Page & Wirtz Construction Co. v. Van Doran Bri-Tico Co.

432 S.W.2d 731, 1968 Tex. App. LEXIS 2559
CourtCourt of Appeals of Texas
DecidedJune 3, 1968
Docket7851
StatusPublished
Cited by18 cases

This text of 432 S.W.2d 731 (Page & Wirtz Construction Co. v. Van Doran Bri-Tico Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page & Wirtz Construction Co. v. Van Doran Bri-Tico Co., 432 S.W.2d 731, 1968 Tex. App. LEXIS 2559 (Tex. Ct. App. 1968).

Opinion

CHAPMAN, Justice.

In the trial court Van Doran Bri-Tico Co., a partnership composed of L. E. Van Doran and S. O. Garner, hereinafter called Van Doran, sued Page & Wirtz Construction Co., a partnership composed of Walter E. Wirtz, his son, Jack Wirtz, and J. C. Page, 1 for prospective profits which it alleges it would have made as subcontractors for the performance of masonry work on Units A & D of Western Plaza Shopping Center in Amarillo under general contractors Page & Wirtz, except for breach by Page & Wirtz of the subcontract.

In April, 1966, certain members of the Hedgecoke family in Amarillo doing business as partners were in the process of inviting bids for construction of two units of Western Plaza Shopping Center. Bidding of the general contractors was to be in to the Hedgecoke Estate by 2:00 P.M., May 12, 1966. Van Dora& submitted its subcontractor’s bid of $204,395.00 between 10:30 and 11:00 on the morning of May 12, 1966. At that hour Page & Wirtz already *733 had in its hands a masonry bid from Southwestern Bricklaying Company, which was about $9,000.00 in excess of the Van Doran bid. At approximately 1:00 P.M. on the same day Southwestern Bricklaying Company submitted another bid on the masonry work which was about $1,595.00 lower than the Van Doran bid.

Southwestern Bricklaying Company was later awarded the masonry contract and Van Doran filed this' Suit. The case was tried to the jury upon Special Issue No. I inquiring if Page & Wirtz “accepted” Van Doran’s bid for the masonry work on Units A & D of the Western Plaza Shopping Center and on Special Issue No. II inquiring as to the amount of net profit Van Doran would have realized in reasonable probability if it had been permitted to perform such masonry work. The word “accepted” as used in the first issue was defined as an expression of assent or agreement not conditioned on acceptance of the terms of the plaintiff’s bid by the Hedge-cokes. To the first issue the jury answered “yes” and to the inquiry concerning the net profits Van Doran would in reasonable probability have earned they answered $25,000.00.

After submitting its bid during the forenoon of May 12, 1966, Van Doran left the offices of Page & Wirtz but was still in the building talking to Wirtz’s son, Jack, when Walter E. Wirtz came out of his office and told J. C. Page to get Franklin Bottoms on the telephone immediately. The latter represents Southwestern Bricklaying Company, a competitor to Van Doran. Immediately after the statement just related Wirtz looked around and saw Van Doran, and knew he had overheard his request to get Bottoms on the telephone. Wirtz testified in the case there was an atmosphere of embarrassment because he thought Van Doran would think he was “peddling” his bid to -Bottoms, knowing Van Doran had accused others of doing so in the past. Van Doran testified, “ * * * I was pretty well shook up and left.” However, he called Wirtz by telephone about 4:00 that afternoon. He testified Wirtz told him, “ * * * this morning I made the biggest bust I ever made in my life” and “ * * * under existing conditions, I can do nothing but give you the job.”

“Q. And what did you say to that?
A. Well, Walter, now, as I understand it, if you get this j ob, I’ve got a job. And he said, yes, sir.”

Van Doran’s written bid to Page & Wirtz provided: “ * * * we guarantee our work for one year only and we do not waive our lien rights.” The Hedgecoke contract with Page & Wirtz required a two-year guarantee and waiver of lien rights, together with several other conditions not included in the Van Doran subcontract masonry bid to Page & Wirtz. Wirtz admitted he used Van Doran’s bid in figuring his general contractor’s bid to the Hedgecoke Estate but denied awarding the subcontract to Van Doran. However, appellant admits for the purpose of this appeal, that Wirtz represented to Van Dor-an on May 12, 1966, that “ * * * if we get the job, the masonry portion of it is your job,” and told Van Doran’s partner, S. O. Garner, on May 16, 1966, that he used Van Doran’s bid in figuring the general contract and they could make their plans accordingly. Van Doran’s trial petition alleges it entered into a contract with Page & Wirtz Construction Co. on May 16, 1966, for performance of the masonry work for the price set forth in Van Doran’s bid on May 12,1966.

Appeal is perfected upon eight points, the first contending that:

“Since the agreement between Van Doran and Wirtz left open for future negotiation material matters to be later agreed upon, no enforceable contract came into existence and no recovery against Page & Wirtz can be sustained.”

Conceding without holding that there is some probative evidence to the effect that the oral contract between Van Doran and Wirtz was not conditioned on acceptance *734 by the Hedgecokes of the terms of the Van Doran bid, the fact still remains that Van Doran admitted throughout his testimony to numerous conditions of the contract between it and Wirtz which would have to be later negotiated. For example, Van Doran testified the requirement to waive lien rights by the subcontractor was a matter which was to be settled at a future time or in future negotiations between it and Wirtz. The same admissions were made as to the two-year guarantee in the Hedgecoke requirements, an escalator clause to apply on future work and as to the arrangement that would have to be made between Van Doran and Wirtz if the Hedgecokes refused to approve of the standard contract conditions of the American Institute of Architecture (A.I.A.). All these, and others, Van Doran admitted were conditions of the subcontract between it and Wirtz which would have to be negotiated in the future between them.

We have searched diligently for a case involving a controversy between a general contractor and subcontractor on questions such as those above related, but to no avail. We perceive no reason why the general rules of contract law would not apply here. One of those rules is that where any essential term of a contract is left open for future negotiations there is no binding contract. 2

Another general rule of contract law is that to make a contract there must be mutual assent; that assent must comprehend the whole of the proposition; must be equal to its extent and provisions; and it must not qualify them by any new matter. Summers v. Mills, 21 Tex.Rep. 77, 78, 88 (Tex.1858) ; Browne Grain Co. v. Walker, 206 S.W. 859 (Tex.Civ.App.-Amarillo, 1918).

The “proposition”, if the contract may be so termed, was admitted by Van Doran to lack at least the several elements above related as constituting conditions still to be negotiated between it and Wirtz.

It is clear in the record that before Van Doran’s bid was submitted the Hedgecokes were insisting on the conditions just related 1 and Van Doran and Wirtz had discussed the fact that efforts would be made by Wirtz to secure modifications thereof to conform to Van Doran’s bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Muscle Shoals Aviation, Inc. v. Muscle Shoals Airport Auth.
508 So. 2d 225 (Supreme Court of Alabama, 1987)
Rialto Theatre, Inc. v. Commonwealth Theatres, Inc.
714 P.2d 328 (Wyoming Supreme Court, 1986)
Retama Manor Nursing Centers, Inc. v. Cole
582 S.W.2d 196 (Court of Appeals of Texas, 1979)
Panama-Williams, Inc. v. Lipsey
576 S.W.2d 426 (Court of Appeals of Texas, 1978)
Briercroft Savings & Loan Ass'n v. Foster Financial Corp.
533 S.W.2d 898 (Court of Appeals of Texas, 1976)
Pine v. Gibraltar Savings Association
519 S.W.2d 238 (Court of Appeals of Texas, 1974)
Parker Chiropractic Research Foundation v. Fairmont Dallas Hotel Co.
500 S.W.2d 196 (Court of Appeals of Texas, 1973)
Etheridge v. Ramzy
276 So. 2d 451 (Mississippi Supreme Court, 1973)
Ingle Bros. Pacific, Inc. v. Scott
478 S.W.2d 210 (Court of Appeals of Texas, 1972)
Sweeney v. Cross
476 S.W.2d 464 (Court of Appeals of Texas, 1972)
Terrazas v. Sullivan
470 S.W.2d 904 (Court of Appeals of Texas, 1971)
Sisk v. Parker
469 S.W.2d 727 (Court of Appeals of Texas, 1971)
Schlusselberg v. Rubin
465 S.W.2d 226 (Court of Appeals of Texas, 1971)
Mattox v. Davis
437 S.W.2d 308 (Court of Appeals of Texas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
432 S.W.2d 731, 1968 Tex. App. LEXIS 2559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-wirtz-construction-co-v-van-doran-bri-tico-co-texapp-1968.