Glacier Park Foundation v. Watt

663 F.2d 882, 1981 U.S. App. LEXIS 15360
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 10, 1981
Docket81-3102
StatusPublished
Cited by15 cases

This text of 663 F.2d 882 (Glacier Park Foundation v. Watt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glacier Park Foundation v. Watt, 663 F.2d 882, 1981 U.S. App. LEXIS 15360 (9th Cir. 1981).

Opinion

663 F.2d 882

GLACIER PARK FOUNDATION, Plaintiff-Appellant,
v.
James G. WATT, Secretary, Department of the Interior, an
agency of the United States of America, Defendant-Appellee,
and
Glacier Park, Inc., Intervenor.

Nos. 81-3102, 81-3511.

United States Court of Appeals,
Ninth Circuit.

Argued and Submitted Oct. 6, 1981.
Decided Dec. 10, 1981.

John D. Hagan, Minneapolis, Minn., for plaintiff-appellant.

Robert T. O'Leary, Butte, Mont., for defendant-appellee.

Sam Haddon, Boone, Karlberg & Haddon, Missoula, Mont., for intervenor.

Appeal from the United States District Court for the District of Montana.

Before BROWNING and WRIGHT, Circuit Judges, and THOMPSON,* Senior District Judge.

EUGENE A. WRIGHT, Circuit Judge:

Glacier Park, Inc. (GPI) has operated the concessions at Glacier Park for 20 years. Its contract with the National Park Service (Service) was to expire in 1985. Because substantial improvements to the park facilities were necessary, the Service decided to cancel the existing contract and solicit proposals for a new long-term contract to provide for the new work. Notice of the Service's intent to solicit proposals was published in the Federal Register in June 1980. Interested parties were given 81 days to submit proposals, the minimum 60-day period plus an additional 21 days added when the Service revised its requirements for the proposals.

GPI and Glacier Park Foundation (Foundation) submitted proposals. The Service evaluated them and rejected the Foundation's proposal. The Service sent a letter to GPI, worded in terms of a rejection. Another letter to a company wishing to buy GPI stated that further negotiations would take place. A 25-year contract between GPI and the Service was signed in December 1980.

The Foundation sought preliminary and permanent injunctions to void the contract. It claimed that the Service, under the authority of the Secretary of the Interior, had: (1) provided insufficient notice of its intent to seek proposals, (2) provided insufficient time for parties to prepare proposals, (3) wrongfully denied the Foundation's Freedom of Information Act request for GPI's past financial reports, and (4) negotiated with GPI after it rejected both proposals in violation of the regulations requiring a resolicitation upon rejection of all proposals. 36 C.F.R. §§ 51.5 and 51.4(c). The Foundation's challenge was based on either the Administrative Procedure Act, 5 U.S.C. § 702, or an implicit private right of action under the Concessions Policy Act, 16 U.S.C. § 20d.

On motion by the Service, the district court dismissed the complaint and denied the preliminary injunction. It specifically retained jurisdiction over the FOIA claim. This court has jurisdiction of the dismissal of the injunction under 28 U.S.C. § 1292(a). Jurisdiction over the dismissal of the complaint is proper under Fed.R.Civ.P. 54(b).

The appeal is not moot even though a new contract was signed. The parties remain adverse and the allegedly improper actions by the Secretary continue to have an adverse effect upon the Foundation. GPI has begun performance under the new contract but can be compensated for work done should that contract be terminated. 16 U.S.C. § 20e. Effective relief may still be granted. Jones v. S. E. C., 298 U.S. 1, 17-18, 56 S.Ct. 654, 658, 80 L.Ed. 1015 (1936).

I. Did the district court properly deny the preliminary injunction?

The district court's refusal to grant a preliminary injunction can be reversed only if there was an abuse of discretion. Miss Universe, Inc. v. Flesher, 605 F.2d 1130, 1132-33 (9th Cir. 1979). A preliminary injunction should be granted only if the movant can show either: (1) probable success on the merits and the possibility of irreparable injury, or (2) that serious questions are raised and the balance of hardships tips sharply in the movant's favor. Id. at 1134. Both tests have been applied in this circuit.

While the Foundation does have a strong chance of success, see Section IV infra, it has not shown that irreparable injury would result from allowing the new contract to stand during the course of these proceedings. Future relief can be granted because any work done by GPI under the new contract will be reimbursed if that contract is later withdrawn. 16 U.S.C. § 20e. The Foundation's allegations of irreparable harm to the environment and historical values are unsubstantiated.

Under the second test for a preliminary injunction, the Foundation again has not made a sufficient showing. The balance of hardships must tip sharply in its favor. The district court found that safety improvements were needed for the 1981 summer season. It found also that these improvements could not be done unless the new contract was allowed to proceed. Although the Foundation disputes this and argues that the improvements would have been done without the new contract, the district court's finding is not clearly erroneous.

The denial of the preliminary injunction is affirmed.

II. Implied private right of action under the Concessions Policy Act.

The Foundation's claim for a private right of action under the Concessions Policy Act must be denied. The primary question in determining whether such an action is implicit in a statute is whether Congress intended to create one. Touche Ross & Co. v. Redington, 442 U.S. 560, 575, 99 S.Ct. 2479, 2489, 61 L.Ed.2d 82 (1979). Several factors are usually examined, including the language and focus of the statute, its legislative history, and its purpose. Cort v. Ash, 422 U.S. 66, 78, 95 S.Ct. 2080, 2087, 45 L.Ed.2d 26 (1975). These factors need not be examined closely here because a private right of action is not " 'necessary to make effective the congressional purpose' ". Chrysler Corp. v. Brown, 441 U.S. 281, 317, 99 S.Ct. 1705, 1725, 60 L.Ed.2d 208 (1979) quoting J. I. Case v. Borak, 377 U.S. 426, 433, 84 S.Ct. 1555, 1560, 12 L.Ed.2d 423 (1964).

In Chrysler, as here, the Court found that the plaintiff could properly challenge the questioned administrative actions under the Administrative Procedure Act, 5 U.S.C. § 702, and thus, a private right of action under the substantive statute was unnecessary. See Fort Sumter Tours, Inc. v. Andrus, 564 F.2d 1119 (4th Cir. 1979) (when the existing concessionaire challenged certain acts by the Secretary under 16 U.S.C. § 20d, the court allowed a claim under the APA).

III.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vaqueria Tres Monjitas, Inc. v. Laboy
448 F. Supp. 2d 340 (D. Puerto Rico, 2006)
Australians for Animals v. Evans
301 F. Supp. 2d 1114 (N.D. California, 2004)
Dellums v. Smith
797 F.2d 817 (Ninth Circuit, 1986)
Oregon Natural Resources Council v. Marsh
628 F. Supp. 1557 (D. Oregon, 1986)
Preston v. Heckler
734 F.2d 1359 (Ninth Circuit, 1984)
Oregon Environmental Council v. Kunzman
714 F.2d 901 (Ninth Circuit, 1983)
California v. Watt
683 F.2d 1253 (Ninth Circuit, 1982)
Rank v. Nimmo
677 F.2d 692 (Ninth Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
663 F.2d 882, 1981 U.S. App. LEXIS 15360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glacier-park-foundation-v-watt-ca9-1981.