Pacific Construction Services, Inc. v. Stone City Ironworks, Inc.

CourtDistrict Court, N.D. Illinois
DecidedMarch 9, 2020
Docket1:19-cv-04036
StatusUnknown

This text of Pacific Construction Services, Inc. v. Stone City Ironworks, Inc. (Pacific Construction Services, Inc. v. Stone City Ironworks, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Construction Services, Inc. v. Stone City Ironworks, Inc., (N.D. Ill. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

PACIFIC CONSTRUCTION SERVICES, INC., ) an Illinois corporation, ) ) Plaintiff, ) ) v. ) Case No. 19-cv-4036 ) STONE CITY IRONWORKS, INC., an ) Indiana corporation, and BRIAN L. SLINKARD, ) ) Defendants. )

MEMORANDUM OPINION AND ORDER Plaintiff Pacific Construction Services, Inc. (“PCS”) filed a two-count complaint against Stone City Ironworks, Inc. (“SCI”) and SCI’s president Brian L. Slinkard (together, “defendants”) alleging breach of contract and fraud. Defendants asserted affirmative defenses in their answer to the complaint and SCI filed a counterclaim. PCS moves to dismiss the counterclaim pursuant to Federal Rule of Civil Procedure 12(b)(6) and to strike the affirmative defenses under Rule 12(f). For the reasons outlined below, the motion is granted. Background For the purposes of this motion, the Court accepts as true the following facts from the complaint. In 2018, PCS was the general contractor for a federal government construction project at the Fermilab Facility in Batavia, Illinois (“the project”). In April 2018, PCS and SCI entered into a subcontract for SCI to provide structural steel work for the project. In May 2018, SCI retained Metropolitan Steel, Inc. (“Metropolitan”) as its steel erector subcontractor for the project and advised PCS that Metropolitan’s total contract amount was $476,500.00. On October 18, 2018, Slinkard submitted a request for payment to PCS, representing that SCI would pay Metropolitan $232,719.00, after retention, for work Metropolitan had completed on the project. That same day, PCS issued a check to SCI in the amount of $466,013.23, which SCI deposited on October 26. PCS next requested an updated partial waiver of lien evidencing that SCI had made the represented payment to Metropolitan, but SCI refused to produce the waiver because, despite its representations, it failed to pay the requested amount to Metropolitan. On December 13, PCS demanded that SCI pay Metropolitan pursuant to the payment request, but SCI did not turn the funds over to Metropolitan. SCI then failed to complete its work under the subcontract.

In January 2019, PCS put SCI on notice of its default and demanded that the default be cured. PCS eventually terminated the subcontract with SCI after it failed to complete its work or pay Metropolitan. PCS has since paid Metropolitan directly for its work on the project. This lawsuit followed, in which PCS asserts a breach-of-contract claim against SCI (Count I) and a fraud claim against both defendants (Count II). Defendants answered the complaint and asserted the following affirmative defenses: (1) “Plaintiff never expressed any problems with the erection services of Metropolitan Steel, Inc.”; (2) “Plaintiff was told in or about December 20, 2019 that Metropolitan would complete all erection services for the balance of the contracted for amount.”; (3) “As of December 20, 2019 the balance of the Metropolitan [sic] was approximately $60,000.00.”; and (4) “Plaintiff should be estopped and barred from claiming erection services to complete the project in excess of the Metropolitan balance.” (Dkt. 14 at 10.) SCI also asserted a counterclaim for damages, alleging that at the precontract meeting, PCS acknowledged its understanding that the contract was to have no retainage on materials and was to

include offsite storage of steel materials prior to erection, that the contract was assumed in good faith to contain the terms agreed to by the parties, and that PCS demanded additional goods and services outside the scope of the agreement and “ultimately agreed such additional services need not be provided without proper compensation and they were not provided.” (Dkt. 14 at 11-12.) Legal Standard A motion to dismiss under Rule 12(b)(6) for failure to state a claim tests the sufficiency of a pleading, not its merits. See Camasta v. Jos. A. Bank Clothiers, Inc., 761 F.3d 732, 736 (7th Cir. 2014). In considering a motion to dismiss, the Court accepts well pleaded factual allegations as true and draws all reasonable inferences in favor of the nonmovant. Erickson v. Pardus, 551 U.S. 89, 94, 127 S.Ct. 2197, 167 L.Ed.2d 1081 (2007); Trujillo v. Rockledge Furniture LLC, 926 F.3d 395, 397 (7th Cir.

2019). To survive a motion to dismiss, the pleading must “state a claim to relief that is plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007). A claim is facially plausible when it contains “factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Boucher v. Fin. Sys. of Green Bay, Inc., 880 F.3d 362, 366 (7th Cir. 2018) (citing Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009)). Affirmative defenses are pleadings and therefore subject to all of the pleading requirements of the Federal Rules of Civil Procedure. Heller Fin. Inc. v. Midwhey Powder Co., Inc., 883 F.2d 1286, 1294 (7th Cir. 1989). Affirmative defenses must contain sufficient factual allegations that state a defense that is plausible on its face under Iqbal and Twombly. The Court may strike affirmative defenses that are conclusory, vague, and unsupported because they do not meet the requirements imposed by Rule 8(a). See Heller, 883 F.2d at 1294. Motions to strike affirmative defenses are disfavored generally but will be granted where they remove unnecessary clutter from the case or

where the affirmative defense is insufficient on the face of the pleadings. Id. However, the striking of an affirmative defense does not necessarily preclude the party from asserting or arguing its substantive merits later in the case. Palomares v. Second Fed. Sav. & Loan Ass’n of Chi., 2011 WL 2111978, *2 (N.D.Ill. May 25, 2011) (citing Instituto Nacional De Comercializacion Agricola (Indeca) v. Cont’l Ill. Nat’l Bank & Trust Co., 576 F.Supp. 985, 988 (N.D.Ill.1983) (Shadur, J.)). Discussion Rule 12(b)(6) motion to dismiss PCS moves to dismiss the counterclaim, arguing that it cannot be faulted for SCI’s failure to review the subcontract before execution or failure to note the retainage provision, that the subcontract unambiguously provides for retainage, and that because the retainage provision is unambiguous it is enforceable as written. (Dkt. 15 at 3-4.) In its response brief, SCI contends that

its counterclaim pleads the right to payment for the work it completed for PCS per their agreement in the subcontract. SCI also asserts several additional facts regarding the subcontract’s language and work it had allegedly completed under the subcontract. (Dkt. 26 at 2-3.) The subcontract between PCS and SCI is governed by Illinois law. (Dkt. 15-1 at 17 (“This agreement shall be governed by the laws of the State of Illinois.”) To state a breach-of-contract claim under Illinois law, a plaintiff must plead facts showing “(1) offer and acceptance, (2) consideration, (3) definite and certain terms, (4) performance by the plaintiff of all required conditions, (5) breach, and (6) damages.” Wigod v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Wigod v. Wells Fargo Bank, N.A.
673 F.3d 547 (Seventh Circuit, 2012)
Agnew v. National Collegiate Athletic Ass'n
683 F.3d 328 (Seventh Circuit, 2012)
Northern Trust Co. v. VIII South Michigan Associates
657 N.E.2d 1095 (Appellate Court of Illinois, 1995)
Patrick Camasta v. Jos. A. Bank Clothiers, Inc.
761 F.3d 732 (Seventh Circuit, 2014)
Asset Exchange II. LLC v. First Choice Bank
2011 IL App (1st) 103718 (Appellate Court of Illinois, 2011)
Ryan Boucher v. Finance System of Green Bay, I
880 F.3d 362 (Seventh Circuit, 2018)
Humberto Trujillo v. Rockledge Furniture
926 F.3d 395 (Seventh Circuit, 2019)
Typenex Co-Investment, LLC v. Solar Wind Energy Tower, Inc.
123 F. Supp. 3d 1017 (N.D. Illinois, 2015)
State Farm Mutual Automobile Insurance v. Riley
199 F.R.D. 276 (N.D. Illinois, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Pacific Construction Services, Inc. v. Stone City Ironworks, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-construction-services-inc-v-stone-city-ironworks-inc-ilnd-2020.