Pacific Telephone & Telegraph Co. v. Monolith Portland Cement Co.

234 Cal. App. 2d 352, 44 Cal. Rptr. 410, 1965 Cal. App. LEXIS 1021
CourtCalifornia Court of Appeal
DecidedMay 12, 1965
DocketCiv. 421
StatusPublished
Cited by7 cases

This text of 234 Cal. App. 2d 352 (Pacific Telephone & Telegraph Co. v. Monolith Portland Cement Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Telephone & Telegraph Co. v. Monolith Portland Cement Co., 234 Cal. App. 2d 352, 44 Cal. Rptr. 410, 1965 Cal. App. LEXIS 1021 (Cal. Ct. App. 1965).

Opinion

BROWN (R.M.), J.

This appeal originated in a proceeding in eminent domain brought by the respondent against the appellant. The condemnation proceeding sought to acquire an easement over two parcels of land for the placement of *354 underground transcontinental coaxial cable, to acquire one parcel in fee for an underground repeater station, and another parcel for an easement for a right of way to be used for ingress to and egress from its underground facilities.

Appellant appeals from the judgment claiming that an improper form of verdict was submitted to the jury, and from an order taxing costs which involved the question whether or not there was a partial abandonment of the proceeding.

Appellant’s contention is that respondent amended its complaint during trial and thereby abandoned substantial claims and demands less than 40 days prior to the time set for the pretrial conference and thus made itself liable for the payment to appellant of costs and disbursements and attorneys’ fees under the provisions of section 1255a, subdivision (c), of the Code of Civil Procedure.

In the complaint filed August 23, 1963, the respondent sought a right of way 20 feet in width in and over parcels One and Two “to construct, operate, maintain, replace and remove such communications systems as plaintiff may from time to time require, consisting of underground cables, wires, conduits, manholes, drains and splicing boxes; surface testing terminals and markers; and other appurtenances; hereinafter collectively referred to as ‘underground facilities. ’ ” Respondent also sought the right to prohibit all structures from being erected on the easement without respondent’s written approval, to clear and keep cleared trees, roots, brush and other obstructions from the surface, to install gates and stiles in fences, to permit construction, maintenance and removal of underground facilities, right of ingress and egress, and to use a strip of land 15 feet on each side of the easement for operation and storage of vehicles and machinery. It was further alleged in the complaint that respondent sought to condemn a parcel of land in fee “as a site upon which to construct” certain underground facilities.

The appellant’s answer generally alleged that it was not fully informed as to the nature and extent of the use of said easement and was unable to allege the value of the lands sought to be condemned or the diminution in value of the remaining lands, and asked leave to amend its answer in the f uture.

The pretrial conference was held November 19, 1963. After much discussion it was agreed that the judge might order the respondent to answer under oath as in an answer to inter *355 rogatories giving the extent and depth of the easement which was required. Appellant’s counsel also wanted a statement as to the extent the easement would interfere with existing facilities which was agreed upon. Thereupon, appellant’s counsel stated that if respondent answered these interrogatories the appellant would know which way to go and could be ready for trial in January. The pretrial order filed December 2, 1963, ordered respondent within two weeks to furnish the appellant with “information concerning the depth to which the easement will extend and its interference, if any, with existing facilities belonging to defendant.” The issues reserved by the pretrial order to be tried by the court included the nature of the easement required, and the necessity for a restrictive condition in the easement interfering with longstanding preexisting use by appellant of extensive water-producing facilities. (Both of these issues- were requested by appellant’s pretrial conference statement.)

On December 7, 1963, the respondent served and filed an affidavit defining the extent of the easement.

Prior to the commencement of the valuation phase of the trial before a jury, the special issues were tried on January 27, 1964, and the trial court made its order on the special issues decreeing that the parcels of land were sought to be condemned for a use authorized by law. Limitations were then ordered as to the easement. Permanent structures were prohibited as to parcels One and Two; certain temporary movable structures were authorized. The respondent was given the right to initially clear any trees, roots, brush and other obstructions from the surface and subsurface, but had no obligation to keep the easement clear. Respondent's use of two additional strips of land on each side of the easement was limited to a period of 90 days and the depth of the easement was limited to 7 feet from the surface to the extent of at least 2 feet vortical distance above and below the cable, and appellant was given the right to install certain sewer lines and similar facilities across and through the easement outside of the clearance.

Concurrently with the signing and filing of this order and judgment, the respondent was permitted to amend its complaint to conform to the provisions set forth in the order.

It is appellant’s claim that this amendment came too late; that appellant’s counsel had prepared for a full-scale trial on the issue of severance damages on the basis of the original *356 complaint in which the easement was sought from the surface to the center of the earth, and appellant takes the position that the affidavit of December 7th cannot operate to amend the complaint and that appellant had a right to rely on the allegations of the complaint as filed and thus was entitled to consideration in preparing for trial on the basis of the complaint as well as to obtain attorneys’ fees. The respondent correctly points out that at the time of the pretrial the appellant requested supplementary information as to the nature and extent of the easement and its anticipated interference with existing water lines and agreed to having that information submitted by affidavit, which was done. At that time the appellant had made no trial preparations. After it received the affidavit it knew the scope and extent of the easement and appellant was not required to prepare for trial on any issues beyond the easement as described in the complaint and limited in the affidavit. Appellant had this information by affidavit almost two months prior to trial.

Respondent urges that the amendment to the complaint was surplusage, and calls attention to the issues requested in appellant’s pretrial statement which were preserved in the pretrial order. The question of public use in condemnation proceedings vests the court with jurisdiction to determine the extent of the use. The appellant having presented the special issue to the court for determination, its order and judgment limiting the use controls without the necessity for amendment of the pleadings.

Further matters occurred during the jury phase of the trial which appellant claims relate to the question of partial abandonment. It is appellant’s claim that it might be liable for damages occurring to the coaxial cable or other facilities by reason of the use of the surface to store and spread water, by percolation, or by electrolysis. Respondent at that time was willing to agree that the court might order as part of the judgment that the appellant would not be liable for damages so occasioned, and on January 30th the respondent did file in the action a unilateral statement to that effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Department of Transportation v. Chelsea Butane Co.
2004 OK CIV APP 48 (Court of Civil Appeals of Oklahoma, 2004)
Heiner v. Kmart Corp.
100 Cal. Rptr. 2d 854 (California Court of Appeal, 2000)
Salton Bay Marina, Inc. v. Imperial Irrigation District
172 Cal. App. 3d 914 (California Court of Appeal, 1985)
Alta Bates Hospital v. Mertle
31 Cal. App. 3d 349 (California Court of Appeal, 1973)
San Francisco Bay Area Rapid Transit District v. Fremont Meadows, Inc.
20 Cal. App. 3d 797 (California Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
234 Cal. App. 2d 352, 44 Cal. Rptr. 410, 1965 Cal. App. LEXIS 1021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-telephone-telegraph-co-v-monolith-portland-cement-co-calctapp-1965.