Oregon Ex Rel. Department of Environmental Quality v. Federal Energy Regulatory Commission

636 F.3d 1203, 2011 WL 711887
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 2, 2011
Docket09-70269, 09-70442, 09-70477
StatusPublished
Cited by20 cases

This text of 636 F.3d 1203 (Oregon Ex Rel. Department of Environmental Quality v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oregon Ex Rel. Department of Environmental Quality v. Federal Energy Regulatory Commission, 636 F.3d 1203, 2011 WL 711887 (9th Cir. 2011).

Opinion

OPINION

PER CURIAM:

The states of Oregon and Washington, Columbia Riverkeeper et al., and the Nez Perce Tribe (collectively, petitioners) seek review of a September 18, 2008 order of the Federal Energy Regulatory Commission (FERC). For the reasons stated below, we dismiss the petition for review as moot and vacate the agency’s September 18, 2008 order.

I

FERC’s September 18, 2008 order incorporated two different authorizations, each with conditions. First, pursuant to Section 3 of the Natural Gas Act (NGA), 15 U.S.C. § 717b(a), FERC authorized Bradwood Landing LLC (Bradwood) to site, construct, and operate a liquefied natural gas (LNG) import terminal in Clatsop County, Oregon. Second, pursuant to Section 7 of the NGA, id. § 717f(c)(1)(A), FERC issued a Certificate of Public Convenience and Necessity (CPCN) authorizing NorthernStar Energy LLC (NorthernStar) to construct and operate a natural gas pipeline that would connect the new Bradwood LNG terminal to the Pacific Northwest’s existing natural gas pipeline network. 1 The pipeline would traverse Clatsop and Columbia Counties, Oregon, and Cowlitz County, Washington. The FERC order also gave NorthernStar blanket certificates to perform certain routine construction activities and operations, and to provide transportation services on an open access basis. After FERC twice denied rehearing, the petitioners seek judicial review in this court under the Administrative Procedure Act. See 5 U.S.C. §§ 702, 704.

The parties have informed us that the following events occurred after the petition for review was filed. First, on May 4, 2010, Bradwood and NorthernStar filed petitions in bankruptcy for Chapter 7 liquidation. See In re NorthernStar Natural Gas, Inc., No. 10-33856 (Bankr. S. D.Tex.); In re Bradwood Landing LLC, No. 10-33867 (Bankr.S.D.Tex.). Second, in a letter dated August 18, 2010, Washington denied without prejudice the proponents’ request for certification under the Clean Water Act, (CWA) 33 U.S.C. § 1341(a)(1), 2 on account of the proponents’ failure to submit information requested by the state. Third, in a letter dated September 14, 2010, Oregon objected to the project proponents’ federal consistency determination under the Coastal Zone Management Act (CZMA), 16 U.S.C. § 1456(c)(3)(A). 3 Oregon made this objec *1206 tion because the project proponents had failed to provide required information, a component of the project was inconsistent with the state’s enforceable land use policies, and the project proponents had failed to obtain necessary state and local authorizations. Finally, on November 5, 2010, BL Credit Holdings, LLC purchased all permits and intellectual property owned by Bradwood at a foreclosure auction. 4

II

A case is moot when it has “lost its character as a present, live controversy of the kind that must exist if we are to avoid advisory opinions on abstract propositions of law.” Hall v. Beals, 396 U.S. 45, 48, 90 S.Ct. 200, 24 L.Ed.2d 214 (1969) (per curiam). We “are without power to decide questions that cannot affect the rights of litigants in the case before [us].’ ” DeFunis v. Odegaard, 416 U.S. 312, 316, 94 S.Ct. 1704, 40 L.Ed.2d 164 (1974) (per curiam) (quoting North Carolina v. Rice, 404 U.S. 244, 246, 92 S.Ct. 402, 30 L.Ed.2d 413 (1971)). This is such a case.

While FERC may authorize a permittee to transfer a Section 3 permit to a new project proponent, 18 C.F.R. § 153.9(a), the CPCN “is not transferable in any manner,” id. § 157.20(e). Once NorthernStar is liquidated in the bankruptcy proceeding, it will no longer exist, and thus will not be able to renew its efforts to obtain Washington’s certification under the CWA or Oregon’s concurrence in the proponents’ federal consistency determination under the CZMA, or proceed with the pipeline project in any other manner. Nor can it transfer the CPCN to a third party. While Bradwood’s Section 3 permit is theoretically transferable, the petitioners concede that the terminal and the pipeline essentially constitute a single project that will go forward together, or not at all, even though the terminal and the pipeline are formally subject to two different permits. Given that the project proponents have filed Chapter 7 petitions, and failed to demonstrate compliance with Washington state water quality standards or consistency with Oregon’s land use policies and project authorization requirements, the future of the project as currently permitted is in grave doubt.

Under these circumstances, the possibility that the project authorized by FERC’s September 18, 2008 order could be revived to threaten the interests of the petitioners is “too remote and too speculative a consideration to save this case from mootness.” Ctr. for Biological Diversity v. Lohn, 511 F.3d 960, 964 (9th Cir.2007) (citing Headwaters, Inc. v. Bureau of Land Mgmt., 893 F.2d 1012, 1015 (9th Cir.1989)). Consequently, we hold that the petitioners’ challenge to the FERC order is moot.

Ill

In cases where intervening events moot a petition for review of an agency order, the proper course is to vacate the underlying order. A.L. Mechling Barge Lines, Inc. v. United States, 368 U.S. 324, 330-31, 82 S.Ct. 337, 7 L.Ed.2d 317 (1961); see 15 U.S.C. § 717r(b). Accordingly, we dismiss the petition as moot and vacate FERC’s September 18, 2008 order.

PETITION DISMISSED; ORDER VACATED.

1

. We refer to the terminal and pipeline collectively as "the project,” and to Bradwood and NorthernStar collectively as the "project proponents.”

2

. The relevant portion of the CWA states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riggs v. Davis
D. Nevada, 2025
Hernandez v. Dzurenda
D. Nevada, 2025
Talamante v. Piaete
D. Nevada, 2025
Johnson v. Marks
D. Nevada, 2024
Olsen v. Becerra
E.D. Washington, 2022
Pg&e v. Ferc
Ninth Circuit, 2020
PayJoy, Inc. v. Cuccinelli
N.D. California, 2020
Alliance for the Wild Rockies v. Christopher Savage
897 F.3d 1025 (Ninth Circuit, 2018)
Barr v. Atlantic Coast Pipeline, LLC
815 S.E.2d 783 (Supreme Court of Virginia, 2018)
Idaho Rivers United v. Hudson
173 F. Supp. 3d 1027 (D. Idaho, 2016)
Fikre v. Federal Bureau of Investigation
142 F. Supp. 3d 1152 (D. Oregon, 2015)
Dennis Walker v. Beard
789 F.3d 1125 (Ninth Circuit, 2015)
California Ass'n of Rural Health Clinics v. Douglas
738 F.3d 1007 (Ninth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
636 F.3d 1203, 2011 WL 711887, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oregon-ex-rel-department-of-environmental-quality-v-federal-energy-ca9-2011.