OXY USA, Inc. v. Southwestern Energy Production Co.

161 S.W.3d 277, 2005 WL 851940
Court of Appeals of Texas·Decided May 19, 2005·No. 13-03-00075-CV·Published·Cited by 18 cases

Opinion

OPINION

Opinion by

Justice HINOJOSA.

This case involves an indemnity agreement between two major oil and gas companies. After both parties filed motions for summary judgment, the trial court granted the motion of appellee, Southwestern Energy Production Company (“SEPCO”) and denied the motion of appellant, OXY USA, Inc. (“OXY”). In four issues, OXY contends the trial court erred in granting SEPCO’s motion for summary judgment and in denying its motion for summary judgment. We reverse and render.

A. BACKGROUND AND PROCEDURAL HISTORY

On June 5, 1997, OXY and SEPCO entered into a Seismic and Exploration Agreement (“SEA”), effective March 27, 1997, to conduct seismic surveys on an area of land referred to as the “Bouré project.” The SEA provided that: (1) OXY and SEPCO would equally share costs for the acquisition and development of three-dimensional seismic data; (2) OXY would receive fifty percent of the rights in seismic agreements and oil and gas leases relating to the project; and (3) OXY and SEPCO would each receive a license to the seismic data acquired. The SEA further provided that OXY and SEP-CO would mutually approve the selection of a contractor to process the seismic data.

Unbeknownst to OXY, SEPCO had previously entered into a letter agreement (“Skelly Letter Agreement”) with Skelly Exploration Company, owned by Denny Whinery (collectively “Skelly”), a consultant to SEPCO. The letter agreement, dated December 16, 1996, provided that SEPCO and Skelly would jointly market a three-dimensional seismic program for the Bouré project. SEPCO would receive a twenty-five percent working interest in all permits, options, leases and data processing, as well as a standard license to the resulting seismic data. Any additional promoted interest or promoted cash would be owned and retained by Skelly.

*281 Also unknown to OXY, on April 29,1997, SEPCO entered into an agreement (“Seitel Agreement”) with a seismic contractor, Seitel Data Limited (“Seitel”), which provided, in part, that SEPCO would purchase four nonexclusive licenses to the Bouré project seismic data. OXY and Skelly were each designated as recipients of a license.

Shortly after OXY and SEPCO entered into the SEA, SEPCO’s parent company, Southwestern Energy Company, conducted an internal investigation of SEPCO. After the investigation, all of SEPCO’s senior management were either terminated or resigned. During the investigation, Southwestern Energy discovered inconsistencies between the SEA and the Seitel Agreement. Upon investigation, Southwestern Energy concluded that OXY was unaware of both the Skelly Letter Agreement and the Seitel Agreement.

Following disclosure of the inconsistent agreements, OXY informed SEPCO that because SEPCO had breached the SEA, OXY would not proceed under the agreement unless Skelly was removed from the project. OXY also voiced concerns regarding potential claims by Skelly if the deal were renegotiated to eliminate Skelly’s participation. In response to OXYs concerns, SEPCO offered to indemnify OXY against any claims relating to the Bouré project.

On October 16, 1997, SEPCO, OXY, and Seitel entered into a new agreement (“New Bouré Agreement”). Under this agreement, OXY and SEPCO agreed to each contribute twenty-five percent of the costs of the seismic shoot; in return, each company would receive one of four licenses to the data and a fifty percent interest in the Bouré project. SEPCO and OXY would jointly designate the recipients of the two remaining licenses. Skelly was not named as a recipient of a license. On December 11, 1997, SEPCO and OXY entered into a Joint Prosecution and Indemnification Agreement (“Indemnity Agreement”) in order to alleviate OXY’s concern that Skelly might claim an interest in the Bouré project.

Before entering into the Indemnity Agreement, SEPCO filed suit in federal court on October 31, 1997, against Whin-ery, Skelly, and others, including former employees of SEPCO, for fraud and violations of the Racketeer Influenced and Corrupt Organizations Act. 1 On June 23, 1998, Skelly counterclaimed against SEPCO for breach of contract, defamation, and tor-tious interference with prospective economic gain. On June 16, 1999, SEPCO settled the lawsuit with Skelly and executed a mutual release of claims relating to the Bouré project. The release failed to include OXY.

Skelly subsequently sued OXY, alleging tortious interference with contract, conversion, and abuse of rights. By letter dated November 16, 1999, OXY notified SEPCO that it had been sued by Skelly, and requested that SEPCO defend and indemnify OXY in accordance with the Indemnity Agreement. SEPCO responded, without reservation of rights, that it would defend OXY. SEPCO assumed payment for OXY’s selected defense counsel, and provided OXY with access to SEPCO’s own local outside counsel. However, on the eve of trial, on June 16, 2000, SEPCO asserted it was not obligated to indemnify OXY under the Indemnity Agreement. OXY settled the lawsuit with Skelly for $2.5 million plus a license to the seismic data. SEPCO contributed $400,000 and the license.

After settling with Skelly, OXY filed suit against SEPCO, alleging breach of con *282 tract and fraudulent inducement. SEPCO counterclaimed for a declaratory judgment that the Indemnity Agreement did not cover the claims asserted by Skelly, and, in the alternative, that the Indemnity Agreement was unenforceable. SEPCO later added a counterclaim for fraud, alleging that it agreed to defend OXY without knowing that on April 27, 1998, OXY had conveyed most of its interest in the Bouré project to Petro-Hunt, L.L.C., but had reserved its rights under the Indemnity Agreement.

Both parties filed motions for partial summary judgment. The trial court denied OXY’s motion and granted SEPCO’s motion on the grounds that the Indemnity Agreement was unenforceable under Texas law and that OXY did not have a right to receive indemnity from SEPCO based on Skelly’s claims. The trial court later severed the contract claims from the remaining claims, making the summary judgment final.

B. STANDARD OF REVIEW

We review the granting of a motion for summary judgment de novo. See Natividad, v. Alexsis, Inc., 875 S.W.2d 695, 699 (Tex.1994); Tex. Commerce Bank-Rio Grande Valley v. Correa, 28 S.W.3d 723, 726 (Tex.App.-Corpus Christi 2000, pet. denied). For summary judgment to be proper, the evidence must establish as a matter of law that there is no genuine issue of material fact as to any of the essential elements of the plaintiffs cause of action, or that the defendant has conclusively established all elements of an affirmative defense. Walker v. Harris, 924 S.W.2d 375, 377 (Tex.1996); Crain v. Smith, 22 S.W.3d 58, 59 (Tex.App.-Corpus Christi 2000, no pet.). In deciding whether to sustain a summary judgment, we accept all evidence favorable to the non-movant as true, and make all reasonable inferences and resolve all doubts in the non-movant’s favor. Am. Tobacco Co. v. Grinnell, 951 S.W.2d 420, 425 (Tex.1997).

Free access — add to your briefcase to read the full text and ask questions with AI

OXY USA, Inc. v. Southwestern Energy Production Co., 161 S.W.3d 277, 2005 WL 851940 (Tex. Ct. App. 2005).

161 S.W.3d 277 (OXY USA, Inc. v. Southwestern Energy Production Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jerry L. Hamblin and Ricochet Energy, Inc. v. Thomas A. Lamont
433 S.W.3d 51 (Court of Appeals of Texas, 2013)
In Re Estate of Anderegg
360 S.W.3d 677 (Court of Appeals of Texas, 2012)
in the Estate of Melvin J. Anderegg
Court of Appeals of Texas, 2012
SETTLEMENT CAPITAL CORPORATION, INC. v. Pagan
649 F. Supp. 2d 545 (N.D. Texas, 2009)
A2D Technologies Inc v. MJ Systems Inc, et
269 F. App'x 537 (Fifth Circuit, 2008)