This text of 23 A.D.3d 202 (Osario v. BRF Construction Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Osario v. BRF Construction Corp., 23 A.D.3d 202, 803 N.Y.S.2d 525 (N.Y. Ct. App. 2005).

Opinion

Order, Supreme Court, New York County (Marylin G. Diamond, J.), entered on or about March 28, 2005, which, insofar as appealed from, denied defendants’ motions for summary judgment seeking dismissal of plaintiffs Labor Law § 240 (1) claim, and granted plaintiffs cross motion for partial summary judgment as to liability on that cause of action, unanimously modified, on the law, to grant defendant Jekmar Associates, Inc.’s [203]*203motion for summary judgment dismissing the complaint as against it, and otherwise affirmed, without costs.

The court properly granted plaintiffs cross motion as against the owner of the building under construction and the general contractor. The ladder provided to plaintiff to cut down temporary feeder cable was not an adequate safety device for the task he had been directed to perform and was a proximate cause of the accident and injuries. The method employed by plaintiff was not, under any view of the evidence, the sole proximate cause of his injuries (see Ben Gui Zhu v Great Riv. Holding, LLC, 16 AD3d 185 [2005]; Dunn v Consolidated Edison Co. of NY., 272 AD2d 129 [2000]). However, defendant Jekmar, the construction manager on the project, hired by the owner, was entitled to summary judgment because the record establishes that it did not have the requisite supervision and control over the injury-producing work (see Russin v Louis N. Picciano & Son, 54 NY2d 311 [1981]). That Jekmar was indemnified by defendant 42-43 Realty LLC under the contract between them for any claims arising out of Jekmar’s performance has no logical bearing on the issue of whether Jekmar in fact exercised such supervision and control.

The motion court properly considered plaintiffs cross motion for partial summary judgment. Although plaintiff cross-moved after the court’s imposed deadline for summary judgment motions, plaintiff made it in response to defendants’ still pending, timely summary judgment motions (see James v Jamie Towers Hous. Co., 294 AD2d 268, 272 [2002], affd 99 NY2d 639 [2003]; see also Bressingham v Jamaica Hosp. Med. Ctr., 17 AD3d 496, 497 [2005]). Concur—Marlow, J.P., Nardelli, Williams, Sweeny and McGuire, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fritz v. JLG Indus., Inc.
2021 NY Slip Op 02598 (Appellate Division of the Supreme Court of New York, 2021)
Brill & Meisel v. Brown
113 A.D.3d 435 (Appellate Division of the Supreme Court of New York, 2014)
Kershaw v. Hospital for Special Surgery
114 A.D.3d 75 (Appellate Division of the Supreme Court of New York, 2013)
Ramirez v. Shoats
78 A.D.3d 515 (Appellate Division of the Supreme Court of New York, 2010)
Miraglia v. H & L Holding Corp.
36 A.D.3d 456 (Appellate Division of the Supreme Court of New York, 2007)
Filannino v. Triborough Bridge & Tunnel Authority
34 A.D.3d 280 (Appellate Division of the Supreme Court of New York, 2006)
Barca v. City of New York
13 Misc. 3d 464 (New York Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
23 A.D.3d 202, 803 N.Y.S.2d 525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/osario-v-brf-construction-corp-nyappdiv-2005.