O'ROURKE v. Jason Inc.

978 F. Supp. 41, 1997 U.S. Dist. LEXIS 24355, 1997 WL 577749
CourtDistrict Court, D. Massachusetts
DecidedSeptember 10, 1997
DocketCivil Action 94-30167-MAP
StatusPublished
Cited by10 cases

This text of 978 F. Supp. 41 (O'ROURKE v. Jason Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'ROURKE v. Jason Inc., 978 F. Supp. 41, 1997 U.S. Dist. LEXIS 24355, 1997 WL 577749 (D. Mass. 1997).

Opinion

PONSOR, District Judge.

Upon de novo review this Report and Recommendation is hereby adopted. Plaintiffs motion to enforce the settlement is DENIED; defendant’s motion for summary judgment is ALLOWED. The clerk is ordered to enter judgment for defendant. So ordered.

REPORT AND RECOMMENDATION WITH REGARD TO PLAINTIFF’S MOTION TO ENFORCE SETTLEMENT AGREEMENT (Docket No. W and DEFENDANT’S MOTION FOR SUMMARY JUDGMENT (Docket No. 50)

August 15, 1997

NEIMAN, United States Magistrate Judge.

I. INTRODUCTION

This matter concerns Kevin O’Rourke (“Plaintiff’)’s motion to enforce a professed settlement agreement against Jason Incorporated (“Defendant”). Plaintiff asserts, among other things, that Defendant had agreed to settle his complaint and that the doctrine of judicial estoppel should apply. Denying that a settlement agreement had ever been finalized, Defendant in turn has moved for summary judgment, contending that the statute of limitations precludes any relief.

Defendant’s motion for summary judgment has been referred to this Court for a report and recommendation pursuant to Rule 3 of the Rules of United Sates Magistrates of the United States District Court for the District of Massachusetts. 28 U.S.C. § 636(b)(1)(B). Because Plaintiffs motion also entails a potentially dispositive issue, the Court has addressed that motion pursuant to Rule 3 as well. For the reasons indicated below, the Court recommends that Plaintiffs motion to enforce the settlement be denied and that Defendant’s motion for summary judgment be granted.

II. BACKGROUND

There is no genuine dispute as to the following facts, many of which were explored *44 in the Court’s August 23, 1996 report and recommendation regarding Defendant’s previous motion for summary judgment. (See Docket No. 35.)

At the time of the accident underlying this lawsuit, Plaintiff was employed by the Springfield Resource Recovery Plant in Agawam, Massachusetts. As a shift supervisor and engineer, he monitored and maintained the plant’s boilers. On July 14, 1991, Plaintiff investigated a malfunction in a boiler. The hopper doors on the boiler in question were hinged at the bottom and opened from top to bottom by way of two sets of nuts and washers. Plaintiff unscrewed the nuts securing the doors in an attempt to cool down the system to facilitate further investigation. When Plaintiff began to unscrew the nuts on one particular door, he observed leaking water and turned away. Pressure within forced the hopper door to swing open, causing Plaintiff to sustain first and second degree burns on his legs and back from scalding water. The injuries required- immediate hospitalization and ongoing treatment.

Plaintiffs product liability complaint against Defendant — who assertedly designed and manufactured the hopper doors — was filed on July 15, 1994. Although the injury had in fact occurred on July 14, 1991, the complaint averred that Plaintiff was injured on July 16, 1991. The complaint, as plead, therefore fell within one day of the applicable three year statutes of limitations. See M.G.L. ch. 260, § 2A; M.G.L. ch. 106, § 2-318. In turn, Defendant’s answer indicated that it was “without knowledge or information sufficient to form a belief as to the truth of [this] allegation.” Plaintiffs pre-trial memorandum, filed on December 6, 1995, also asserted that his injury occurred on July 16, 1991. Defendant’s pre-trial memorandum, filed December 7, 1995, did not contest this date.

Plaintiffs later court documents also assumed that the accident occurred on July 16, not July 14, 1991. For example, in his February 23, 1996, opposition to Defendant’s original motion for summary judgment, Plaintiff included his responses to Defendant’s interrogatories in which he stated that his injury occurred on July 16, 1991. Likewise in his February 1, 1996, motion to amend his complaint, which sought to add a claim of market share liability, Plaintiff referred to July 16, 1991, as the date of injury. Following the parties’ lead, the Court’s August 23, 1996, report and recommendation accepted as an undisputed fact that Plaintiffs injury occurred on July 16, 1991. District Judge Michael A. Ponsor adopted the recommendation to deny Defendant’s motion for summary judgment and set a jury trial for February 24,1997.

On February 14, 1997, Plaintiff moved to enter and view the Springfield Resource Recovery Plant. In his motion, Plaintiff, for the first time in court documents, referred to his injury as having occurred on July 14, 1991. As it happened, that same day, February 14, 1997, Plaintiffs counsel, with the approval of Defendant’s counsel, contacted the clerk’s office and reported that the parties had reached an oral settlement agreement. The proposed agreement involved a compromise of the statutory lien held by the worker’s compensation insurer as required by M.G.L. ch. 152, § 15. Plaintiffs counsel requested a hearing before Judge Ponsor in order to obtain approval of the settlement. The clerk scheduled the hearing for the afternoon of February 24, 1997, the originally scheduled trial date.

On the morning of the scheduled hearing date, Plaintiffs counsel, after reviewing the draft release prepared by Defendant’s counsel, advised Defendant’s counsel that the injury occurred on July 14, 1991, not July 16, 1991. Defendant’s counsel thereupon refused to sign the petition for approval of settlement, which already had been endorsed by the worker’s compensation insurer. The parties appeared in court that afternoon and reported that the matter was not settled. Judge Ponsor scheduled a status conference for March 3, 1997, at which time he ordered that Plaintiffs proposed motion to enforce the settlement agreement and Defendant’s proposed motion to dismiss be filed by March 21, 1997. The Court addresses these two motions in turn.

III. MOTION TO ENFORCE SETTLEMENT

Plaintiff essentially makes four arguments why the parties’ purported settlement should *45 be enforced: (1) he has an enforceable oral contract with Defendant to settle the case for a specific amount; (2) he did not actively deceive Defendant as to the date of the accident; (3) the doctrine of judicial estoppel should be employed to enforce the parties’ agreement; and (4) Defendant is being contradictory regarding its knowledge of the date of injury. These arguments are addressed below after a discussion of two preliminary matters.

First, the Court notes that both parties rely on the Restatement (Second) of Contracts and draw no distinction between contracts entered into by parties themselves and those entered into by the parties’ counsel. Nevertheless, from the facts presented,.it is apparent that each party’s attorney had actual authority to enter a binding settlement. Compare Michaud v. Michaud, 932 F.2d 77, 81 (1st Cir.1991), and Milewski v. Roflan Co., 195 F.Supp. 68, 69 (D.Mass.1961) (denying motion to enforce settlement agreement finding attorney lacked authority to bind client). See also Mason & Dixon Lines, Inc. v. Glover,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barnia v. Kaur
D. Massachusetts, 2022
McCormick v. Lischynsky
D. Massachusetts, 2021
Greene v. General Hospital Corp.
794 F.3d 133 (First Circuit, 2015)
Enos v. Union Stone, Inc.
732 F.3d 45 (First Circuit, 2013)
Tabb v. JOURNEY FREIGHT INTERNATIONS
584 F. Supp. 2d 334 (D. Massachusetts, 2008)
Smit Americas, Inc. v. the M/T MANTINIA
259 F. Supp. 2d 118 (D. Puerto Rico, 2003)
Horney v. Westfield Gage Co.
211 F. Supp. 2d 291 (D. Massachusetts, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
978 F. Supp. 41, 1997 U.S. Dist. LEXIS 24355, 1997 WL 577749, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orourke-v-jason-inc-mad-1997.