Otto Misch Co. v. E. E. Davis Co.

217 N.W. 38, 241 Mich. 285, 1928 Mich. LEXIS 982
CourtMichigan Supreme Court
DecidedJanuary 3, 1928
DocketDocket Nos. 47, 48.
StatusPublished
Cited by11 cases

This text of 217 N.W. 38 (Otto Misch Co. v. E. E. Davis Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otto Misch Co. v. E. E. Davis Co., 217 N.W. 38, 241 Mich. 285, 1928 Mich. LEXIS 982 (Mich. 1928).

Opinion

McDonald, J.

.These two cases were tried together in the court below and are here in the same record. They will be disposed of in one opinion. In the first case, the plaintiff entered into a contract with the board of education of the city of Detroit for the erection *288 of the Lynch sehoolhouse. A guaranty was required that the construction of the roof, which was designed for a playground, should be in accordance with the plans and specifications, without defects in workmanship and materials, and would not leak for a period of ten years after completion. The plaintiff sublet the construction of the roof to the defendant, the E. E. Davis Company. The Davis Company furnished the required guaranty in the form of. a letter directed to the plaintiff, which the plaintiff also signed and filed with the clerk of the board of education. After the roof was completed, leaks developed in many places. The defendant was notified but disclaimed any responsibility for the condition of the roof, on the ground that it had been constructed in accordance with the plans and specifications prepared by the architect of the board of education. The board made necessary temporary repairs and later laid an entirely new roof over that put on by the defendant. The Otto Misch Company was called upon to pay the amount so expended and did so. It then began this suit against the E. E. Davis Company to recover the amount which it had paid.

In the second case, the main facts are substantially the same. John Bollin Company secured a contract to build two schoolhouses, known as the Noble school and the Brady school. The Southern Surety Company was the surety on its bond. The roof construction was sublet to the E. E. Davis Company. A guaranty, similar to that in the Otto Misch Company case, was given and the work was performed, with the same results. The board of education made temporary repairs and the surety company reimbursed it and began this suit to recover the amount paid. The two cases were tried together by the court without a jury. Findings of fact and law were filed, on which judgments were entered in favor of both plaintiffs. The defendant has brought error.

*289 The first question presented is that the findings are “against the manifest weight of the evidence.”
“The law is well settled in this case that a trial judge’s findings of fact take the place of a verdict by a jury, and ordinarily will not be disturbed if there is evidence in the record to support them.” Atlas v. Gunsberg Packing Co., 240 Mich. 141.

The findings complained of are, substantially, that the roofs were not built according to the plans and specifications; that, because of defects in workmanship and materials, the roofs leaked, and that the repairs made by the board of education were necessary and were reasonably worth what was charged therefor. It will not be necessary to detail the testimony which influenced the trial judge in reaching his findings on the facts. A brief reference to some of the evidence will suffice. Mr. Fred Laffrey was a witness for the plaintiff. He had 22 years of experience with work of this kind. He was superintendent and inspector for the architect while these roofs were being constructed by the E. E. Davis Company. He testifies that the plans and specifications were not followed, that he so informed the defendant’s foreman and superintendent, and was told that they were following their own method and had guaranteed the results. He says that because of the manner in which they performed the work:

“When the thaw came in January we had lots of rain and one day I went up there and the people called me upstairs and we had four or five washtubs in the various rooms and large sections of the plaster were loosened and things were in bad shape from the leaks and the water came through, poured through.”

His testimony was supported by that of other witnesses of equal credibility. On the part of the defendant, it is a significant fact that neither the superintendent nor foreman in charge of the work was *290 called to testify. The only witness who testified that the work was done according to the plans and specifications was Mr. Davis, the president of the defendant company. The plaintiffs testimony was ample and of such a quality as to leave no doubt that the trial judge arrived at a correct conclusion on the facts. There was not a substantial compliance with the plans and specifications.

But it is insisted by the defendant that the architect ■waived a compliance with the specifications because, with full knowledge of the fact that they were not being complied with, he permitted the defendant to continue the work, and, upon its completion, issued a final certificate to the general contractor.

“A waiver implies an intention to overlook a deficiency, or to forego a right to have the defect remedied or to have compensation therefor, and necessarily implies a knowledge of the defect that is waived, or acquiescence under circumstances reasonably implying unconditional acceptance of the work as a full performance.” Eaton v. Gladwell, 108 Mich. 678.

In 9 C. J. p. 797, it is stated:

“So where the work or materials is under the inspection of the owner, or his architect, during its progress, if the builder is not complying with the contract, it is the duty of the owner or architect to object to such work or materials as obviously do not comply with the contract, and on his failure to do so the owner cannot, after the work is completed, claim that the work or materials was not in accordance with the contract.”

Citing Pennsylvania Rubber Co. v. Detroit Shipbuilding Co., 186 Mich. 305, in which case it was said:

“The defects complained of were obvious; and it has been held that if the defects are obvious, the failure to reject is equivalent to approval.”

The specifications provided for the construction of *291 asphalt roofs, the bottom layer of which was to be five-eighths of an inch thick. As laid by the defendant, it is claimed that it was one-half of an inch thick. It was required that the top layer should overlap the joints of the lower layer. As laid, the top layer did not overlap the joints of the lower layer. It was provided that the ingredients of the asphalt should be mixed in certain proportions. There is. testimony that, after leaks developed in these roofs,, an examination of the asphalt disclosed that it had not been mixed according to the specifications ; that it was spongy and porous and contained too much sand. It is said that these are the defects which caused the roofs to leak.

The testimony is undisputed that, except as to the defect in the mixture of the composition, which was not obvious at the time, the defects were pointed out to the defendant’s foreman and superintendent, but that they insisted on laying the roofs according to their own methods. Mr. Laffrey, superintendent for the architect, testified:

“I told the foreman that he was not doing it right as soon as I got on the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & W Roofing, LLC v. Scott Shepperson
Supreme Court of New Hampshire, 2020
Forton v. Laszar
609 N.W.2d 850 (Michigan Court of Appeals, 2000)
Kokkonen v. Wausau Homes, Inc.
289 N.W.2d 382 (Michigan Court of Appeals, 1980)
Baranowski v. Strating
250 N.W.2d 744 (Michigan Court of Appeals, 1976)
Dierickx v. Vulcan Industries
158 N.W.2d 778 (Michigan Court of Appeals, 1968)
525 Main Street Corp. v. Eagle Roofing Co.
168 A.2d 33 (Supreme Court of New Jersey, 1961)
Izumi v. Kwan Doo Park
351 P.2d 1083 (Hawaii Supreme Court, 1960)
Carter v. State Farm Mutual Automobile Insurance
87 N.W.2d 105 (Michigan Supreme Court, 1957)
Shannon v. Polish Falcons of America
82 N.W.2d 523 (Michigan Supreme Court, 1957)
Pastucha v. Roth
287 N.W. 355 (Michigan Supreme Court, 1939)
Richards-Wilcox Manfg. Co. v. Talbot & Meier
233 N.W. 437 (Michigan Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
217 N.W. 38, 241 Mich. 285, 1928 Mich. LEXIS 982, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otto-misch-co-v-e-e-davis-co-mich-1928.