Oregon Natural Resources Council v. Marsh

628 F. Supp. 1557, 24 ERC 1211, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 24 ERC (BNA) 1211, 1986 U.S. Dist. LEXIS 28675
CourtDistrict Court, D. Oregon
DecidedMarch 3, 1986
DocketCiv. 85-6433-E
StatusPublished
Cited by12 cases

This text of 628 F. Supp. 1557 (Oregon Natural Resources Council v. Marsh) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oregon Natural Resources Council v. Marsh, 628 F. Supp. 1557, 24 ERC 1211, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 24 ERC (BNA) 1211, 1986 U.S. Dist. LEXIS 28675 (D. Or. 1986).

Opinion

OPINION AND ORDER

JAMES M. BURNS, District Judge.

I. INTRODUCTION

Oregon Natural Resources Council (ONRC) brought this action to enjoin the Corps of Engineer’s (Corps) construction of a dam at Elk Creek in the Rogue River Basin in Southern Oregon. ONRC sought a preliminary injunction; the Corps opposed this motion, and also responded with a motion for summary judgment.

ONRC initially charged the Corps with violating both the National Environmental Policy Act (NEPA) and the Wild and Scenic Rivers Act (WASRA). 1 Prior to the hearing on the motion for preliminary injunction, ONRC withdrew its WASRA claim. 2 At issue here, therefore, is only whether the Corps violated the requirements of NEPA in the preparation of its Final Environmental Impact Statement Supplement (FEISS) on the Elk Creek project.

A hearing was held on January 16, 1986 at which, after testimony was taken and oral argument had, I gave a brief oral opinion denying ONRC’s motion for preliminary injunction. I advised the parties I would issue a written opinion addressing both ONRC’s motion for preliminary injunction and the Corps’ motion for summary judgment.

FACTS

The parties have thoroughly canvassed the facts (largely undisputed) of this case. The voluminous administrative record also contains a detailed accounting of the facts. 3 It is, therefore, unnecessary to review the facts in detail for either party’s benefit. *1561 Any reader desiring more detail may consult the entire record filed with the court.

Briefly, the construction of the Elk Creek Dam was authorized in 1962 as part of a three dam Rogue River Basin project. The project’s primary purpose was to control flooding in the Rogue River Basin in Southern Oregon. The other.two dams, Lost Creek Dam and Applegate Dam, have already been completed.

The Corps completed an Environmental Impact Statement (EIS) on the Elk Creek dam in 1971. After conducting further studies on the turbidity potential of the proposed construction the Corps drafted a supplemental (EISS) in 1975. However, because of controversy over the environmental effects of the project the Governor of Oregon withdrew the state’s support and requested that work be suspended until the Corps could evaluate the effects of the Lost Creek dam on the water quality in the Rogue River. The 1975 draft EISS was never finalized.

After studying the water quality effects of the Lost Creek Dam, the Corps prepared another draft EISS in 1980. After public comment and response, that EISS was finalized (FEISS) in December, 1980.

In February, 1982 the Corp issued a Record of Decision for the Dam’s construction, subject to Congressional authorization. A § 404 Water Quality study was conducted and completed in October, 1983. 4 Also during that year the dam’s structure was redesigned to lower the anticipated water temperatures. An Environmental Assessment (EA), Finding of No Significant Impact (FONSI), and a Supplemental Information Report (SIR) were completed on those changes.

Despite the Division Engineer’s Decision of Record recommending construction of the dam, the Corps did not seek funding for it. Nevertheless, in August, 1985, after five years of extensive testimony (before the relevant committees) and study regarding Elk Creek, Congress appropriated moneys and directed the Corps to build the dam. 5 ONRC then filed this suit to enjoin the dam’s construction.

II. DISCUSSION — PRELIMINARY INJUNCTION STANDARDS

This circuit has adopted two alternative tests to determine whether a preliminary injunction should be issued:

The first test requires that a court find 1) the moving party will suffer irreparable injury if the injunctive relief is not granted; 2) there is a substantial likelihood that the moving party will succeed on the merits; 3) in balancing the equi *1562 ties the nonmoving party will not be harmed more than the moving party is helped; and 4) granting injunctive relief is in the public interest____ The second test requires the moving party to demonstrate either 1) a combination of probable success on the merits and the possibility of irreparable harm; or 2) that serious questions are raised and the balance of hardships tips sharply in his favor.

City of Tenakee Springs v. Block, 778 F.2d 1402, 1407 (9th Cir.1985).

Under either test ONRC must establish a likelihood, or at least serious questions, that the Corps violated NEPA requirements in preparing its final EIS.

“The purpose of NEPA is to assure that federal agencies are fully aware of the impact of their decision on the environment.” Friends of the Endangered Species v. Jantzen, 760 F.2d 976, 985 (9th Cir.1985). To satisfy this purpose, NEPA requires that federal agencies undertaking projects with significant environmental consequences must identify and discuss all those foreseeable environmental consequences in an EIS. 42 U.S.C. § 4332. 6

An EIS serves two basic purposes. It a) “should provide decision-makers with an environmental disclosure sufficiently detailed to aid in the substantive decision whether to proceed with the project in light of its environmental consequences” and b) “the impact statement should provide the public with information on the environmental impact of a proposed project as well as encourage public participation in the development of that information.” Trout Unlimited, Inc. v. Morton, 509 F.2d 1276 (9th Cir.1974).

In reviewing an agency’s compliance with NEPA I am required to

employ a “rule of reason” that inquires whether an EIS contains a “reasonably thorough discussion of the significant aspects of the probable environmental consequences.” Trout Unlimited, Inc. v. Morton, 509 F.2d 1276, 1283 (9th Cir.1974). This standard is not susceptible to refined calibration. It instead requires a reviewing court to make a pragmatic judgment whether the EIS’s form, content and preparation foster both informed decision-making and informed public participation. Warm Springs Dam Task Force v. Gribble, 565 F.2d 549, 552 (9th Cir.1977) (per curiam); Trout Unlimited, Inc., 509 F.2d at 1283. This standard of review, however, does not authorize a reviewing court to substitute its judgment for that of the agency concerning the wisdom or prudence of a proposed action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oregon Natural Resources Council v. Harrell
52 F.3d 1499 (Ninth Circuit, 1995)
In Re Application of SDDS, Inc.
472 N.W.2d 502 (South Dakota Supreme Court, 1991)
Marsh v. Oregon Natural Resources Council
490 U.S. 360 (Supreme Court, 1989)
Oregon Natural Resources Council v. Marsh
677 F. Supp. 1072 (D. Oregon, 1987)
Oregon Natural Resources Council v. Marsh
820 F.2d 1051 (Ninth Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
628 F. Supp. 1557, 24 ERC 1211, 16 Envtl. L. Rep. (Envtl. Law Inst.) 20475, 24 ERC (BNA) 1211, 1986 U.S. Dist. LEXIS 28675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oregon-natural-resources-council-v-marsh-ord-1986.