Oregon Natural Resources Council v. Marsh

845 F. Supp. 758, 1994 WL 43846
CourtDistrict Court, D. Oregon
DecidedFebruary 10, 1994
DocketCiv. 85-6433-BU, 92-1550-BU
StatusPublished
Cited by4 cases

This text of 845 F. Supp. 758 (Oregon Natural Resources Council v. Marsh) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oregon Natural Resources Council v. Marsh, 845 F. Supp. 758, 1994 WL 43846 (D. Or. 1994).

Opinion

Opinion and Order

JAMES M. BURNS, Senior District Judge.

This dam case is back again. Its progress through the judicial system has resulted in *763 less than half a dam, and, as the caption reflects, a second lawsuit. Plaintiffs seek mandatory injunctive relief ordering the removal of the partially completed dam from Elk Creek. Defendants seek dissolution of the present injunction so that further planning, design, and, ultimately, construction can go forward. Their motions are pending in the older case, Oregon Natural Resources Council v. Marsh, (Marsh). Both sides move for summary judgment under Rule 56(c) and the same injunctive relief in the newer case, Oregon Natural Resources Council v. Harrell (Harrell).

I. FACTUAL BACKGROUND

For a more complete history, readers may consult one or more of the opinions offered earlier in this case, some of which are cited below. Initially, I found and held that the Corps of Engineers had taken the required “hard look” for NEPA purposes. That was almost eight years ago, in the spring of 1986, when I denied plaintiffs’ request for a preliminary injunction. Oregon Natural Resources Council v. Marsh, 628 F.Supp. 1557 (D.Or. 1986).

I knew plaintiffs intended to appeal. Therefore, I granted them a short stay to apply to the Ninth Circuit for a stay pending appeal. A panel of the Court of Appeals denied plaintiffs’ motion for a stay, and construction of the dam began.

A little over a year later, a different panel of the Court of Appeals found that the Corps had not properly done its NEPA job. The appellate reversal carried with it directions for me to issue an injunction appropriate to the mid-construction circumstances. Oregon Natural Resources Council v. Marsh, 832 F.2d 1489 (9th Cir.1987). Accordingly, I issued an injunction requiring the Corps to halt construction before the dam was completed. Oregon Natural Resources Council v. Marsh, 677 F.Supp. 1072 (D.Or.1987). In accordance with my ruling, the Corps closed down the project when the dam structure reached a height of 1,563 feet. This is approximately one third of the planned height of the dam.

Neither side appealed my injunction. However, defendants sought review in the Supreme Court of the ruling by the Court of Appeals on all but one of the NEPA issues. For reasons that still continue to baffle me, the Justice Department lawyers saw fit not to ask for review of the so-called “cumulative impacts” issue. Almost exactly one year after the ruling of the Court of Appeals, the Supreme Court granted certiorari. Robertson v. Methow Valley Citizens Council, 487 U.S. 1217, 108 S.Ct. 2869, 101 L.Ed.2d 905 (1988). Just about a year later, the Supreme Court reversed the Court of Appeals on all the issues presented in the appeal. Marsh v. Oregon Natural Resources Council, 490 U.S. 360, 109 S.Ct. 1851, 104 L.Ed.2d 377 (1989), companion case Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 109 S.Ct. 1835, 104 L.Ed.2d 351 (1989). 1

On February 22, 1990, pursuant to the order from the Court of Appeals, I modified the injunction, prohibiting further construction until the Corps had supplemented its Environmental Impact Statement consistent with the opinions of this court, the Court of Appeals, and the Supreme Court. The net result of those opinions was the Ninth Circuit ruling requiring the Corps to supplement the discussion of cumulative impacts, the issue which had not been appealed to the Supreme Court.

The Corps issued its second supplement to the Environmental Impact Statement (Second EISS) on May 1, 1991. The Division Engineer (“Harrell”) issued the final Record of Decision (“ROD”) on January 24, 1992, selecting the NCP or “no conservation pool” alternative operating mode. Based on completion of the Second EISS, the Corps moved for dissolution of the injunction on July 22, 1992. 2

*764 Meanwhile, the Secretary of the United States Department of Agriculture, acting through Regional Forester Lowe (“Forest Service” or “Lowe”) of the United States Forest Service, and the Secretary of the United States Department of the Interior, acting through Director Bibles of the United States Bureau of Land Management (“BLM” or “Bibles”), jointly prepared a “Section 7(a) determination” under the Wild and Scenic Rivers Act (‘WSRA”), 16 U.S.C. § 1278. The Forest Service and BLM issued the Section 7(a) determination on November 5, 1992. In it, they concluded that the partially completed Elk Creek Dam project unreasonably diminishes fishery resources in the Rogue River, a designated Wild and Scenic River under WSRA. They found that the project would continue to unreasonably diminish the WSRA values of the Rogue River if it is completed and operated in the NCP operating mode as presently designed.

II. STANDARDS

A. SUMMARY JUDGMENT

The court should grant summary judgment if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). The moving party must show that there are no genuine issues of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). If the moving party meets its burden, the non-moving party must go beyond the pleadings and designate facts showing an issue for trial. Celotex Corp. 477 U.S. at 322-23, 106 S.Ct. at 2552.

B. INJUNCTIVE RELIEF

To obtain injunctive relief, the moving party must show irreparable injury and inadequacy of legal remedies. Amoco Production Co. v. Gambell, 480 U.S. 531, 542, 107 S.Ct. 1396, 1402, 94 L.Ed.2d 542 (1987); Sierra Club v. Penfold, 857 F.2d 1307, 1318 (9th Cir.1988). For a preliminary injunction, the moving party must show either probable success on the merits and the possibility of irreparable injury or serious questions on the merits and the balance of hardships tipping sharply in its favor. William Inglis & Sons Baking Co. v. ITT Continental Baking Co., 526 F.2d 86, 88 (9th Cir.1975); United States v. Odessa Union Warehouse Co-op, 833 F.2d 172, 174 (9th Cir.1987); Half Moon Bay Fishermans’ Marketing Asso. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
845 F. Supp. 758, 1994 WL 43846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oregon-natural-resources-council-v-marsh-ord-1994.