Dierickx v. Vulcan Industries

158 N.W.2d 778, 10 Mich. App. 67, 1968 Mich. App. LEXIS 1381
CourtMichigan Court of Appeals
DecidedMarch 22, 1968
DocketDocket 2,428
StatusPublished
Cited by14 cases

This text of 158 N.W.2d 778 (Dierickx v. Vulcan Industries) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dierickx v. Vulcan Industries, 158 N.W.2d 778, 10 Mich. App. 67, 1968 Mich. App. LEXIS 1381 (Mich. Ct. App. 1968).

Opinion

J. H. Gtllis, P. J.

This is an action for breach of contract. Defendant, Vulcan Industries, is a corporation engaged in the waterproofing of basement walls by application of a “Nu-Miracle Process.” By this process, defendant forces its material into and around the masonry thus effectuating a watertight bond without the necessity for excavating around the outside of the basement wall.

In March of 1954 Thomas Dierickx contracted with Vulcan to waterproof a certain portion of his basement wall. The material terms of the contract were:

“Vulcan Industries, hereinafter called the contractor, proposes to furnish all material and labor necessary to waterproof the sub-soil masonry against seepage through the walls on building located at [plaintiff’s address] using the patented *70 ‘Nu-Miracle process’ without excavation, as per sketch below: [Sketch indicating one wall of plaintiff’s basement]

The contract further stated:

“Guarantee: We guarantee any area where we have applied our ‘Nu-Miracle Process’ against all seepage through the walls, providing that all areas or [sic] the sub-soil masonry is free of defective construction. Por a period of five years.”

The contract price was $100.

Water continued to seep into the basement and in April, 1956, at defendant’s suggestion, a second contract was entered into for treatment of a larger area of the masonry. The printed terms of this contract were the same as the other with the sketch indicating the larger area to be treated. Written terms on this contract further provided that Vulcan was to “check grade” and also “seal at base where there isn’t any paneling. If leaks where paneling is [sic] customer will remove and replace.” The price was $130.

The seepage continued however. From 1956 to 1965 defendant and plaintiff tried various measures to seal the basement and during this period defend7 ant made many service calls to the Dierickx house. Their efforts apparently were to no avail. In the late spring of 1965 defendant ostensibly gave up on the basement.

Plaintiff, in 1965, hired another contractor who controlled the seepage but only after breaking up a portion of plaintiff’s driveway and excavating the outside of the basement wall. Suit was brought in the common pleas court for the city of Detroit, alleging defendant’s breach of contract and seeking damages in the sum of $4,795. The bill of particulars *71 itemized the component elements of damage for which compensation was sought:

Vulcan Industries March 1954 ............... $100.00 April 1956 ................ 130.00
Manuel Márchese ............. 980.00
Replace Drive ................ 780.00
Replace interior wall paneling and damaged tile ...... 805.00'
Compensation for personal injuries and damage to property stored in the basement....... 2,000.00
$4,795.00

■ The trial judge found that defendant breached ‘its contract and gave judgment for Mr. Dierickx- in the amount of $230, the amount he had paid to Vulcan under the two contracts. Plaintiff appeals solely on the issue of inadequacy of damages.

. At trial, the plaintiff attempted to introduce evidence to show the work performed by the second .contractor in support of a portion of his damage claim. The trial judge ruled that while such evi- - dence would be proper in a suit based on negligence, it was improper in a contract action. Plaintiff: maintained at trial, as he does here, that the damage to property and the subsequent costs of excavation all flow from defendant’s breach and are properly admissible in an action in assumpsit.

Since plaintiff on this appeal has questioned the adequacy of the damages awarded to him, we must determine what are the recoverable damages that may arise out of a breach of a repair contract. While the generally accepted rule regarding damages for breach is simply stated, application to .repair contracts has proven no small task.

- On a, broad view, the object and measure of compensatory damages for breach is to “put the injured *72 party in as good a position as lie would have had if performance had been rendered as promised.” 5 Corbin on Contracts, § 992, p 5. And in Brodsky v. Allen Hayosh Industries, Inc. (1965), 1 Mich App 591, 597, 598, we said:

“ ‘Where a breach of contract occurs, the law aims to make compensation adequate to the real injury sustained, and to place the injured party, so far as money can do it, in the same position he would have occupied if the contract had been fulfilled.’ Hammond v. Hannin (1870), 21 Mich 374, 384.”

In assessing damages for breach of contract the breaching party is obliged to make good on the promise. He cannot be accountable for items of subsequent repair, alteration, or correction where the benefit to the nonbreaching party would exceed the benefit contemplated by the contract. Thus in Ciminelli v. Umland Bros., Inc. (1932), 236 App Div 154 (258 NYS 143), defendant contracted to build a new roof for plaintiff guaranteed for five years. The new roof was faulty, leaked badly, and construction of another new roof was necessary. The plaintiff then contracted for a new roof which was guaranteed for 10 years. The appellate division reversed the lower court’s judgment awarding plaintiff the full cost of the new roof (p 155):

“To be sure, even in proving the damages under the correct rule, the proof of what it actually cost to complete the work undertaken and left unfinished or defectively done may be proved as some evidence of the damage. Kidd v. McCormick, 83 NY 391; Mayor of New York City v. Second Ave. R. Co., 102 NY 572 (7 NE 905, 55 Am Rep 839). However, the only evidence here offered related to the cost of a ten-year roof to take the place of the five-year roof which defendant undertook to build. Let us sup *73 pose, for example, plaintiffs had elected to build a copper roof to remedy the condition caused by defendant’s failure to build a five-year asphalt roof. Assuredly proof of the actual cost of such copper roof would not furnish a just measure of damage. While plaintiffs are entitled to as good a roof as defendant undertook to build, no matter how advantageous may have been the bargain they made with defendant, still defendant should not be called upon to pay the cost of a better roof than it contracted to build.”

It is not a bar to recovery that the second contract was more expensive than the first, but only where the later contract was to obtain the same result or benefit as that contemplated originally. For instance, in Scheppegrell v. Barth (1960), 239 La 42 (117 S2d 903), the defendant contracted to paint the inside of plaintiff’s house for $1,100.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brent Sitto v. Kimberly W Stout Pc
Michigan Court of Appeals, 2025
Richard Ambler v. Randy Thompson
Michigan Court of Appeals, 2016
Body Rustproofing, Inc. v. Michigan Bell Telephone Co.
385 N.W.2d 797 (Michigan Court of Appeals, 1986)
Johnson v. Patmon, Young & Kirk, PC
326 N.W.2d 511 (Michigan Court of Appeals, 1982)
Kokkonen v. Wausau Homes, Inc.
289 N.W.2d 382 (Michigan Court of Appeals, 1980)
Goodwin, Inc. v. ORSON E. COE PONTIAC, INC.
233 N.W.2d 598 (Michigan Court of Appeals, 1975)
Allen v. Michigan Bell Telephone Co.
232 N.W.2d 302 (Michigan Court of Appeals, 1975)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
Maraldo Asphalt Paving, Inc. v. Harry D. Osgood Co.
220 N.W.2d 50 (Michigan Court of Appeals, 1974)
Bruno v. Detroit Institute of Technology
215 N.W.2d 745 (Michigan Court of Appeals, 1974)
Dobler v. Malloy
214 N.W.2d 510 (North Dakota Supreme Court, 1973)
Ambassador Steel Co. v. Ewald Steel Co.
190 N.W.2d 275 (Michigan Court of Appeals, 1971)
Oakwood Villa Apartments, Inc. v. Gulu
157 N.W.2d 816 (Michigan Court of Appeals, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
158 N.W.2d 778, 10 Mich. App. 67, 1968 Mich. App. LEXIS 1381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dierickx-v-vulcan-industries-michctapp-1968.