PACT TWO, LLC VS. TOWNSHIP OF HAMILTON (L-1717-19, MERCER COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided April 20, 2020·No. A-1762-19T3·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-1762-19T3

PACT TWO, LLC, Plaintiff-Respondent,

v. TOWNSHIP OF HAMILTON, Defendant-Respondent,

and

QUAD CONSTRUCTION COMPANY,

Defendant-Appellant.

Submitted March 23, 2020 – Decided April 20, 2020 Before Judges Messano, Ostrer and Vernoia.

On appeal from the Superior Court of New Jersey, Law Division, Mercer County, Docket No. L-1717-19.

Walter S. Zimolong, attorney for appellant.

Elissa Grodd Schragger, Township Attorney, attorney for respondent Township of Hamilton.

Florio Perrucci Steinhardt Cappelli Tipton & Taylor LLC, attorneys for respondent Pact Two, LLC (Teresa M. Lentini, on the brief).

PER CURIAM Defendant Quad Construction Company (Quad) appeals from Judge Mary C. Jacobson's order reversing defendant Hamilton Township's (Hamilton) award of a wastewater treatment construction contract to the second-lowest bidder, Quad, and directing the contract be awarded to the lowest bidder, plaintiff Pact Two, LLC. Hamilton rejected plaintiff's bid because it deviated from the bid specifications. Judge Jacobson determined the deviation was not material, and Hamilton's decision not to waive the deviation and award the contract to plaintiff constituted an abuse of discretion because it was not based on sound business judgment and is inconsistent with the policies underlying the Local Public Contracts Law (LPCL), N.J.S.A. 40A:11-1 to -49. We agree and affirm.

I.

The pertinent facts are not disputed. Hamilton published a notice to bidders for the award of a contract for the rehabilitation of the gravity thickener collector mechanism and existing digester floating cover at its wastewater treatment plant. Hamilton provided bid specifications detailing the work and

A-1762-19T3

equipment to be supplied under the contract, and the requirements for the bid submissions.

The specifications required installation of a domed "guided gas holder cover" (cover) over the existing digester tank. The cover is an important and integral part of the rehabilitation project for which the bids were requested.1 Section 11661 of the specifications required bidders supply information concerning "the furnishing, installation, . . . [and] testing" of the cover.

Part 2 of Section 11661 detailed the cover's requirements. More particularly, Part 2.3(D) required an analysis, "using a finite element model with all applied loading" (finite model analysis), of the cover the bidder proposed to install. The specifications also required "[t]he analysis . . . be performed using recognized software which is commercially available with verification problems and complete documentation and instructions."

Most pertinent to this appeal, Part 2.3(G) specified the cover manufacturer "must have provided [a finite model analysis] on no less than [ten] covers in the

1 The specifications explained the cover is "for installation in the existing [d]igester which is [forty-five] feet in diameter"; is dome-shaped; must be designed by a professional engineer; and "shall all be made of structural steel." The specifications further required the cover "have a radius 1.5 times the tank diameter" and its "framework shall consist of arched radial erection beams held in position by a center compression ring and peripheral thrusting ring."

A-1762-19T3

past [five] years." Part 2.3(G) further directed that "[e]vidence" the cover manufacturer performed a finite model analysis "on no less than [ten] covers in the past [five] years . . . be provided with the bid package," including the "location of [the] projects and [the] software used."

On July 31, 2019, Hamilton opened the seven bids it received for the contract. Plaintiff's $1,945,000 bid was lowest, and Quad's $2,048,850 bid was second lowest.2 Plaintiff's and Quad's bids included deviations from Part 2.3(G). Plaintiff did not include evidence its intended cover manufacturer performed finite model analyses on no less than ten covers in the past five years, or the location of the projects and software used to perform such analyses , as required under Part 2.3(G). Quad's bid included evidence of its cover manufacturer's performance of the finite model analyses, but it did not include evidence concerning the software used.

In a July 31, 2019 letter to Hamilton, Quad "formally protest[ed]"

plaintiff's bid. Quad asserted the bid was "non-responsive to the solicitation" because it did not include evidence concerning the cover manufacturer's finite

2 The remaining bids included: Eastern Environmental Contractors, Inc., $2,194,200; Stonehill Contracting Co., Inc., $2,331,549; BR Welding, Inc., $2,332,500; Spectraserv, Inc., $2,335,750; and GMH Associates of America, Inc., $2,425,204.

A-1762-19T3

model analyses as required by Part 2.3(G). Quad asserted the omission "was a material defect which cannot be waived . . . in accordance with the [LPCL]."

On August 20, 2019, Hamilton adopted a resolution awarding the contract to Quad. The resolution listed the amount of each bid, noted plaintiff was the lowest bidder, and stated plaintiff's bid "was non-compliant missing required documentation [and] therefore deemed a no[-]bid."

Plaintiff filed a complaint and order to show cause challenging Hamilton's rejection of its bid and award of the contract to Quad, and requesting injunctive relief. At the order to show cause hearing, Judge Jacobson noted Hamilton rejected plaintiff's bid because it found the failure to include evidence concerning the cover manufacturer's finite model analyses constituted a material bid deviation it lacked the authority to waive. The judge, however, found the record did not permit a determination whether plaintiff's failure to include the evidence constituted a non-waivable material bid deviation under the standard established in Township of River Vale v. R.J. Longo Construction Co., 127 N.J. Super. 207 (Law Div. 1974), as adopted by our Supreme Court in Meadowbrook Carting Co. v. Borough of Island Heights, 138 N.J. 307 (1994), or a deviation Hamilton had discretion to waive under the principles addressed in Serenity Contracting Group, Inc. v. Borough of Fort Lee, 306 N.J. Super. 151 (App. Div.

A-1762-19T3

1997). The judge further observed Hamilton failed to consider Quad's bid deviated from Part 2.3(G)'s requirements because Quad did not provide evidence of the software used by its cover manufacturer to perform the finite model analyses.

Judge Jacobson entered an order granting plaintiff's application for a preliminary injunction barring implementation of the contract. The judge remanded the matter for Hamilton to determine whether plaintiff's bid deviation deprived Hamilton of assurance the contract would be performed as expected; placed plaintiff in a position of advantage over other bidders; or otherwise undermined competitive bidding. The court ordered Hamilton to make the same determinations concerning the deviation in Quad's bid. The court also required that Hamilton consider whether other bid requirements provided Hamilton with adequate assurance the contract would be performed as expected if plaintiff and Quad supplied the evidence missing from their bids after the bid opening. 3

Free access — add to your briefcase to read the full text and ask questions with AI

PACT TWO, LLC VS. TOWNSHIP OF HAMILTON (L-1717-19, MERCER COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

PACT TWO, LLC VS. TOWNSHIP OF HAMILTON (L-1717-19, MERCER COUNTY AND STATEWIDE) (PACT TWO, LLC VS. TOWNSHIP OF HAMILTON (L-1717-19, MERCER COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Terminal Construction Corp. v. Atlantic County Sewerage Authority
341 A.2d 327 (Supreme Court of New Jersey, 1975)
In Re Jasper Seating Co., Inc.
967 A.2d 350 (New Jersey Superior Court App Division, 2009)
Matter of On-Line Games Contract
653 A.2d 1145 (New Jersey Superior Court App Division, 1995)
Meadowbrook Carting Co. v. Borough of Island Heights
650 A.2d 748 (Supreme Court of New Jersey, 1994)
Marvec Const. v. Belleville Tp.
603 A.2d 184 (New Jersey Superior Court App Division, 1992)
Tp. of River Vale v. RJ Longo Const. Co.
316 A.2d 737 (New Jersey Superior Court App Division, 1974)
Tec Electric, Inc. v. Franklin Lakes Board of Education
665 A.2d 803 (New Jersey Superior Court App Division, 1995)
Serenity Contracting Group, Inc. v. Borough of Fort Lee
703 A.2d 352 (New Jersey Superior Court App Division, 1997)
Sklodowsky v. Lushis
11 A.3d 420 (New Jersey Superior Court App Division, 2011)
In re Stallworth
26 A.3d 1059 (Supreme Court of New Jersey, 2011)