Osterholt v. St. Charles Drilling Co.

500 F. Supp. 529, 30 U.C.C. Rep. Serv. (West) 807, 1980 U.S. Dist. LEXIS 14747
CourtDistrict Court, E.D. Missouri
DecidedOctober 14, 1980
Docket78-1357-C(3)
StatusPublished
Cited by7 cases

This text of 500 F. Supp. 529 (Osterholt v. St. Charles Drilling Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Osterholt v. St. Charles Drilling Co., 500 F. Supp. 529, 30 U.C.C. Rep. Serv. (West) 807, 1980 U.S. Dist. LEXIS 14747 (E.D. Mo. 1980).

Opinion

500 F.Supp. 529 (1980)

Fred OSTERHOLT, Plaintiff,
v.
ST. CHARLES DRILLING COMPANY, INC., Defendant.

No. 78-1357-C(3).

United States District Court, E. D. Missouri, E. D.

October 14, 1980.

*530 Frank Susman, Barbara L. Beran, Clayton, Mo., for plaintiff.

Frederick Drakesmith, St. Charles, Mo., for defendant.

MEMORANDUM

FILIPPINE, District Judge.

This matter is before the Court for a decision on the merits, after a trial to the Court, of plaintiff's two-count complaint. Count I of the complaint alleges a breach of contract; Count II alleges misrepresentation. After consideration of the testimony of the witnesses, the exhibits, and the stipulations of the parties, the Court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT

Plaintiff is a resident of the City of Collinsville, Illinois, and a citizen of the State of Illinois. Defendant Osage Homestead, Inc., d/b/a St. Charles Drilling Co., Inc., is a Missouri corporation with its principal place of business in St. Charles County, Missouri.

In November, 1974, plaintiff contacted the defendant to inquire about the possibility of defendant installing a well and water system on plaintiff's property in Illinois. Plaintiff's property consists in twenty acres located on Kosten Hill Road in Collinsville, Illinois, east of Illinois Highway 157. At the time, there were only two houses planned for construction on the property. The defendant's salesman Bob Torrance came to plaintiff's property and selected a site for the well; drilling began but a cave was encountered and that drilling site was abandoned.

Plaintiff agreed to a second drilling attempt. However, plaintiff wanted the water system which was to be installed with this well to have a capacity to serve twelve houses, as plaintiff had conceived the plan eventually to build ten more houses on his property. Plaintiff developed this plan in part because the second well and water system were to be much more costly than the first would have been, because the second well was to be dug at a considerable distance from plaintiff's property.

The estimate developed by defendant for the well and water system, in which 1¼" pipe was to be used, showed a total price of *531 $4,620.00. Plaintiff was told by Bob Torrance that to harness the capacity of the system to serve twelve houses, plaintiff would only need to: 1) replace the 2 h. p. pump, which was to be installed, with a 5 h. p. pump, and 2) install a 300 gallon tank in each additional home. On July 11, 1975, plaintiff and Bob Torrance executed an agreement for the installation by defendant of the well and water system. The agreement, plaintiff's Exhibit 9, was signed on plaintiff's Illinois property.

The agreement itself contained no description of the items which were to be included in the water system. It did show a maximum total price of $4,620.00 for the well and water system. Among the general terms and conditions contained in the agreement were a one-year guarantee on labor and parts, and the statement "[n]o agreements, expressed or implied, other than stated herein shall be considered as part of this contract." Next to the quoted statement was written "See Supplement Letter 7-11-75."

In the "supplement letter," dated July 11, 1975, plaintiff specified certain items which he wanted to be certain were part of the agreement; he would have allowed no work to be done by defendant on his property had the defendant not agreed to the terms in the "Supplement Letter." Defendant sent a letter to plaintiff, dated July 18, 1975, in which it confirmed the terms of the plaintiff's supplement letter; but defendant added a qualification. Part of defendant's letter to plaintiff, plaintiff's Exhibit 12, reads as follows: "1¼" pipe is large enough to supply 12 homes at 12 GPM each, total 144 GPM (30 # to 50 # pressure at houses); with proper sized pump and accumulator system." (Emphasis added). The underlined words or their equivalent were not contained in plaintiffs' supplement letter. Defendant's letter also confirmed plaintiff's understanding that the "[w]ater line [was] to be buried 36 inches deep."

The defendant, in adding the phrase "with proper sized pump and accumulator system" to its letter to plaintiff, meant to convey to plaintiff that he would have to purchase a 10,000 gallon tank for installation on top of his property to provide the level of service specified in the letter. However, the phrase "accumulator system" is ambiguous. It could refer either to a system of tanks or to a single large tank. Plaintiff understood it to refer to the 300 gallon tanks which Bob Torrance had told him it would be necessary to install in each additional house.

After receipt of this letter from defendant, plaintiff did not contact the defendant but he later allowed the work to proceed. Drilling began in late August, 1975, and the system was completed in early September, 1975. As installed, the system consisted basically in an 81' deep well with a 2 h. p. pump, a 42 gallon "float-type" squat tank, pressure controls near the well, approximately 2300' of 1¼" (inner diameter) PVC (plastic) pipe, and a 120 gallon tank in each of the two houses which had been constructed on plaintiff's property.

The well was drilled on the western side of Highway 157; plaintiff obtained an easement from the farmer who owned the property on which the well was dug, and the pipe was laid for approximately 1300' along the edge of the farmer's field to reach plaintiff's property. The two houses on plaintiff's property were located on top of a hill of 160'. This second well was not drilled where it was first staked by defendant because there were electrical wires too close to the staked site; plaintiff had to obtain a new easement for the well as eventually dug, and this caused plaintiff an additional expense of $175.00.

Plaintiff was ultimately billed for $4,778.39; the billing included certain authorized extra items. Plaintiff has paid the defendant the full amount billed.

The parties had agreed that the squat tank in the well, which was used to absorb pressure in the water system, was to be of the "bladder" type, in which the water is totally encased in a rubber sack. Plaintiff admitted that he has suffered no monetary loss from defendant's failure to install the bladder-type tank.

*532 The plastic pipe, which, according to the terms of the defendant's letter to plaintiff, was to be buried at a uniform depth of 36", was in fact buried at less than that depth at two points: 1) at the point of entry into plaintiff's house, and 2) at the drainage ditch alongside Highway 157. At the point where the pipe enters plaintiff's house, it is 24"-25" deep. The drainage ditch is 24" deep. (Plaintiff employed an independent company to drill beneath the highway and to lay an iron pipe under the highway; it was not a part of the plaintiff's agreement with defendant that defendant would drill under the highway.) The water entering plaintiff's house has never frozen, despite the less-than-36" depth of the pipe where it enters plaintiff's house.

The parties had agreed that there would be a 315 gallon tank installed in one of the two homes, instead of the two 120 gallon tanks which were installed. Although the tank could not have been installed in plaintiff's house because it could not have fit through the doors, it could have been installed in the other house. One 315 gallon tank would have cost $50.00 more than the two 120 gallon tanks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higgins v. Lauritzen
530 N.W.2d 171 (Michigan Court of Appeals, 1995)
In re Trailer & Plumbing Supplies
578 A.2d 343 (Supreme Court of New Hampshire, 1990)
Medical Protective Co. v. Bell
716 F. Supp. 392 (W.D. Missouri, 1989)
DeGroft v. Lancaster Silo Co.
527 A.2d 1316 (Court of Special Appeals of Maryland, 1987)
Hammermill Paper Co. v. Pipe Systems, Inc.
581 F. Supp. 1189 (W.D. Pennsylvania, 1984)
McKinnon v. Tibbetts
440 A.2d 1028 (Supreme Judicial Court of Maine, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
500 F. Supp. 529, 30 U.C.C. Rep. Serv. (West) 807, 1980 U.S. Dist. LEXIS 14747, Counsel Stack Legal Research, https://law.counselstack.com/opinion/osterholt-v-st-charles-drilling-co-moed-1980.