Owens-Corning Fiberglas Corp. v. Fox Smith Sheet Metal Co.

351 P.2d 516, 56 Wash. 2d 167, 1960 Wash. LEXIS 327
CourtWashington Supreme Court
DecidedApril 28, 1960
Docket35071
StatusPublished
Cited by9 cases

This text of 351 P.2d 516 (Owens-Corning Fiberglas Corp. v. Fox Smith Sheet Metal Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Owens-Corning Fiberglas Corp. v. Fox Smith Sheet Metal Co., 351 P.2d 516, 56 Wash. 2d 167, 1960 Wash. LEXIS 327 (Wash. 1960).

Opinion

Hunter, J.

— This is an appeal from a judgment for the plaintiff entered in an action for breach of contract. The action instituted by the plaintiff, Owens-Corning Fiberglas Corporation, against the defendants, Fox Smith Sheet Metal Company and the United Pacific Insurance Company, arose out of the following facts.

The Bechtel Corporation entered into a contract with the Shell' Oil Company to build a refinery at Anacortes, Washington. One phase of the construction involved covering the refinery structures with insulating material and aluminum sheeting. The plaintiff company, while negotiating with the Bechtel Corporation for the insulation subcontract, dispatched invitations to bid on the sheet metal phase of the insulation work to the defendant sheet metal company and two other sheet metal firms.

To facilitate the preparation of its bid, the defendant sent one Paul R. Inman, an experienced engineer and estimator, to plaintiff’s Los Angeles office. Upon his arrival, Inman conferred with plaintiff’s contract manager and was provided with all the plans and specifications which had been furnished by the Bechtel Corporation. Before leaving Inman submitted a tentative cost figure, which members of the plaintiff’s staff thought to be lower than practical. Pursuant to their suggestion, the prices per unit were raised, but subsequently the parties agreed all prices appearing on the bid would be reduced fifteen per cent. On February 8,1955, the defendant submitted a bid based upon the plans and specifications, quoting total and unit prices for the work to be performed.

Plaintiff replied to defendant’s proposal on February 17, 1955, as follows:

"...
“This letter is to serve as our interim Purchase Order and is a letter of intent which should serve as prospective authorization for you to purchase and fabricate metal mate *169 rials in strict accordance with your letter of February 8, 1955. A firm Purchase Order will he forwarded to you within five days from this date.” (Italics ours.)

The subcontract between the Bechtel Corporation and the plaintiff was entered into on February 15, 1955. On March 15, 1955, a job conference was held at the job site, which was attended by representatives of the Shell Oil Company, the Bechtel Corporation, and the plaintiff and defendant companies. During the latter part of April some of the materials for the job, which had been prefabricated in the defendant’s Spokane shop, were shipped to the job site. Plaintiff’s foreman went to Anacortes about the first of May, but it was later in the month when the insulation and sheet metal work actually commenced.

Mr. John Smith, president of the defendant company, visited the project site on June 13, 1955. Subsequently, in a letter, dated June 20, 1955, to the plaintiff, he expressed surprise at finding that many tanks had stairways and platforms installed, and stated that this required a substantial amount of additional cutting and fitting, not included in the original plans and specifications, and not contemplated in the defendant’s bid. He went on to inform the plaintiff that this would make it impossible to perform at the original bid price, but that he would be willing to negotiate a new price.

On July 7, 1955, following a meeting with the manager of the plaintiff’s Los Angeles office, Mr. Smith wrote to the plaintiff corporation and informed it that defendant’s original bid would have to be increased thirty-six thousand dollars. This was refused by the plaintiff and, on July 11, 1955, the defendant withdrew from the project.

The plaintiff then entered into a contract with another firm to complete the sheet metal work. Subsequently, the plaintiff commenced this action for breach of contract. The defendant Sheet Metal Company cross-complained seeking recovery on a quantum meruit basis for work done prior to leaving the project. Judgment was entered for the plaintiff and against the defendant on its cross-complaint. Additional testimony was taken to determine the amount the *170 defendant was to be allowed as compensation for extra work, which sum was deducted from the amount of damages awarded to the plaintiff. The defendant companies appeal.

The sole question essential to a disposition of this appeal is whether a valid contract ever existed between the appellant sheet metal company and the respondent.

The trial court found that the appellant’s offer was accepted by the respondent’s letter of February 17, 1955, and the parties intended and understood that the appellant’s proposal of February 8th, and respondent’s acceptance of February 17th, constituted a binding contract. The record does not support these findings of the trial court.

An acceptance of an offer must always be identical with the terms of the offer or there is no meeting of the minds and no contract. Blue Mountain Constr. Co. v. Grant County School Dist., 49 Wn. (2d) 685, 306 P. (2d) 209 (1957); Ferris v. Blumhardt, 48 Wn. (2d) 395, 293 P. (2d) 935 (1956). The respondent’s letter of February 17, 1955, expressly states it is only a temporary order to be followed in five days by a firm order. At the end of the five-day period the appellant’s offer was still in existence, and capable of being accepted, but no “firm” purchase order was transmitted by respondent. The next correspondence between the parties was respondent’s letter of March 8, 1955, advising appellant of the pending job conference and containing the following language:

"...
“Bechtel was not particularly satisfied with the details which you submitted and we also believe that we can do the work for less money than would be the case with the details you submitted. Consequently, we proceeded with details here copies of which I am forwarding you under separate cover Air Mail today.
“Friday, March 4th, I met with Bechtel engineers in San Francisco regarding these details and have tentative approvals at this particular moment. We would suggest you look these over and be prepared to discuss them thoroughly with us on the coming Monday so that when we enter into the job conference we will be agreed amongst ourselves at *171 least as to what we can or cannot do. Will you please advise me Air Mail at once if this will suit your plans.
“We have not finalized a purchase order for you since we think it would be more fitting to do so after we meet Monday and Tuesday. ...”

It seems apparent from the language of this letter that the respondent only intended to enter into a “firm” agreement when and if the details were worked out at the ensuing conference.

Later correspondence between the parties indicate clearly that the conference had left details unresolved, or that new uncertainties had subsequently arisen. On May 11, 1955, the respondent sent the following letter to appellant:

"...
“Enclosed please find latest revised prints. These revisions have been based upon recommendations over our various additions by Bechtel engineering forces.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lambert v. Kysar
First Circuit, 1993
Multicare Medical Center v. Department of Social & Health Services
790 P.2d 124 (Washington Supreme Court, 1990)
City of Roslyn v. Paul E. Hughes Construction Co.
24 Cont. Cas. Fed. 82 (Court of Appeals of Washington, 1978)
Koller v. Flerchinger
441 P.2d 126 (Washington Supreme Court, 1968)
Banks v. Crescent Lumber & Shingle Co.
379 P.2d 203 (Washington Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
351 P.2d 516, 56 Wash. 2d 167, 1960 Wash. LEXIS 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/owens-corning-fiberglas-corp-v-fox-smith-sheet-metal-co-wash-1960.