P C L Civil Constructors Inc v. F J Burnell Inc

CourtDistrict Court, W.D. Louisiana
DecidedApril 9, 2020
Docket5:19-cv-00195
StatusUnknown

This text of P C L Civil Constructors Inc v. F J Burnell Inc (P C L Civil Constructors Inc v. F J Burnell Inc) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P C L Civil Constructors Inc v. F J Burnell Inc, (W.D. La. 2020).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA SHREVEPORT DIVISION

PCL CIVIL CONSTRUCTORS, INC. CIVIL ACTION NO. 5:19-CV-00195

VERSUS JUDGE TERRY A. DOUGHTY

F.J. BURNELL, INC. MAG. JUDGE MARK L. HORNSBY

RULING Plaintiff PCL Civil Constructors, Inc., (“PCL”) sued Defendant F.J. Burnell, Inc., (“Burnell”) for breach of contract. Pending here is PCL’s Motion for Partial Summary Judgment [Doc. No. 15]. Burnell has filed an opposition [Doc. No. 19]. PCL has filed a reply to the opposition [Doc. No. 20]. For the following reasons, the Motion for Partial Summary Judgment is GRANTED. I. FACTS PCL entered into a Prime Contract dated June 23, 2014, with the Louisiana Department of Transportation and Development (“LADOTD”), to furnish certain material, labor, and services necessary for the construction of a road project related to Interstate 49 in Caddo Parish, Louisiana (“the Project”). PCL entered into a Subcontract Agreement (“the Subcontract”) with Burnell in the original amount of $9,836,247.40, whereby Burnell was required to perform a certain scope of the Prime Contract work. With additional revisions that changed the scope of work, the final Subcontract sum totaled $10,012,279.55. With certain back charges claimed by PCL in the amount of $351,656.88, the final revised Subcontract sum was $9,660,622.67. PCL contends that, mainly because of Burnell’s failure to pay its subcontractors and suppliers, PCL was forced to make total payments of $10,387,461.28 for the work that Burnell was to perform under the Subcontract, rather than the final revised Subcontract sum of $9,660,622.67, a difference of $726,838.61. On February 15, 2019, PCL filed this lawsuit against Burnell, in which it contends that it

is entitled under the provisions of the Subcontract to recover this $726,838.61 in payments above and beyond the revised final Subcontract sum that it made, in addition to other damages for Burnell’s alleged breach of the Subcontract, interest, and attorney’s fees. On March 4, 2020, PCL filed the pending motion seeking a partial summary judgment for the $726,838.61. PCL reserves all rights to seek any remaining damages, interest, and attorney’s fees at trial. Burnell responds that most, if not all, of the added expenses claimed by PCL were caused by early delays in the project for which Burnell is not responsible. The motion is fully briefed, and the Court is prepared to rule.

II. LAW AND ANALYSIS A. Standard of Review Under Federal Rule of Civil Procedure 56(a), A[a] party may move for summary judgment, identifying each claim or defense--or the part of each claim or defense--on which summary judgment is sought. The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.@ The moving party bears the initial burden of informing the court of the basis for its motion by identifying portions of the record which highlight the absence of genuine issues of material fact. Topalian v. Ehrmann, 954 F.2d 1125, 1132 (5th Cir. 1992); see also Fed. R. Civ. P. 56(c)(1) (AA party asserting that a fact cannot be . . . disputed must support the assertion by . . . citing to particular parts of materials in the record . . . ). A fact is Amaterial@ if proof of its existence or nonexistence would affect the outcome of the lawsuit under applicable law in the case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A dispute about a material fact is Agenuine@ if

the evidence is such that a reasonable fact finder could render a verdict for the nonmoving party. Id. If the moving party can meet the initial burden, the burden then shifts to the nonmoving party to establish the existence of a genuine issue of material fact for trial. Norman v. Apache Corp., 19 F.3d 1017, 1023 (5th Cir. 1994). In evaluating the evidence tendered by the parties, the Court must accept the evidence of the nonmovant as credible and draw all justifiable inferences in its favor. Anderson, 477 U.S. at 255. However, “a party cannot defeat summary judgment with conclusory allegations, unsubstantiated assertions, or only a scintilla of evidence.” Turner v. Baylor Richardson Med. Ctr., 476 F.3d 337, 343 (5th Cir. 2007) (citing Anderson, 477 U.S. at 248.)

B. Analysis Under Louisiana law, the contract is “the law between the parties” and “is read for plain meaning.” In re Liljeberg Enters., Inc., 304 F.3d 410, 439 (5th Cir. 2002) (quoting Nat’l Union Fire Ins. Co. v. Circle, Inc., 915 F.2d 986, 989 (5th Cir. 1990)). Therefore, when the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties’ intent. Id. The Court need not look beyond the four corners of the contract to determine the mutual intent of the parties. Liberty Mut. Ins. Co. v. Pine Bluff Sand & Gravel Co., 89 F.3d 243, 246 (5th Cir.1996). PCL has submitted as summary judgment evidence the Affidavit of Dustin Guszkiewicz, PCL’s Project Manager for the Project. [Doc. No. 15-4]. Attached to the Affidavit as Exhibit “A” is a copy of the Subcontract. Exhibit “B” establishes that additional revisions changed the scope of the work, making the final Subcontract sum total $10,012,279.55; and, that certain back charges in the amount of $351,656.88 resulted in the final revised Subcontract sum to be

$9,660,622.67. Exhibit C to the Guszkiewicz Affidavit is a spreadsheet listing the payments made by PCL totaling $10,387,461.28 for the work Burnell was to perform under the Subcontract and establishing that PCL has expended $726,838.61 beyond the revised Subcontract sum of $9,660,622.67. Exhibit D establishes that, in some instances, liens had been filed and/or demands for payment had been made by Burnell’s subcontractors or suppliers for certain amounts that Burnell was responsible for paying. PCL additionally attaches portions of the deposition of Grover W. Netherton

(“Netherton”), owner of Burnell, to show that he acknowledged PCL’s contractual right to assert back charges in its deposition and further acknowledged that the contractual right was never waived or modified. [Doc. Nos. 15-5,6]. PCL points to specific provisions of the Subcontract which give it a contractual right to back charge Burnell and to recover certain monies expended by PCL from Burnell. For example, under Article 5 of the Uniform Conditions of Subcontract (“the Uniform Conditions”), PCL has the unilateral right to deduct the costs of work it performed to remediate defective work performed by Burnell if Burnell fails to remedy the deficiency. [Doc. No. 15-4, pp 13,14]. Under Article 6.4 of the Uniform Conditions, PCL has the unilateral right to deduct its costs of clean-up if, after notice, Burnell fails or refuses to perform the clean-up work itself. [Id., p. 14]. Under Article 9 of the Uniform Conditions, PCL is empowered to withhold and/or back charge Burnell for a variety of enumerated reasons. [Id., pp. 15, 16]. Also, Article 9 of the Uniform Conditions provides that Burnell agreed to timely pay all amounts due its sub-subcontractors and suppliers, and that PCL could make payment to Burnell

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
P C L Civil Constructors Inc v. F J Burnell Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-c-l-civil-constructors-inc-v-f-j-burnell-inc-lawd-2020.