City of Roslyn v. Paul E. Hughes Construction Co.

24 Cont. Cas. Fed. 82, 573 P.2d 385, 19 Wash. App. 59, 1978 Wash. App. LEXIS 2066
CourtCourt of Appeals of Washington
DecidedJanuary 11, 1978
Docket2123-3
StatusPublished
Cited by7 cases

This text of 24 Cont. Cas. Fed. 82 (City of Roslyn v. Paul E. Hughes Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Roslyn v. Paul E. Hughes Construction Co., 24 Cont. Cas. Fed. 82, 573 P.2d 385, 19 Wash. App. 59, 1978 Wash. App. LEXIS 2066 (Wash. Ct. App. 1978).

Opinion

Green, J.

Defendants appeal from a judgment for damages in favor of plaintiff, City of Roslyn, for breach of contract. The controlling issue presented is whether a valid and enforceable contract was created between the parties. We reverse.

In April 1972, the City of Roslyn (City) issued a public call for bids for construction of a sewage collection and *60 treatment system. Hughes Construction Company (Hughes) submitted a bid proposal in accordance with the bid call. The bid documents expressly included and incorporated the terms and conditions of the notice and instructions to bidders, the construction contract, and the detailed specifications and plans. According to these documents, the City reserved the right to delay the award of the contract, even though the bid opening was June 5, 1972:

No bidder may withdraw his bid after the hour set for the opening thereof, or before the award of contract, unless said award is delayed for a period exceeding sixty (60) days.

The notice and instructions to bidders provided:

5. The party to whom the contract is awarded will be required forthwith to execute the contract and a performance and payment bond within 10 calendar days from the date when the written notice of award of the contract is mailed to the bidder at the address given by him. . . .
6. It is understood that the work to be done is being financed with a loan or grant or both from the Farmers Home Administration, U.S. Department of Agriculture. Contractors' proposals shall hold firm for 60 days to allow the owner to complete its financing arrangements. Mutually agreed upon extensions of time may be made, if necessary.
16. For the purpose of clarification it is understood that the work to be done is being financed in whole or in part by means of a loan and grant made or insured by the United States acting through the Farmers Home Administration of the Department of Agriculture. The Farmers Home Administration will, therefore, require approval by its representatives of all contracts, attachments, and, similar documents, all partial and final payment estimates, and all change orders.

(Italics ours.)

Hughes submitted its bid proposal on the form provided in the bid documents. It contained the following terms:

2. The undersigned bidder does hereby declare and stipulate that this proposal is made in good faith . . . and that it is made in pursuance of and subject to all *61 the terms and conditions of the notice and instructions to bidders, the construction contract, the detailed specifications, and the plans pertaining to work to be done, all of which have been examined by the undersigned.
4. The undersigned bidder agrees to execute the contract and a performance bond for the total of this bid within 10 calendar days from the date when the written notice of the award of contract is delivered to him at the address given on this proposal.

The foregoing provisions of the bid documents clearly provide that a bid could not be withdrawn for 60 days "to allow the owner [City] to complete its financing arrangements" with FHA. It is also clear that any extensions of the 60-day time limit were to be "mutually agreed upon." Further, the documents notified the bidder that FHA approval of all "contracts, attachments, and similar documents, all partial and final payment estimates, and all change orders" would be required.

On August 4, 1972, the 60th day after the bid opening date, the City sent a written notice of award to Hughes, the low bidder. This notice was identical to the form of the notice of award set forth in the bid documents; except, it contained the following additional terms:

Because of need to obtain modification of building right-of-way permits, without which FHA's necessary approval and acceptance of the contract cannot be secured, there may be a delay. As you know, in the notice and instructions to bidders and in the contract documents the award and letting of the contract cannot be made without approval and acceptance of the FHA.
Since there may be a delay, you need not submit the necessary contract performance and payment bond and insurance until required by FHA or until FHA approves and accepts this award of contract, whichever is earlier.
If there is a delay, in fairness to you the City of Roslyn will not require you to work on the project between October 15, 1972 and May 15, 1973, and will extend the completion date accordingly.

*62 After receipt of this notice, Hughes informed the City that because there were serious uncertainties relating to the length of time that may be taken by FHA, the notice should contain language to protect it in the event the delay would force construction well into the next year, increasing the cost of materials, supplies and labor. However, if FHA approval was given in time to start the project by August 30, 1972, Hughes offered to accept the contract. No change in the notice was made by the City regarding these requests. Subsequently, on August 22, Hughes informed the City that it was withdrawing its bid and would not execute the contract.

Some time thereafter, the City prepared new bid documents and a call for bids. The construction contract was awarded to a different contractor, and the project was finally completed at a greater cost to the City than the bid proposed by Hughes, partially due to changes in the plans and specifications. The City commenced this action for damages for breach of contract.

The trial court determined that Hughes' bid constituted an offer to contract and the written notice of award was a valid acceptance of this offer. In support of this determination, the court found that the notice was substantially as set forth in the contract documents, added no new conditions or requirements, merely reminded Hughes that the contract required approval by FHA, extended the completion date bid omitting October 1972 to May 1973, and allowed Hughes to defer submission of the necessary bonds. The trial court concluded that Hughes breached the contract and awarded damages to the City. 1

*63 First, defendants contend the court erred in determining that the notice of award was a valid acceptance of the bid proposal, an offer, and as such, created a contract. They argue that the notice set forth new conditions which constituted a material variance from its offer and, consequently, was a counteroffer it could properly reject. Defendants claim the notice was an attempt to (1) secure a bid award for holding purposes until financing arrangements with FHA were complete, and (2) make a tender of time extensions beyond the 60-day limit.

On the other hand, the City argues that a delay for FHA approval was an express condition contained in the original offer and call for bids and any reference in the notice to FHA approval was merely a reminder of that condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travis v. Tacoma Public School Dist.
85 P.3d 959 (Court of Appeals of Washington, 2004)
Travis v. Tacoma Public School District
120 Wash. App. 542 (Court of Appeals of Washington, 2004)
Sea-Van Investments Associates v. Hamilton
881 P.2d 1035 (Washington Supreme Court, 1994)
Northwest Television Club, Inc. v. Gross Seattle, Inc.
640 P.2d 710 (Washington Supreme Court, 1982)
Northwest Television Club, Inc. v. Gross Seattle, Inc.
612 P.2d 422 (Court of Appeals of Washington, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
24 Cont. Cas. Fed. 82, 573 P.2d 385, 19 Wash. App. 59, 1978 Wash. App. LEXIS 2066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-roslyn-v-paul-e-hughes-construction-co-washctapp-1978.