Pacific Engineering Inc. v. United States

United States Court of Federal Claims·Decided October 23, 2025·No. 25-1115·Published

Opinion

In the United States Court of Federal Claims BID PROTEST

) PACIFIC ENGINEERING INC., ) ) Plaintiff, ) ) v. ) ) THE UNITED STATES OF AMERICA, ) No. 25-1115C ) (Filed Under Seal: October 7, 2025 Defendant, ) Reissued: October 23, 2025) ∗ ) and ) ) BAE SYSTEMS LAND & ARMAMENTS ) L.P., ) ) Defendant-Intervenor. ) )

Ryan C. Bradel, Ward & Berry, PLLC, Tysons, VA, for Plaintiff, with whom were Mary Pat Buckenmeyer, Aaron L. Jackson, P. Tyson Marx, and Nicholas L. Perry, Of Counsel.

Mariana Teresa Acevedo, William J. Grimaldi, Patricia M. McCarthy, and Brett A Shumate, U.S. Department of Justice Washington, DC, for Defendant, with whom was Eric M. Carlson, Naval Sea Systems Command, Washington, DC, Of Counsel.

Jeffery M. Chiow, Greenberg Traurig, LLP, Washington, DC, for Defendant-Intervenor, with whom were Eleanor M. Ross and Olivia C. Bellini, Of Counsel.

OPINION AND ORDER KAPLAN, Judge

In this post-award bid protest, Plaintiff, Pacific Engineering, Inc. (“PEI”), challenges the decision of the Department of the Navy, Naval Sea Systems Command (“NAVSEA” or the “Agency” or the “Navy”) to award Defendant-Intervenor, BAE Systems and Land Armaments

∗ This opinion was originally issued under seal, and the parties were given the opportunity to request redactions. The Plaintiff, Pacific Engineering Inc., did not request redactions. The government and the Defendant-Intervenor, BAE Land & Systems Land & Armaments L.P., requested a few unopposed redactions, which the Court has adopted. L.P. (“BAE”), a contract to produce MK 41 Vertical Launching Systems (“VLS”) canisters. The canister variant that is the subject of this protest is the MK 29. See AR Tab 5 at 67.

VLS canisters are used as missile shipping containers and launch tubes. See AR Tab 17a at 714. For the last thirty years, the Navy has awarded all its MK 41 VLS canister contracts to BAE, AR Tab 16 at 479, most recently on February 11, 2020, AR Tab 82 at 7822. In the NAVSEA’s two most recent attempted competitive actions to procure the canisters, BAE was the only offeror. Id.

To address the problem of limited competition, the Navy conducted market research and adjusted the Solicitation in some respects, as explained below. Their efforts bore some fruit as three offerors submitted proposals in response to the Solicitation at issue here: PEI, BAE, and [* * *]. Still, NAVSEA ultimately awarded the canister contract to BAE again, finding its proposal represented the best value to the government.

PEI challenges the award to BAE on several related grounds. Its central contention is that NAVSEA’s decision to assign four weaknesses to PEI’s technical proposal was arbitrary and capricious and reflected disparate treatment. Pl.’s Mot. for J. on the Admin. Rec. (“MJAR”) at 8– 22, ECF No. 37. Therefore, PEI contends, the relatively low adjectival ratings assigned to its proposal (“Marginal” based on its technical approach and presenting a “Moderate” performance risk) were unjustified. Id. at 22–25. In addition, PEI claims the discussions the Agency held with it regarding the four weaknesses were not meaningful and that the result of the Agency’s approach to PEI’s proposal was to effectively convert the procurement into a de facto sole source acquisition. Id. at 25–36.

On September 30, 2025, the Court ruled on the parties’ cross-motions for judgment on the administrative record, denying PEI’s motion and granting the motions of the government and BAE. ECF No. 52. What follows is an explanation of that ruling.

BACKGROUND

I. The Solicitation On May 30, 2023, the Navy issued Solicitation No. N00024-23-R-5324 (the “Solicitation” or “RFP”). See AR Tabs 17–17zf. It contemplated the award of a firm fixed price contract, on a best value basis, to “fabricate, assemble, inspect, test, and deliver the VLS Canister and associated equipment in accordance with technical drawings and specifications identified in the Statement of Work.” AR Tab 17a at 716. The Solicitation was amended six times, making changes in response to bidder’s questions and extending the proposal submission dates. See AR Tabs 18–24.

As noted, to increase competition, NAVSEA conducted market research as part of the planning process for the procurement. It gathered feedback from industry by issuing a Request for Information, and it held several industry events. See AR Tabs 2–4, 6, 9–11.

The feedback the Agency received resulted in several changes to its procurement strategy. Foremost among these was the Agency’s decision to split the Solicitation into three parts based on canister type: steel (0xxx series), quad pack steel (1xxx series), and composite

2 (2xxx series). AR Tab 3 at 53; AR Tab 13 at 463; AR Tab 14 at 470. This change gave offerors the option of submitting proposals for any one canister type, or for all of them. AR Tab 16 at 484.

PEI’s protest concerns the Agency’s decision to award the contract to produce the 2xxx composite canister series. AR Tab 24a at 2713–26, 2812. The other contract awards are not at issue in this action.

A. Evaluation Criteria The Solicitation provided NAVSEA would evaluate proposals by reference to three factors: Technical Approach and Production Capability (Factor 1); Past Performance (Factor 2); and Total Evaluated Price (“TEP”) (Factor 3). Id. at 2828. The Agency reserved the right to conduct discussions in accordance with FAR 15.306. Id. at 2815. After any discussions the Agency decided to hold, it would request Final Proposal Revisions (“FPRs”) from all offerors within the competitive range. Id.

1. Factor 1: Technical Approach and Production Capability Technical Approach and Production Capability covered five elements: Production in Accordance with the Technical Data Package (“TDP”) (Element 1); First Article Qualification Testing and Factory Acceptance Testing (Element 2); Facility and Tooling (Element 3); Quality Assurance Approach (Element 4); and Program Management (Element 5). Id. at 2821–22, 2828. The evaluation of the parties’ proposals under Elements 1, 3, and 5 are relevant to the present protest.

Under Element 1, the Solicitation required offerors to provide a manufacturing plan that included an Integrated Master Plan, Integrated Master Schedule, and a Work Breakdown Structure. Id. at 2821. Offerors were instructed to demonstrate their technical approach and production capability to perform the contract in accordance with the delivery schedule. Id. The RFP also stated that the manufacturing plan should identify any risks and the offerors’ approach to managing those risks. Id.

Under Element 3, offerors were instructed to “describe the proposed production assets, test assets, and capital assets in sufficient detail as to demonstrate adequate infrastructure, capability, and capacity for the production and test of the proposed canisters at the production rates that result in on-time delivery.” Id. The Solicitation directed that they “specifically discuss” both the “availability of assets during the contract period of performance” and their “ability to mitigate the risk of a major equipment failure impacting schedule.” Id.

Finally, under Element 5, the Solicitation dictated that proposals “describe [an offeror’s] program management approach for staffing, subcontractor management, production planning, and communications with the Government.” Id. at 2822. The staffing plans were to demonstrate how the offeror would provide the resources needed to execute the contract as well as the experience of the planned engineering staff in “first article inspection, fault isolation, failure analysis, source qualification, and test equipment design for military systems used in a United States Department of Defense or allied country military production program.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific Engineering Inc. v. United States, (uscfc 2025).

Pacific Engineering Inc. v. United States (Pacific Engineering Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
Axiom Resource Management, Inc. v. United States
564 F.3d 1374 (Federal Circuit, 2009)
Honeywell, Inc. v. The United States v. Haz-Tad, Inc.
870 F.2d 644 (Federal Circuit, 1989)
E.W. Bliss Company v. United States
77 F.3d 445 (Federal Circuit, 1996)
Advanced Data Concepts, Incorporated v. United States
216 F.3d 1054 (Federal Circuit, 2000)
Bannum, Inc. v. United States
404 F.3d 1346 (Federal Circuit, 2005)
Glenn Defense Marine (Asia), PTE Ltd. v. United States
720 F.3d 901 (Federal Circuit, 2013)
Greenland Contractors I/S v. United States
131 Fed. Cl. 216 (Federal Claims, 2017)
Palantir Usg, Inc. v. United States
904 F.3d 980 (Federal Circuit, 2018)
Xotech, LLC v. United States
950 F.3d 1376 (Federal Circuit, 2020)
Office Design Group v. United States
951 F.3d 1366 (Federal Circuit, 2020)