Pacific Coast Shredding, Llc, Appellant/cross-res. v. Port Of Vancouver, Usa, Res/cross-app.

Court of Appeals of Washington·Decided September 1, 2020·No. 52020-6·Published

Opinion

Filed

Washington State

Court of Appeals

Division Two

September 1, 2020

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

PACIFIC COAST SHREDDING, L.L.C., a No. 52020-6-II Washington limited liability company,

Appellant/Cross-Respondent, v.

PORT OF VANCOUVER, USA, a PUBLISHED OPINION Washington municipal corporation,

Respondent/Cross-Appellant.

GLASGOW, J.—The Port of Vancouver USA (Port) condemned a portion of land it leased to Pacific Coast Shredding LLC (PCS) and informed PCS of its right under federal and state law to receive financial compensation for any reasonable and necessary costs that PCS incurred as a result of the taking. PCS made a number of significant modifications to its operations and requested reimbursement for each of them. The Port largely rejected the request and paid PCS only for the cost of moving some of its personal property out of the condemned area.

PCS appealed to an administrative panel, which upheld the Port’s decision. PCS then appealed to the superior court, which reversed. The court ruled that the panel erred in denying additional compensation because it failed to consider which of PCS’s actions were reasonable and necessary responses to the taking. The court held that the taking required PCS to do more than simply move personal property out of the condemned area in order to continue its operations. The Port did not further appeal this decision.

On remand, the administrative panel again denied additional compensation to PCS. The panel found that none of PCS’s actions were reasonable and necessary and that any increased operational costs incurred as a result of the taking were minimal. PCS again appealed to the superior court. The court ruled that the panel violated its remand instructions from the initial appeal and erred in denying any additional compensation. The court determined that PCS was entitled to the cost of reconfiguring one piece of heavy equipment and increased costs of moving shred material that PCS had incurred up until it reconfigured the equipment. But PCS was not entitled to reimbursement for any other operational changes.

PCS appeals, seeking reimbursement for the cost of its full site reconfiguration. It argues that the panel’s decision violated the law of the case and was unsupported by substantial evidence, contrary to law, and arbitrary and capricious. The Port also filed a notice of appeal from the superior court’s decision but does not assign error to any aspect of the panel’s decision.

We hold that although the panel’s challenged factual findings were supported by substantial evidence, the panel erred in denying additional compensation to PCS because it misapplied the law. First, the panel was bound by the superior court remand order, which the Port did not appeal, to award some level of compensation beyond only reimbursement for moving personal property out of the condemned area. Second, although the panel’s findings were supported by substantial evidence, it was a misapplication of the law and arbitrary and capricious for the panel to reject some additional compensation when the panel established that the taking required periodic relocation of shred material and, therefore, the taking impacted PCS’s operations beyond simply necessitating a move of personal property out of the condemned area.

We reverse the panel’s decision in part and conclude that PCS is entitled to some additional compensation for reasonable and necessary relocation of shred material, as well as reasonable and necessary reconfiguration of one piece of equipment, the conveyor. The panel’s alternative findings establish that the amounts awarded by the superior court are appropriate. This matter is therefore remanded to the panel for entry of a final order awarding PCS $347,800 in expenses for reconfiguration of the conveyor and an additional $46,000 in tramming costs incurred to move shred material prior to reconfiguration, in addition to the $68,259 already paid. We otherwise affirm the panel’s decision rejecting all other claims. Consistent with the superior court’s order, the panel may consider any requests related to costs and fees.

FACTS

PCS operates a scrap metal recycling operation on land leased from the Port. Prior to the taking at issue in this case, PCS bought scrap metal and collected it at the north end of the property, where it fed the metal into a shredder. The machine broke the scrap metal into smaller pieces and separated ferrous and nonferrous material. Nonferrous shred was deposited into piles, while ferrous shred was conveyed through a “‘Z box,’” which filtered out impurities, to a picking station where employees checked for additional impurities. Clerk’s Papers (CP) at 6. At this point, a conveyor picked up the shred and deposited it into a large, partial annulus shaped “‘conveyor- stacked shred’” pile near the southern edge of the property. CP at 187. Depending on the size of this pile, PCS occasionally used front-end loaders to push some of the shred into another pile at the southwest corner of the property. Trucks entered the property from the east and then moved counterclockwise around the property, loading and unloading at various piles.

The Port condemned a 47,598-square foot strip of the 13-acre leasehold, left of the orange dotted line in the image below, of which 7,332 square feet was used by PCS for its operations. The condemned area overlapped with the truck traffic path and some of the area PCS used to pile shred material. The following image is a demonstrative exhibit depicting a portion of PCS’s operations prior to the taking, with the dotted line depicting the boundary of the taking:

Administrative Record (AR) at 1155. The condemnation required PCS to move its truck traffic path several feet to the north of where it was previously located, which then encroached into another area where PCS would pile shred material. Around 45 times a year, this shred pile grew big enough that it would block or partially block the new truck traffic path, creating a choke point.

The Port informed PCS of its right under federal and state law to receive financial assistance to relocate or reconfigure its operations in light of the taking. A relocation specialist for

the Port, Martyn Daniel, determined that PCS was eligible for reimbursement only for the cost of moving the shred and other materials out of the condemned area. The Port accordingly paid PCS $68,259.

PCS disputed the Port’s conclusion that it was entitled only to payment for moving personal property from the condemned area. PCS contended that the taking required more substantial changes to its operations to maintain the traffic path necessary for trucks to travel along the south side of the property, as well as the space necessary for piling shred. To make room for the relocation of the truck traffic path, PCS reconfigured the conveyor by turning it 90 degrees to the west and extending it 77 feet, and PCS built a new shred pad in the new conveyor-stacked shred location. The following is a demonstrative exhibit depicting a portion of PCS’s operations after the taking:

AR at 1160. In addition, PCS relocated a rail spur to the west, upgraded some storm water facilities, expanded and improved employee parking, added a new picking conveyor, and made substantial changes to its office space and the property entrance. Together these changes cost over $6.1 million.

PCS sought full reimbursement for all of these changes, arguing that they were all reasonable and necessary consequences of the taking. The Port rejected the claim. PCS appealed, and the Port convened a three-person panel to consider the evidence, hear testimony, and resolve the appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific Coast Shredding, Llc, Appellant/cross-res. v. Port Of Vancouver, Usa, Res/cross-app., (Wash. Ct. App. 2020).

Pacific Coast Shredding, Llc, Appellant/cross-res. v. Port Of Vancouver, Usa, Res/cross-app. (Pacific Coast Shredding, Llc, Appellant/cross-res. v. Port Of Vancouver, Usa, Res/cross-app.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Municipality of San Juan v. Rullan
318 F.3d 26 (First Circuit, 2003)
Tapper v. Employment Security Department
858 P.2d 494 (Washington Supreme Court, 1993)
Utter v. STATE, DEPT. OF SOC. & HEALTH SER.
165 P.3d 399 (Court of Appeals of Washington, 2007)
McCausland v. McCausland
118 P.3d 944 (Court of Appeals of Washington, 2005)
Roberson v. Perez
123 P.3d 844 (Washington Supreme Court, 2005)
Steven Lodis & Deborah Lodis v. Corbis Holdings, Inc.
192 Wash. App. 30 (Court of Appeals of Washington, 2015)
PacifiCorp v. Washington Utilities & Transportation Commission
376 P.3d 389 (Court of Appeals of Washington, 2016)
Karanjah v. Department of Social & Health Services
199 Wash. App. 903 (Court of Appeals of Washington, 2017)
Roberson v. Perez
156 Wash. 2d 33 (Washington Supreme Court, 2005)
In re the Marriage of McCausland
152 P.3d 1013 (Washington Supreme Court, 2007)
Cedar River Water & Sewer District v. King County
315 P.3d 1065 (Washington Supreme Court, 2013)
State ex rel. Smith v. Superior Court
128 P. 648 (Washington Supreme Court, 1912)
Attorney General's Office v. Utilities & Transportation Commission
116 P.3d 1064 (Court of Appeals of Washington, 2005)
In re the Marriage of McCausland
129 Wash. App. 390 (Court of Appeals of Washington, 2005)
Utter v. Department of Social & Health Services
140 Wash. App. 293 (Court of Appeals of Washington, 2007)
Herman v. Shorelines Hearings Board
204 P.3d 928 (Court of Appeals of Washington, 2009)
Bank of America, NA v. Owens
311 P.3d 594 (Court of Appeals of Washington, 2013)
Morawek v. City of Bonney Lake
337 P.3d 1097 (Court of Appeals of Washington, 2014)
B&R Sales, Inc. v. Department of Labor & Industries
344 P.3d 741 (Court of Appeals of Washington, 2015)