One Bluff Drive, LLC v. K. A. P., Inc.

CourtCourt of Appeals of Georgia
DecidedNovember 21, 2014
DocketA14A1165
StatusPublished

This text of One Bluff Drive, LLC v. K. A. P., Inc. (One Bluff Drive, LLC v. K. A. P., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
One Bluff Drive, LLC v. K. A. P., Inc., (Ga. Ct. App. 2014).

Opinion

THIRD DIVISION BARNES, P. J., BOGGS and BRANCH, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

November 21, 2014

In the Court of Appeals of Georgia A14A1165. ONE BLUFF DRIVE, LLC et al. v. K. A. P., INC.

BRANCH, Judge.

A jury returned an award of $400,000 to a contractor on its claims against

certain homeowners for failure to pay the contractor in full for a major house

renovation; the jury also awarded $112,221 of attorney fees for bad faith, stubborn

litigiousness or causing the contractor unnecessary trouble and expense. Following

the denial of the homeowners’ motion for new trial, the homeowners appeal. The

homeowners do not challenge the sufficiency of the evidence. Instead, they contend

the trial court erred by charging the jury on quantum meruit and by denying their two

motions that attempted to limit the contractor’s possible damages. For the reasons

stated below, we affirm. On appeal following a jury verdict and judgment, this Court “must construe the

evidence with every inference and presumption in favor of upholding the verdict, and

after judgment, the evidence must be construed to uphold the verdict even where the

evidence is in conflict.” Harris v. Tutt, 306 Ga. App. 377, 378 (1) (702 SE2d 707)

(2010) (citation and punctuation omitted).

So construed, the evidence presented at trial relevant to the claims on appeal

shows that in 2006, K. A. P., Inc. (“KAP”), a general contractor, through its

owner/president, John Kicklighter, entered into an agreement with One Bluff Drive,

LLC and its sole member, Kenneth R. Hardigan, to supervise the construction of

improvements to the bottom floor of Hardigan’s residence located at 1 Bluff Drive

in Savannah. After KAP commenced work, Hardigan fired the architect, hired a

replacement, and significantly revised the scope of the project, including adding the

second floor to the scope. In response, KAP prepared a two-page, “Main Summary

Base Bid” showing a $1,092,943 estimated cost to complete the project as of

September 5, 2007; the detail supporting documents were attached thereto.

The Base Bid document is a table of values for the different aspects of the

project; it does not contain any contractual provisions or a projected completion date.

It was an estimate based on information that was limited at the time because Hardigan

2 had changed architects and the second architect had yet to prepare specifications or

a schedule for completion. KAP presented the Base Bid to Hardigan that evening, and

the parties added a “contingency” of $107,057 to bring the total estimate to $1.2

million; it was understood, however, that any changes to the scope of the project

reflected in the Base Bid would change the cost of the project. Thus, Kicklighter

testified, the project was to be billed on a time and materials basis. In meetings with

representatives of KAP, Hardigan acknowledged that he understood the nature of the

Base Bid. The Base Bid also reflects that KAP chose not to charge for any overhead

or profit; Kicklighter testified that he did so because of his friendship with Hardigan

and because the two had worked together on several other projects. The following

day, KAP delivered a letter to Hardigan that referenced their meeting on the prior

evening “with regards to the budget number we met about last night.” The letter

continued, “The 1.2 million budget (worked on a time and material basis) for KAP

was based upon the newly acquired renovation drawings from [the second architect].”

After work continued on the project, Hardigan increased the scope of the work

“many times,” including changes that required ripping out work already performed.

KAP presented evidence that because of additions and changes to the scope of the

work, the total cost of time and materials for the project exceeded $1.5 million. Given

3 that the parties stipulated that Hardigan ultimately paid KAP $1,102,479.30, KAP

presented evidence that Hardigan owed KAP in excess of $459,000. At one point

toward the end of the project, Hardigan contacted KAP and asked, “I need a number

from you to complete this house. I don’t know what the number is, but could you give

me the number that it’s going to take to finish this house?” Hardigan intended to

borrow additional funds to complete the project based on that number. Based on the

information available at that time, KAP projected the remaining costs to be $300,000,

and Hardigan sought and obtained an additional loan of $350,000 but did not use it

to pay KAP. KAP finished the project, obtained a certificate of occupancy, and

submitted the final two invoices totaling $511,243 to Hardigan. Hardigan moved into

the house and lived there for three years but never paid KAP the total amount due.

On September 29, 2009, KAP filed suit to foreclose on a lien it filed in May

2009. On December 28, 2010, the appellants moved for partial summary judgment,

arguing that KAP’s Base Bid represented a fixed-sum contract and, therefore, that the

amount of damages KAP could recover was limited to the costs of the extras and

changes beyond the scope of the original contract. On June 17, 2011, the trial court

denied the motion, rejecting the argument that the parties entered into an agreement

as to the maximum amount that could be charged for changes to the Base Bid. On

4 November 14, 2011, the appellants moved in limine to prohibit KAP from

introducing evidence of the total costs of the project. The trial court denied the

motion. The case was tried before a jury in September 2013.

1. The appellants contend the trial court erred by charging the jury on the law

of quantum meruit because KAP never raised a claim under that theory and that KAP

was required to plead quantum meruit in a separate count. We hold that the

appellants’ arguments are baseless as a matter of fact and law.

“A trial court has a duty to charge the jury on the law applicable to issues

which are supported by the evidence. If there is even slight evidence on a specific

issue, it is not error for the court to charge the jury on the law related to that issue.”

Jones v. Sperau, 275 Ga. 213, 213 (2) (563 SE2d 863) (2002). “Whether the evidence

presented is sufficient to authorize the giving of a charge is a question of law.” Davis

v. State, 269 Ga. 276, 279 (496 SE2d 699) (1998). We therefore review the issue de

novo. See Jordan v. State, 322 Ga. App. 252, 256 (4) (a) (744 SE2d 447) (2013).

The essential elements of a claim of quantum meruit are that the provider

performed services valuable to the recipient that were requested by or knowingly

accepted by the recipient, that the recipient’s receipt of the services without

compensating the provider would be unjust, and that the provider expected

5 compensation at the time the services were performed. Hollifield v. Monte Vista

Biblical Gardens, 251 Ga. App. 124, 128-129 (2) (a) (553 SE2d 662) (2001). See also

OCGA § 9-2-7 (“Ordinarily, when one renders service or transfers property which is

valuable to another, which the latter accepts, a promise is implied to pay the

reasonable value thereof.”). And, even if there is an express contract,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Biederbeck v. Marbut
670 S.E.2d 483 (Court of Appeals of Georgia, 2008)
Brannen v. Lanier
102 S.E.2d 96 (Court of Appeals of Georgia, 1958)
American Teleconferencing Services, Ltd. v. Network Billing Systems, LLC
668 S.E.2d 259 (Court of Appeals of Georgia, 2008)
Llop v. McDaniel, Chorey & Taylor
320 S.E.2d 244 (Court of Appeals of Georgia, 1984)
Forsyth County v. Martin
610 S.E.2d 512 (Supreme Court of Georgia, 2005)
Oliver v. Irvin
196 S.E.2d 429 (Supreme Court of Georgia, 1973)
Coregis Insurance v. Nelson
639 S.E.2d 365 (Court of Appeals of Georgia, 2006)
Gerdes v. Russell Rowe Communications, Inc.
502 S.E.2d 352 (Court of Appeals of Georgia, 1998)
Hollifield v. Monte Vista Biblical Gardens, Inc.
553 S.E.2d 662 (Court of Appeals of Georgia, 2001)
Jones v. Sperau
563 S.E.2d 863 (Supreme Court of Georgia, 2002)
Andrews v. Wilbanks
458 S.E.2d 817 (Supreme Court of Georgia, 1995)
G. E. C. Corp. v. Southern Fabricators, Inc.
177 S.E.2d 497 (Court of Appeals of Georgia, 1970)
Gosule v. Bestco, Inc.
490 S.E.2d 532 (Court of Appeals of Georgia, 1997)
Stowers v. Hall
283 S.E.2d 714 (Court of Appeals of Georgia, 1981)
Nee v. State Farm Fire & Casualty Co.
236 S.E.2d 880 (Court of Appeals of Georgia, 1977)
Franklin v. Gwinnett County Public Schools
407 S.E.2d 78 (Court of Appeals of Georgia, 1991)
Kwickie/Flash Foods, Inc. v. Lakeside Petroleum, Inc.
541 S.E.2d 699 (Court of Appeals of Georgia, 2000)
Davis v. State
496 S.E.2d 699 (Supreme Court of Georgia, 1998)
Puritan Mills, Inc. v. Pickering Construction Co.
262 S.E.2d 586 (Court of Appeals of Georgia, 1979)
Harris v. Tutt
702 S.E.2d 707 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
One Bluff Drive, LLC v. K. A. P., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/one-bluff-drive-llc-v-k-a-p-inc-gactapp-2014.