Orleans Dredging Co. v. United States

89 Ct. Cl. 170, 1939 WL 327
CourtUnited States Court of Claims
DecidedMarch 7, 1938
DocketNo. 41951
StatusPublished

This text of 89 Ct. Cl. 170 (Orleans Dredging Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orleans Dredging Co. v. United States, 89 Ct. Cl. 170, 1939 WL 327 (cc 1938).

Opinion

[171]*171MEMORANDUM

Per Curiam:

Pursuant to the order of court new testimony was presented in support of the second motion of defendant for a new trial. This evidence was heard by 'a. commissioner .of this court and he has made his report thereon. The parties to the case, through their respective counsel, .each filed' exceptions to this report, but upon reexamination of the evidence we think it is substantially correct. Tire report shows that the amount of material pumped by the plaintiff which went into the old riverside borrow pits and was not paid for by the Government had been miscalculated upon the testimony originally introduced in the case. Defendant’s motion for a new trial on the ground of a miscalculation has accordingly been sustained insofar as to enter an order correcting the figures stated in the original findings and used in the calculation of the amount of this material. An examination of this order will show that the changes made in the findings do not affect any of the legal questions decided in the original opinion but merely the amount of plaintiff’s recovery under Claim 6 [Paragraph X1/2 of the petition]. It is not therefore necessary to make any change in the opinion except to correct the calculation of the plaintiff’s recovery and the amount of judgment to be rendered. The new Finding 24 shows that the correct amount of ma[172]*172terial which went into the old riverside borrow pits was 669,647 cubic yards, which at the contract price of 35.47 cents a cubic yard, amounts to $237,523.79. The former judgment has been set aside and a new judgment entered in favor of plaintiff for the amount last stated.

More than thirty days after the filing of the exceptions to the commissioner’s report and after all time had expired for further filings, whether the proceedings were treated as on motion for new trial or under the rules applied to original hearings, defendant’s counsel presented to the court in typewriting a long brief on remand. Some peculiar circumstances not necessary to be recited here have induced us to permit this brief to be filed and, being, filed, it should be and is considered. Part of this last brief is based upon the ground that the actual capacity of the borrow pits was not sufficiently shown by the evidence. It may be conceded that it could not be shown exactly, but this does not prevent plaintiff’s recovery. The commissioner had no difficulty in determining an amount which we think is substantially correct and we have followed his findings although plaintiff’s counsel insists that the amount which he found is much too small and defendant’s counsel insists that it is altogether too large.

The greater portion of defendant’s last brief is devoted to an effort to show that the agents of plaintiff and defendant did not understand that the provision of the contract upon which plaintiff has been granted a recovery was to be carried out; and, assuming that this appears from the testimony, it is contended in effect that the contract is to be treated as if this provision were not a part thereof. Cases are cited in support of the familiar rule that where the terms of a contract are ambiguous or the language of a provision is not plain and is capable of more than one construction, parol testimony may be considered to show the understanding of the parties as to what in fact the contract was between them.But here the language of the contract is clear, definite, and positive. In fact, as we stated in the original opinion, it is much plainer than with reference to most of the matters in controversy in the case. The important part of the provision in question was, as shown in the original opinion, a note attached to the contract drawing, ■ and the contract. [173]*173itself required the work to be strictly in accordance with the specifications and drawings. It may be that plaintiff’s engineer or agents had not noticed this provision and were not aware of it. Plain agreements in a contract are not to be nullified on account of some oversight or even by a misunderstanding. They can only be taken out by another agreement. The rule which defendant invokes has no application here and on this third argument by defendant our former conclusion is reaffirmed.

The equities of this case are strongly with the plaintiff. By unreasonable and unnecessary requirements on the part of the Government officials the plaintiff was compelled to do far more work than was required by the contract. The defendant has sought to defeat plaintiff’s recovery by every technicality that could possibly be urged and unfortunately the nature of plaintiff’s work was such that it was impossible to show how much more was performed than was necessary. The case has been drawn out to great length by hearing and rehearing until we think no further proceedings should be had except to enter judgment.

FINDINGS AND ORIGINAL OPINION

The findings, amended as shown, together with the original opinion in the case, March 7, 1938, are as follows:

SPECIAL FINDINGS OF FACT

1. Orleans Dredging Company, the plaintiff herein, is a corporation of the State of Louisiana, with its principal office and place of business in the City of New Orleans.

2. On August 22, 1929, plaintiff entered into a contract with the United States, represented by John C. H. Lee, Major, Corps of Engineers, District Engineer, as contracting officer, whereby plaintiff agreed, as the contract recited, to-

* * * furnish all labor and materials, and perform al] work required for the construction of landside enlargement, Stations 1850-1998 and 2085-2190, inclusive, and riverside enlargement; Stations 1998-2065, inclusive, of Beulah to Lake Vermillion levee, on the left [174]*174bank of the Mississippi River, material to be placed under alternate method as described in paragraph 39.1 of the specifications, subproject item No. 8, requiring about two million four hundred thousand (2,400,000) cubic yards of earthwork, more or less, for the consideration of thirty five and forty seven hundredths (35.47) cents per cubic yard, making a total consideration of approximately eight hundred fifty-one thousand two hundred eighty dollars ($851,280.00), in strict accordance with the specifications, schedules, and drawings, all of which are made a part hereof and designated as follows:
Specifications for levee work dated June 22, 1929, numbered 1 to 39.8 and attached hereto. Drawing No. 3 showing the work and method of construction, and two sketches of alternate method, one for riverside enlargement, 60% complete, and one for landside enlargement, 70% complete, also attached hereto.

The contract proAdded that the work was to commence within 20 calendar days after the date of receipt by the contractor of notice to proceed, and be completed withiii 18 calendar months after the said date of receipt. ■

A copj? of the contract is attached to the petition as plaintiff’s exhibit C and is made part hereof by reference.

The “alternate method” required by the contract was described in subproject item No. 8 of paragraph 39.1 as

placing * * * the required yardage hydraulically in.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orleans Dredging Co. v. United States
86 Ct. Cl. 404 (Court of Claims, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
89 Ct. Cl. 170, 1939 WL 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orleans-dredging-co-v-united-states-cc-1938.