Pacific Gas & Electric Co. v. Parachini

29 Cal. App. 3d 159, 105 Cal. Rptr. 477, 1972 Cal. App. LEXIS 683
CourtCalifornia Court of Appeal
DecidedDecember 6, 1972
DocketCiv. 38449
StatusPublished
Cited by5 cases

This text of 29 Cal. App. 3d 159 (Pacific Gas & Electric Co. v. Parachini) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas & Electric Co. v. Parachini, 29 Cal. App. 3d 159, 105 Cal. Rptr. 477, 1972 Cal. App. LEXIS 683 (Cal. Ct. App. 1972).

Opinions

Opinion

FILES, P. J.

This eminent domain proceeding was brought to acquire an easement 350 feet in width across defendants’ cattle ranch for two 500 kilovolt transmission lines, on a route between the Diablo Canyon generating site in San Luis Obispo County and the Gates substation near Coalinga. After a jury trial, a judgment was entered on August 7, 1970 that plaintiff was entitled to take the easement upon payment of $30,800 to defendants. A final order of condemnation was entered the same day. Defendants are appealing from both the judgment and the order.

[162]*162Defendants’ first two contentions are that the trial court lacked jurisdiction, and that plaintiff failed to prove necessity for the taking. Some background is necessary to put these arguments into context.

On December 23, 1966, plaintiff, applied to the Public Utilities Commission of California for a certificate of public convenience and necessity under section 1001 of the Public Utilities Code to construct and operate a nuclear fueled power plant at a site in Diablo Canyon. Hearings were held on this application and, on November 7, 1967, the Commission handed down its decision No. 73278, containing an interim order that a certificate issue to construct and operate a nuclear fueled power generating unit of approximately 1,060,000 kilowatts capacity, together with appurtenant facilities and transmission lines as described in that proceeding. In its decision, the commission noted that plaintiff contemplated eventual installation of six generating units in the same locality, and the commission approved the construction of an intake structure to handle cooling water for three units. The switchyard area, as shown in the plan which the commission approved, was sized to accommodate six units. The approved plan included a single 500 kv transmission line to Gates and another to' Midway substation. The commission observed, “The two lines would handle somewhat more than the output of the proposed unit but an additional circuit would be required upon construction of a second generating unit at the site.”

On February 16, 1968, plaintiff filed an application with the commission for a certificate to construct and operate a second nuclear fueled power plant at Diablo Canyon. After investigation and a public hearing, this application was granted by an interim order on March 25, 1969, in decision No. 75471. The decision again noted that plaintiff was looking ahead to a possible total of six units.

On January 27, 1970, the commission undertook an investigation looking towards the issuance of a general order to protect the environment and carry out the commission’s other responsibilities in connection with the planning and construction of facilities for generating and transmitting electricity. This investigation culminated in the commission’s decision No. 77301, issued June 3, 1970, which adopted General Order No. 131. This order provides, among other things, that no regulated utility shall begin construction of overhead line facilities designed for voltage in excess of 200 kilovolts without the commission’s first having found, after consideration of the environmental impact, that the facilities are required by the public convenience and necessity. The order further establishes procedures for hearings, and standards for the issuance of the certificates required under that order.

[163]*163The complaint in this eminent domain proceeding was filed January 29, 1969.

When this case was called for trial on June 8, 1970, counsel for defendants informed the court that a complaint was about to be filed with the Public Utilities Commission asking that the route of the transmission line be changed. He requested the court to continue , the trial until after the commission had reached a decision on that complaint. Plaintiff opposed a continuance and the trial court denied it. The trial then went forward.

On June 8, 1970, Mary Hartzell, one of the defendants, filed with the Public Utilities Commission a complaint requesting the commission to (a) issue a temporary order restraining plaintiff from proceeding with right-of-way acquisition along the Diablo-Gates route, (b) undertake a study of alternate routes, and (c) select an alternate and prohibit plaintiff permanently from constructing on the route which had theretofore been selected.

Jurisdiction

It is now defendants’ contention that the filing of the complaint before the Public Utilities Commission on June 8, 1970, divested the superior court of jurisdiction in this eminent domain proceeding. Defendants’ counsel cites no cases for that proposition, but relies generally upon the statutes which prohibit a utility from constructing a facility without a certificate from the commission (Pub. Util. Code, § 1001) and which forbid any court other than the Supreme Court to interfere with the commission in the performance of its duties (Pub. Util. Code, § 1759). There is no indication that the commission ever issued the restraining order which defendant Hartzell requested.

The acquisition of property through the power of eminent domain and the construction of facilities thereon are distinct functions. The acquisition of property by a public utility does not necessarily interfere with the exercise of the commission’s authority to determine what shall be built and where. We must reject the bald proposition that a defendant in an eminent domain proceeding may, at will, oust the court of jurisdiction by the simple act of filing a petition with the commission.1

Necessity to the Proposed Public Use

The trial commenced with testimony as to the necessity for taking the easement. The sole witness on that subject was a consulting electrical engi[164]*164neer, a retired employee of plaintiff. The witness described generally the projected need for additional generating facilities in California over the next decade, plaintiff’s plans for the Diablo Canyon development, - and the manner in which the electricity generated there would be transmitted through the Gates substation for connection with the Pacific Northwest-Pacific Southwest intertie system. He testified that the Public Utilities Commission had approved in principle the proposed construction of six generating units at Diablo Canyon, that both the Public Utilities Commission and the Atomic Energy Commission had specifically approved the first unit, which was then under construction, that the Public Utilities Commission had approved the second; and that the application before the Atomic Energy Commission for the second unit was pending.2 He explained that an easement 200 feet wide would be necessary for a single transmission line (which had been approved by the Public Utilities Commission in 1967), but 350 feet would be required to accommodate two parallel 500 kilovolt lines. The second line to Gates would be necessary when the third generating unit began to operate, which the witness estimated would be in 1975 or 1976.

Defendants offered no evidence to contradict or impeach this testimony. The trial court thereupon made its finding that the taking of the easement was necessary for a public use.

Deféndants’ attack here upon the sufficiency of the evidence focuses upon the second line, and the claimed necessity for a 350-foot easement rather than the 200 feet which would suffice for the single line which the Public Utilities Commission had theretofore expressly authorized.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foley Investments v. Alisal Water Corp.
California Court of Appeal, 2021
Cantu v. Pacific Gas & Electric Co.
189 Cal. App. 3d 160 (California Court of Appeal, 1987)
Pacific Gas & Electric Co. v. Hay
68 Cal. App. 3d 905 (California Court of Appeal, 1977)
State Ex Rel. Department of Water Resources v. Clark
33 Cal. App. 3d 463 (California Court of Appeal, 1973)
Pacific Gas & Electric Co. v. Parachini
29 Cal. App. 3d 159 (California Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
29 Cal. App. 3d 159, 105 Cal. Rptr. 477, 1972 Cal. App. LEXIS 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-electric-co-v-parachini-calctapp-1972.