court, Paliotta first argues that, based on the Eichleay formula, 1 he is entitled to additional damages for extended home office overhead for the period of time beyond the original ninety-two days duration of the Project. 2 We disagree.

Section 111.02 of the Department’s Publication 408, which governs delay claims against the Department, 3 states that home office overhead “cannot be‘included in any delay claim against the Department.” Section 111.04(d) of Publication 408 (emphasis added) states:

Only expenses for extra non-salaried labor, material, and equipment costs will be considered by the Department in the event it is determined that operations were delayed by the Department. To these costs will be added 10% to cover allocable home office overhead. Likewise, in the event a delay claim is filed with the Board of Claims, only the foregoing expenses may be claimed.

Thus, Paliotta may recover delay damages for home office overhead only as ten per cent of his extra costs for non-salaried labor, material and equipment. 4 That is not what Paliotta seeks here. Rather, Pa-liotta seeks additional damages for home office overhead based on the Eichleay formula. Such a claim is prohibited by section 111.02 of Publication 408.

Accordingly, we affirm the Board’s denial of Paliotta’s extended home office overhead claim.

B. Extended Equipment Costs

Next, Paliotta argues that he is entitled to additional damages in the amount of $56,636.61 for equipment “standby” costs for the period of time beyond the original ninety-two-day duration of the Project. Paliotta maintains that the Board should have accepted his estimate of $56,636.61 as a reasonable substitute for evidence of his actual equipment costs. We disagree.

The final paragraph of section 111.04(d) of Publication 408 (emphasis added) states as follows:

*391 When measuring additional equipment expenses (i.e. ownership expenses) arising as a direct result of a delay caused by the Department, do not use in any way the Blue Book or any other rental rate book similar thereto. Use actual records kept in the usual course of business, and measure increased ownership expenses pursuant to generally accepted accounting principles.

Paliotta’s expert, Mark M. Gleason, C.P.A., testified that, in calculating the extended equipment costs claim, he intended to “quantify Paliotta’s loss of value on [his] equipment.” (R.R. at 198a; N.T. at 659.) Gleason explained that, because the equipment was idle, Paliotta could not generate revenue to recover the depreciation of the equipment. 5 (R.R. at 199a; N.T. at 661.) Inasmuch as Paliotta’s extended equipment costs claim involves a recovery of depreciation, it involves an “ownership expense.” 6 Thus, section 111.04(d) of Publication 408 applies here.

Although section 111.04(d) requires that contractors use actual business records to support their claims for equipment ownership expenses, the Board found that Paliot-ta could not provide with any degree of reasonable accuracy his actual equipment costs for the period of the delay. (Findings of Fact, No. 178.) Paliotta does not dispute that finding. Paliotta merely asserts that he “did not maintain [his] accounting records in such a manner that [his actual equipment costs were] ... retrievable.” (Paliotta’s brief at 26.) Thus, in presenting his claim for extended equipment costs, Paliotta failed to comply with section 111.04(d) of Publication 408. 7

Accordingly, we affirm the Board’s denial of damages for extended equipment costs.

C. Curb Gutters

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green Construction Co. v. Department of Transportation
643 A.2d 1129 (Commonwealth Court of Pennsylvania, 1994)
Department of Transportation v. Anjo Construction Co.
666 A.2d 753 (Commonwealth Court of Pennsylvania, 1995)
Commonwealth, Department of Transportation v. Burrell Construction & Supply Co.
534 A.2d 585 (Commonwealth Court of Pennsylvania, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
750 A.2d 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paliotta-v-department-of-transportation-pacommwct-2000.