Orleans Dredging Co. v. United States

86 Ct. Cl. 404, 1938 U.S. Ct. Cl. LEXIS 217, 1938 WL 3962
United States Court of Claims·Decided March 7, 1938·No. No. 41951·Published·Cited by 1 cases

Opinion

Green, Judge,

delivered the opinion of the court:

The plaintiff entered into a contract with the defendant for dredging, transporting, and placing material to be used in the construction of an addition to a levee along the Mississippi River. The price of the work per cubic yard placed was fixed at 35.47 cents and the contract estimate of its amount was approximately $851,280. Excluding the claims which have now been abandoned under the allegations of the petition, the plaintiff seeks to recover approximately $1,022,958.64 for additional work and expense alleged to have been wrongfully caused or required by the defendant in the course of the operations under the contract together with $2,550 deducted as liquidated damages for delay. Included in the recovery asked is an alternative claim for [435] work alleged to have been performed under the contract and not paid for.

As the parties do not agree upon the construction of the contract or upon the facts shown by the evidence it becomes necessary to first construe the contract and then determine what has been proved or disproved by the testimony.

The plaintiff claims that the contract was one for dredging work; the defendant insists it was for levee work. The contract provided in substance that the material should be moved by a hydraulic dredge but it was well understood that the fill which was to be made with the materials moved was to constitute the base of the addition to a levee, except where the material was used to fill old borroAv pits pursuant to the contract. We think that neither party is entirely right with reference to the construction of the contract.

The contract is not as clear as it might have been made and we find it necessary to construe its provisions in the light of all of the circumstances in the case.

The specifications attached to the contract provided that — ■

Alternate bids will be received for placing * * * the required yardage hydraulically in any approved manner.

The contracting officer and counsel for defendant construe the words “in any approved manner” to mean in a manner approved by the contracting officer, but we think it clear that so far as these words taken alone are concerned they can not be so construed. It is not so stated in the words quoted and they would not be so understood as applied to engineering work. The words “approved manner,” when used without other limiting expressions with reference to the performance of the work, we think mean “sanctioned” or “endorsed” generally by those skilled in the business or occupation which is exercised in the performance of the work. This approval need not be unanimous as there is often a difference of opinion in such matters even among those most skilled. In such cases, however, if the practice used is sanctioned by a decided majority or by those shown to be best informed and skilled in the work it becomes established as the “approved method.”

[436] Counsel for defendant in further support of the argument that the approval of the Government engineer was required quotes the following from specification 22 of the contract, which provides—

In the event that the contractor proposes to do the work by hydraulic methods his plan of operation shall be submitted to the contracting officer for approval.

We think that this provision of the contract was abandoned or waived. A plan of operations could not be furnished by the contractor until he received the necessary construction notes and was assigned a borrow pit or pits from which he was to dredge for the fill. No attention seems to have been paid by either party to this provision. No plan was furnished by plaintiff nor was any requested by defendant. The reason appears to be that the work was begun long before complete construction notes necessary for preparing a plan were furnished by defendant and some of the work was begun before any construction notes were available. In fact, defendant advised plaintiff that toe distances could not be given until plaintiff had started pumping and defendant had an opportunity to determine the class of material to be placed in the fill, and further that defendant could not furnish more than 500 feet of construction notes [at one time] which was too short for practical purposes and insufficient for the preparation of a plan of operations. The contracting officer, however, claimed the absolute right to pass finally upon the method used by plaintiff in placing the material and considered that when he determined it was “not proper” this ended the matter. In this respect he erred, but this holding will be found not material to the decision of the case as we proceed with its further consideration.

There is another provision of the contract which defendant claims was violated by plaintiff and was one of the reasons given by defendant for requiring plaintiff to remove a large quantity of material which plaintiff claims had been properly placed in accordance with the contract. Section 22 of the specifications of the contract provides—

No earth showing a tendency to slough shall be placed in the embankment.

[437] The meaning of the word “slough” as given in the dictionary [except where used as a medical term] is to shed or cast off. As thus used it refers to a separation of material. We are unable to apply the clause of the contract quoted above to the conditions under which hydraulic work must necessarily be carried on. The material had to be pumped and it could only be pumped when in a semi-fluid condition, and when discharged it would not only separate but actually flow. Its condition when discharged at the end of the suction pipe was such that this provision could have no application thereto. If this clause has any application, it must refer to the material which had settled and been deposited, but here another difficulty is encountered. What kind of an appearance would be presented by material “showing a tendency to slough” is not disclosed by the testimony. Our determination of other provisions of the contract considered later on is, however, such that a construction of this provision is of no importance.

The contract was not only for moving material but for placing it by hydraulic methods. Moreover, it was stated therein that the earth to be moved was to be used as an embankment for the construction of an addition to a levee. Placing the material in an approved hydraulic manner did not end with its discharge from the suction pipe. It is true that a hydraulic dredge draws into its pipe the material just as it comes. The material to a certain extent is disintegrated and segregated into its component parts by reason of the action of the cutters in the borrow pits and the agitation caused by pumping. (See Finding 14.) This agitation cannot be controlled but the evidence shows that as the material is discharged it is possible to substantially control the placing of it so that the suitable material will be deposited in the fill and the unsuitable material for the most part flow off. Such being the case, we think the contract required that when the material was distributed after it emerged from the discharge pipe it should be so placed by means of settling basins and control of the flowage that any considerable quantity of unsuitable material would not be deposited in one place when intended to be used as part of the base of an enlargement of the levee.

Free access — add to your briefcase to read the full text and ask questions with AI

Orleans Dredging Co. v. United States, 86 Ct. Cl. 404, 1938 U.S. Ct. Cl. LEXIS 217, 1938 WL 3962 (cc 1938).

86 Ct. Cl. 404 (Orleans Dredging Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Orleans Dredging Co. v. United States
89 Ct. Cl. 170 (Court of Claims, 1938)