K.A.P., Inc. v. Hardigan

560 B.R. 895, 2016 U.S. Dist. LEXIS 157841, 2016 WL 6803100
CourtDistrict Court, S.D. Georgia
DecidedNovember 15, 2016
DocketCV 416-089; Bankr. Case No. 12-40484; Advers. Case No. 12-04069
StatusPublished
Cited by3 cases

This text of 560 B.R. 895 (K.A.P., Inc. v. Hardigan) is published on Counsel Stack Legal Research, covering District Court, S.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K.A.P., Inc. v. Hardigan, 560 B.R. 895, 2016 U.S. Dist. LEXIS 157841, 2016 WL 6803100 (S.D. Ga. 2016).

Opinion

ORDER

HONORABLE J. RANDAL HALL, UNITED STATES DISTRICT JUDGE, SOUTHERN DISTRICT OF GEORGIA

Creditor K.A.P., Inc. (“Appellant”) appeals from the Bankruptcy Court’s March 28, 2016 Order granting summary judgment against Appellant and in favor of Debtor Dr. Kenneth R. Hardigan (“Appel-lee”) and finding that Appellee’s debt to Appellant was dischargeable through Ap-pellee’s Chapter 7 Bankruptcy. Because Appellant fails to present sufficient factual evidence to create a genuine dispute as to the disputed element of its claim, this Court AFFIRMS the Bankruptcy Court’s Order. -'

I. BACKGROUND

In 2006, Appellee purchased a home in Savannah, Georgia (the “Property”). (Bankruptcy Record, Doc. 3-2, at R:481.)1 In September 2007, Appellee hired Appel[897]*897lant, a general contractor engaged in the construction of commercial and residential buildings, to make substantial renovations to the Property (the “Project”). (R:1147-50, 1503-05.) The parties never memorialized them verbal agreement with a written contract, but agreed that Appellant would perform the renovations at cost and on a “time-and-materials” basis. (R:1503-05.) After receiving bids from subcontractors, Appellant presented Appellee with a “base bid” anticipated Project budget of $1,092,943.00. (R:482, 507-36, 1503-05.) Appellee subsequently borrowed $1,095,000.00 from non-party SunTrust Bank (“SunTrust”) to finance the Project (the “First Loan”). (R:483.) During its work on the Project, Appellant would submit periodic invoices to Appellee for payment,2 which, for the majority of the Project, Appellee timely paid. (R:537-53,1292, 1294,1422-98,1661.)

Over the course of the Project, Appellee requested numerous revisions and upgrades to the Project’s original plans, thereby increasing the Project’s scope and expense. By October 2008, despite work still remaining to be done, Appellee had exhausted the proceeds from the First Loan. (R:469.) Indeed, he was only able to pay $206,000,00 towards Appellant’s October 23, 2008 inyoice of $238,866.00. (R-.546-48.)

In an effort to secure additional financing, Appellee sought revised estimates from Appellant as to the anticipated cost to finish the Project. (R:1292-93,1619.) On December 12, 2008, Appellant provided Appellee with an estimated additional budget of $314,417.00, with' which Appellee was able to obtain a commitment for an unsecured loan of $350,000.00 from Sun-Trust (the “Second Loan”). (R:555-58, 1294, 1340-44, 1619, 1661-62.) Based on assurances from Appellee in late December 2008 or early January 2009 that he would satisfy any arrears and finance the completion of the Project with the funds recently obtained from SunTrust and directions from Appellee to complete the Project, Appellant resumed work.on the Project. (R:1296, 1300, 1307-08, 1619-20.) On or about January 21, 2009, Appellee received the proceeds from the Second Loan (i.e., $350,000.00) from SunTrust.3 (R:1282-84, 1304.) Despite, having received these funds, Appellee never made any payments to Appellant to satisfy -its arrears from October. 2008 or any other subsequent invoices,4

On February 26, 2009, Appellant finished the Project. (R:1306, 1608-09.) Ap-pellee took up residence in the Property in mid-March 2009. After Appellee failed to satisfy the amounts outstanding to Appellant, Appellant placed a materialmen’s lien on the Property in the amount of $544, 109.93 ori May 18,2009. (R:606-08.)

On September 24, 2009, Appellant filed suit against Appellee for breach of contract in the Superior Court of Chatham Courity, Georgia, CAFN: CV-09-2276-AB [898]*898(the “State Action”). (R:610-15.) On March 7, 2012, Appellee filed for relief under Chapter 7 of the Bankruptcy Code. On October 17, 2012, Appellant initiated the instant adversary proceeding to determine the dischargeability of Appellee’s debt (the “Adversary Action”). (R.T6-21.) On January 22, 2013, the Bankruptcy Court entered an order in the Adversary Action abstaining from further proceedings pending the resolution of the State Action. (R:364-71.) In September 2013, a jury awarded $400,000.00 in damages in favor of Appellant in the State Action.5 (R:476.)

On March 3, 2015, the Bankruptcy Court entered an Order granting Appellee’s requested Chapter 7 discharge. On September 30, 2015, Appellee moved for summary judgment against Appellant in the Adversary Action. (R:452-65.) On March 28, 2016, the Bankruptcy Court entered summary judgment in favor of Appellee and against Appellant. (R:1667-85.) Appellant subsequently perfected the present appeal.

II. JURISDICTION AND STANDARD OF REVIEW

This Court has appellate jurisdiction pursuant to 28 U.S.C. § 158(a)(1) and Bankruptcy Rules 8001 et seq. On appeal, the Court reviews the Bankruptcy Court’s grant of summary judgment de novo. In re Optical Techs., Inc., 246 F.3d 1332, 1335 (11th Cir. 2001).

Summary judgment is appropriate only if “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); see also Fed. R. BankR. P. 7056. The Court shall grant summary judgment “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to summary judgment as a matter of law.” Hickson Corp. v. N. Crossarm Co., 357 F.3d 1256, 1259, 1260 (11th Cir. 2004); Fed. R. Civ. P. 56(c). The “purpose of summary judgment is to pierce the pleadings and to assess the proof in order to see whether there is a genuine need for trial.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986) (internal citation omitted).

“[The] party seeking summary judgment always bears the initial responsibility of informing the district court of the basis for its motion, and identifying those portions of the [record before the court] which it believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). If—and only if—the movant carries its initial burden, the non-movant may avoid summary judgment by demonstrating that there is indeed a genuine issue as to the material facts of its case. Clark v. Coats & Clark, Inc., 929 F.2d 604, 608 (11th Cir. 1991). Facts are “material” if they could affect the outcome of the suit under the governing substantive law. Anderson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robb v. Gividen
N.D. Georgia, 2025
Pucci, Sr v. Hill
N.D. Georgia, 2021
Shaw v. Osborne
M.D. Georgia, 2020

Cite This Page — Counsel Stack

Bluebook (online)
560 B.R. 895, 2016 U.S. Dist. LEXIS 157841, 2016 WL 6803100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kap-inc-v-hardigan-gasd-2016.