Olyphant v. St. Louis Ore & Steel Co.

28 F. 729, 1886 U.S. App. LEXIS 2345
U.S. Circuit Court for the District of Eastern Missouri·Decided September 22, 1886·Published·Cited by 4 cases

Opinion

Brewer, J.,

(orally.) In the matter of the intervening petition of ' the Lackawanna Iron & Coal Company in the case of Olyphant v. St. Louis Ore & Steel Company, the facts are that the ore and steel company, organized for the manufacture of steel rails as well as for the [730] mining of ore, made some contracts with railroad companies in 1883 for the sale to them of steel rails, deliverable monthly at a fixed price. Instead of itself manufacturing those rails, it turned around and made contracts with other manufacturing companies, among them the Lackawanna Company, for the manufacture by them of rails at a less price than that at which it agreed to sell to the railroad companies. These contracts were partially carried out. Several thousand tons of rails were manufactured by the Lackawanna Company, delivered to the Ore and Steel Company, and by it delivered to the railroad companies.

At the time the receiver was appointed, the value of the rails delivered by the Lackawanna Company was $167,248.12. Of that sum $109,207.79 had been paid; $22,040.33 remained confessedly unpaid; $36,000 had been disposed of, temporarily at least, by the Ore and Steel Company sending their accepted drafts on Cherrie & Co. to the Lackawanna Company, giving assurances that those drafts would be paid by Cherrie & Co., and directing the Lackawanna Company to collect those drafts, and apply the amount on the claim. Those drafts were accepted by Cherrie & Co., but shortly thereafter Cherrie & Co. became insolvent, and an assignee was appointed under the laws of the state of Illinois, in which they did business. The Lacka-wanna Company presented those acceptances to the assignee, and they were allowed, but'nothing has ever been realized upon them. A part of the claim of the Lackawanna Company is for that sum of $36,000. The Ore and Steel Company insists that the action of the Lackawanna Company in presenting these acceptances to Cherrie’s assignee, and obtaining an allowance, was equivalent to a personal appropriation of those acceptances, and made them to operate as payment. We think not. They were never taken, in the first instance, as payment. There was no agreement that they should be accepted as payment. They were received under directions to collect whatever could be collected on them, and apply on the debt; and the mere fact that the Lackawanna Company proceeded in good faith to try and collect them of the assignee of Cherrie & Co. did not amount to an appropriation by it of those acceptances so far as to release its claims against the Ore and Steel Company. We think, therefore, the master was right in allowing that amount as a demand against the Ore and Steel Company.

In the petition filed in July by the trustee of one of the mortgages on the Ore and Steel Company, he stated the insolvent condition of the Ore and Steel Company; set forth these contracts; and prayed for the appointment of a receiver, with power to maintain and operate a railroad which belonged to the Ore and Steel Company, to keep the same in proper repair, and to operate the coal and ore mines, and to carry out and perform said contracts for the delivery of coal and ore, and the purchase and sale of steel rails.

In the order of the court appointing the receiver, he was directed [731] to carry out and perform the contracts of the Ore and Steel Company for the purchase and sale of steel rails, and to preserve and protect all the property of said corporation, and to collect, as far as possible, all accounts, dioses in actions, and credits due the said company, acting in all things under the order of this court. Now it is insisted that this claim for unpaid moneys should, by virtue of this order, be given priority over the mortgages upon the Ore and Steel Company. Counsel concede that but for this order such a claim for moneys due would be simply a general claim, and entitled to no priority over secured indebtedness. Indeed, that is very evident; for the claim has none of the equities of a supply claim. It was not for supplies purchased to enable the Ore and Steel Company to carry on its legitimate business of mining or manufacturing; neither was it a contract for betterments. It was really no more than a speculative contract, by which it, instead of mining and manufacturing, went into the market, and bought from one party for the purpose of soiling to another. But the argument is this: As the Ore and Steel Company was a defaulter in the payment for rails already manufactured and delivered by the Lackawanna, Company, and as there was a single contract extending forward into the future for the delivery of further rails, when the court directed its receiver, on the petition of the trustee of the mortgage, to carry out and perform, that contract, it virtually assumed it in its entirety as one made by the court for tho benefit of the property in tho hands of tho receiver. It is said that the Lackawanna Company was under no obligations to deliver any more rails, but could treat the contract as then terminated, and present its claim for the unpaid balance; and that when the court, at the instance of the bondholders, directed the carrying out and fulfillment of the contract, it could not thereby appropriate that which was beneficial, and repudíalo that which was burdensome, but took it as an entirety, and cast, therefore, upon the property in the hands of the receiver a lion prior to that of tho mortgage.

Free access — add to your briefcase to read the full text and ask questions with AI

Olyphant v. St. Louis Ore & Steel Co., 28 F. 729, 1886 U.S. App. LEXIS 2345 (circtedmo 1886).

28 F. 729 (Olyphant v. St. Louis Ore & Steel Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Guaranty Trust Co. v. Seaboard Air Line Ry. Co.
14 F. Supp. 555 (E.D. Virginia, 1935)
Pacific Western Oil Co. v. McDuffie
69 F.2d 208 (Ninth Circuit, 1934)
Jackson v. Washington, Baltimore, & Annapolis Electric Railway Co.
35 App. D.C. 41 (District of Columbia Court of Appeals, 1910)
Breed v. Glasgow Inv. Co.
92 F. 760 (U.S. Circuit Court for the District of Western Virginia, 1899)