Page-River-Curran v. United States

574 F.2d 1063, 24 Cont. Cas. Fed. 82,320, 216 Ct. Cl. 246, 1978 U.S. Ct. Cl. LEXIS 121
United States Court of Claims·Decided April 19, 1978·No. No. 566-71·Published·Cited by 10 cases

Opinion

Per Curiam:

This is a petition, originally filed in the Tax Court, for redetermination of the excessive profits of a joint venture for its accounting year ended December 31, 1963. The Renegotiation Board determined by unilateral order that petitioner realized excessive profits in the amount of $1,200,000, before tax credits, and ordered elimination of that amount under 50 U.S.C. App. § 1215. The Tax Court [251] petition was transferred here under Pub.L No. 92-41, 85 Stat. 97, 98, and we have jurisdiction under the same statute, which amended 50 U.S.C. App. § 1218.

The case was tried before Trial Judge David Schwartz, who has submitted a recommended decision and conclusion of law under Rule 134(h). He would reduce the determination to $778,036 and both parties except. After briefing and oral argument, the court agrees with the said recommended decision and adopts the same as its own, with minor corrections, and with a few added comments which here follow. We adopt as our own the findings of fact (except for the conclusion of law at the end, which is replaced by ours), but they are not printed herewith, having been furnished to the parties. All the most significant facts are stated in the opinion.

The plaintiff was formed to submit proposals for the single contract here in issue. The joint venturers were Page Communications Engineers, River Construction Corporation, Curran and Company, and Fischbach & Moore, Inc. The contract called for installation in South Dakota of the buried intersite cable communication system in one of the six wings of the intercontinental ballistic missile network known as the Minuteman. The original price, as bid, was $5,476,132, but there were numerous changes, and plaintiff suffered from numerous delays that were attributable to defendant, including delays in delivery of government furnished material. The defendant obligated much over the contract price from the very outset. Rather than a series of equitable adjustments, the parties decided to negotiate a single new fixed price. This was done in late April and early May 1963, and the new fixed contract price was $13,000,000, of which $1,152,000 was the estimated allowance for profit, equal to 8.8 percent of the agreed price. Throughout the negotiation, it was assumed and expected that the negotiated price would allow 10 percent profit on costs. By the date of this supplemental agreement, much of the work had been done and major problems overcome. The trial judge believed that plaintiff at the date of the negotiation could have estimated its costs for the entire job with approximate accuracy. The parties still debate what [252] uncertainties remained. Clearly there were some, but we do not consider it helpful to measure them exactly.

The plaintiffs entire revenues from the job were $13,200,494 and its costs, $10,484,147, leaving a net profit of $2,716,347. These figures are reviewed in this proceeding in their entirety, and revenues under no other contract are involved, because this renegotiation was conducted on a completed contract basis of accounting.

The trial judge, after an exhaustive analysis, constructed a reasonable profit figure by allowing 10 percent, not on actual costs, but on the estimated costs in the negotiation, thus, $1,152,000, the profit contemplated in the 1963 negotiations. Then he added 5 percent of actual costs, for efficiency, and 2% percent for contribution to the defense effort, making a total non-excessive profit of $1,938,311.

Defendant criticizes this as too generous and would restrict the plaintiff to the 10 percent of costs it said it expected.

We note at the outset of our review that the trial judge characterizes the cost estimates plaintiff used in the 1963 negotiation as "inflated.” This is true in the sense that hindsight shows they were excessive by a large figure. It does not mean they were willfully false or that plaintiff had corrective data that it withheld. Defendant disavows such a contention, and necessarily. The Truth in Negotiations Act, Pub.L. No. 87-653, 76 Stat. 528, 10 U.S.C. § 2306(f), as amended, was applicable to this negotiation. Defendant considered but rejected invoking it, but now would accomplish the result it would have achieved if it had invoked that Act, and established that the entire excess of the estimated over the actual cost was contrary to data in plaintiffs possession. The Renegotiation Act is intended for a different purpose. If plaintiff had achieved a large saving in actual as against estimated costs, in a fixed price negotiated contract, negotiated in good faith before performance began, no one would have doubted that in renegotiation it would have been at least entitled to share in the benefit the saving achieved. We are not convinced that the circumstances dictate a different result here. If defendant had wanted to restrict plaintiff to 10 percent on audited costs, it could have proposed a contract to that end. [253] If the original contract overruns had been left to be settled by change order and equitable adjustment, the same result would have occurred, substantially. In insisting on rolling the whole thing into a fixed price contract, without cost escalation, defendant cannot but have supposed it was protecting itself against possible costs in excess of the estimates. We think that by achieving actual costs below good faith estimates, plaintiff is entitled to credit in renegotiation under the "efficiency” and "reasonableness of cost” factors, even though the estimates in question came late and applied partly to costs actually realized already, though not accurately known.

We conclude, then, using as a "starting point” the expected profit of $1,152,000 — which certainly should stand even though the cost on which it was based was lowered — it would be reasonable to share equally between plaintiff and defendant the benefit inuring from the reduction in costs below the estimates. The trial judge’s determination approximately does this, and therefore it need not depend wholly on his 5 percent and 2% percent allowances, which without corroboration might seem arbitrary to some minds.

Free access — add to your briefcase to read the full text and ask questions with AI

Page-River-Curran v. United States, 574 F.2d 1063, 24 Cont. Cas. Fed. 82,320, 216 Ct. Cl. 246, 1978 U.S. Ct. Cl. LEXIS 121 (cc 1978).

574 F.2d 1063 (Page-River-Curran v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

National States Ins. Co. v. Commissioner
81 T.C. No. 25 (U.S. Tax Court, 1983)
United Fire Ins. Co. v. Commissioner
81 T.C. No. 26 (U.S. Tax Court, 1983)
Equipment, Inc. v. United States
30 Cont. Cas. Fed. 70,427 (Court of Claims, 1982)
Page-River-Curran
224 Ct. Cl. 616 (Court of Claims, 1980)
Kilgore Corp. v. United States
613 F.2d 279 (Court of Claims, 1979)
American Diversified Corp. v. United States
609 F.2d 442 (Court of Claims, 1979)
Bata Shoe Co. v. United States
595 F.2d 9 (Court of Claims, 1979)
Manufacturers Service Co. v. United States
582 F.2d 561 (Court of Claims, 1978)