P. J. Carlin Const. Co. v. Guerini Stone Co.

241 F. 545, 154 C.C.A. 321, 1917 U.S. App. LEXIS 1788
CourtCourt of Appeals for the First Circuit
DecidedApril 2, 1917
DocketNo. 1256
StatusPublished
Cited by5 cases

This text of 241 F. 545 (P. J. Carlin Const. Co. v. Guerini Stone Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. J. Carlin Const. Co. v. Guerini Stone Co., 241 F. 545, 154 C.C.A. 321, 1917 U.S. App. LEXIS 1788 (1st Cir. 1917).

Opinion

BINGHAM, Circuit Judge.

This is a writ of error from a judgment, in favor of the Guerini Stone Company against the P. J. Carlin Construction Company, entered in the United States District Court for Porto Rico, in an action brought by the former against the latter io recover damages for an alleged breach of contract. The case has been twice tried before a jury, and each time a verdict has been found in favor of the plaintiff. At the conclusion of the first trial the plaintiff, feeling aggrieved in the amount of the verdict, prosecuted a writ of error to the Supreme Court, and a new trial was granted. The opinion of the court is reported in 240 U. S. 264, 36 Sup. Ct. 300, CO L. Ed. 636, where a general statement of the case will be found.

The grounds upon which the new trial was granted were: (1) That the obligations of the defendant under the eleventh paragraph of the contract were unduly limited and practically annulled by the rulings of the trial judge; that it was error to read into the subcontract, to which the plaintiff and defendant were parties, certain provisions contained in the general contract, between the defendant and the government, and relieve the defendant from liability for damages due to delays resulting from “the action of the representatives of the government in changing foundations” or “in suspending or stopping the work”; (2) that the ruling of the trial court — that “if there was delay in the furnishing of the granite, there could have been no liability under the sulxmntract for such delay in money, but such a condition was to be remedied by an extension of time for completion as therein provided” — was error; that paragraph 11 of the subcontract bound the “defendant to reimburse plaintiff for any loss caused by delay resulting from defendant’s failure to provide labor and material not included in the subcontract,” and for loss caused by delay in providing granite and foundations; that the extension of time provided for in paragraph 7 was inserted for the purpose of relieving the subcontractor from “liability to liquidated damages imposed upon [him] * * * by paragraph 6 for failure to complete his work within the time therein limited,” and could not “properly be construed to deprive him of his right under paragraph 11 to reimbursement for losses attributable to delays assumed by the general contractor”; and (3) that the court erred in excluding an “estimate of the total cost to plaintiff of the doing of the work called for in the subcontract,” to the effect that it could he done for $53,012 and at a profit of $9,700; that profits based on such testimony were not contingent and speculative, and that “no more definite or certain method of estimating profits could well be adopted than to deduct from the contract price the probable cost of furnishing the materials and doing the work.” These were the grounds upon which the judgment was vacated.

[548]*548The court, however, passed upon alleged errors assigned to the refusal of the trial judge to instruct the jury in accordance with two requests for rulings, as to both of which it held there was no error. The first of these requests was held to have been properly refused, on the ground that the evidence failed to show that the requisitions, which the plaintiff was bound by the contract to submit before payments could be required, were based upon the cost of actual work erected, or that a unit price had been agreed upon that *might be employed in making up the requisitions.” And the other request was held to have been properly refused for the reason that its application had not been “confined to the case of the plaintiff being found entitled to' recover upon the theory that the contract was rightfully terminated by the notice of May 22, 1912”; that other grounds of action were declared on to which the instruction would not be applicable.

In the concluding paragraph of,the opinion, the court said:

“Exceptions were taken to tbe refusal of certain other instructions requested by plaintiff with tbe object of basing a recovery of damages, including profits, upon tbe ground of plaintiff having been prevented by defendant’s acts from performing its contract within tbe time specified or a reasonable extension thereof, or on tbe ground that defendant’s refusal to make payments and other breaches of contract were so unreasonable and inexcusable as to indicate an inability or unwillingness on its part to carry out tbe contract or to amount to a refusal- to perform it in tbe future, sue % as to justify plaintiff in stopping worlc. But these exceptions have not been fully argued, and tbe requests are perhaps wanting in accuracy; hence we pass them without consideration.”

It is apparent, therefore, that the Supreme Court did not pass upon the question whether the plaintiff was justified in declining to go on and complete the work under the contract, either because of the defendant’s alleged failure to make payments as required by the contract, or because of the alleged prevention of performance of the contract by the plaintiff, within the time specified or a reasonable extension thereof, through delays attributable to the- defendant.

The present writ of error is prosecuted by the defendant. Many errors are assigned, but the only available ones relate to the admission or exclusion of evidence and to instructions which were given to the jury or refused.

The evidence discloses that, on the 22d day of May, 1912, the plaintiff wrote the defendant, notifying it that it terminated the contract, would proceed no further with the work and should hold defendant liable for damages for its breach.

One of the grounds on which the action proceeded was that the plaintiff had been prevented from performing its contract within the time agreed upon or a reasonable extension thereof, through defendant’s delay in providing the foundations of the building, in furnishing the granite to erect the basement walls, and in stopping plaintiff’s work on the 9th of March, 1912, until the foundations were underpinned, and that, because of this, the-plaintiff was justified in declining to go on and complete its work under the contract.

As bearing upon this view of the case, the defendant requested the court to charge the jury that the plaintiff was not justified in terminat[549]*549mg the contract because of delays. This request was refused and the defendant excepted. It is covered by assignment of error No. 41. _

[1] Whether these delays constituted a breach which would entitle the plaintiff to maintain an action for damages under paragraph 11 of the contract, provided it went on, or held itself ready to go on, and complete the work, or whether they constituted a breach which would justify the plaintiff in declining to go on and perform the balance of the work, are, in view of the terms of the contract, quite different propositions. It is plain, as held by the Supreme Court, that under paragraph 11 of the contract the defendant would be liable to respond in damages for delays in the material progress of plaintiff’s work attributable to defendant’s failure to provide labor and materials, and to its failure to provide foundations and granite, if-plaintiff completed, or stood ready to complete, its contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LeRoy Dyal Co. v. Allen
161 F.2d 152 (Fourth Circuit, 1947)
United States v. Harris
100 F.2d 268 (Ninth Circuit, 1938)
Vulcan Trading Corp. v. Kokomo Steel & Wire Co.
268 F. 913 (Seventh Circuit, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
241 F. 545, 154 C.C.A. 321, 1917 U.S. App. LEXIS 1788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-j-carlin-const-co-v-guerini-stone-co-ca1-1917.