Jackson v. Washington, Baltimore, & Annapolis Electric Railway Co.

35 App. D.C. 41, 1910 U.S. App. LEXIS 5863
CourtDistrict of Columbia Court of Appeals
DecidedApril 5, 1910
DocketNo. 2082
StatusPublished

This text of 35 App. D.C. 41 (Jackson v. Washington, Baltimore, & Annapolis Electric Railway Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson v. Washington, Baltimore, & Annapolis Electric Railway Co., 35 App. D.C. 41, 1910 U.S. App. LEXIS 5863 (D.C. 1910).

Opinion

Mr. Justice Robb

delivered the opinion of the Court:

There are but two assignments of error, both relating to the court’s instruction to the jury as to the measure of damages. Since the question as to whether the appellee was guilty of a breach of the contract was submitted to the jury at the instance of the appellee, it is estopped to deny the propriety of [46]*46such submission. Capital Traction Co. v. Brown, 29 App. D. C. 473, 12 L.R.A. (N.S.) 831, 10 A. & E. Ann. Cas. 813; Steven v. Saunders, 34 App. D. C. 321. We are here concerned, therefore, with the single question of the correctness of the court’s instruction as to the measure of damages.

As to the rule of damages to be applied to the ties actually in possession of the contractor when the breach occurred, there is no controversy. The contractor admits that, as to them, damages based on the difference between the contract price and the market value would be proper. Our inquiry, therefore, narrows to the ties not in the possession of the contractor at that .time.

The Supreme Court of the United States appears squarely to have met this issue in Roehm v. Horst, 178 U. S. 1, 44 L. ed. 953, 20 Sup. Ct. Rep. 780. In that case, the plaintiff had contracted with the defendant to supply him with hops for a period of five years, at a fixed price.- There was a breach by the defendant after partial performance by the plaintiff. The plaintiff introduced evidence showing at what prices he could have made subcontracts for the sale of the hops which defendant refused to take, these prices being considerably lower than those named in the.original contract. After reaffirming the prevailing and undoubted doctrine that after refusal to perform by one party to a contract, the other party need make no further attempt to carry out its provisions, but may consider it at an end, the court said: “As to the question of damages, if the. action is not premature, the rule is applicable that plaintiff is entitled to compensation, based, as far as possible, on the ascertainment of what he would have suffered by -the continued breach of the other party down to the time of complete performance, less any abatement by reason of circumstances of which he ought reasonably to have availed himself. If a vendor is to manufacture goods, and, during the process of manufacture, the contract is repudiated, he is not bound to complete the manufacture,. and estimate his damages by the difference between the market price and the contract price, but the measure of damage is the difference between the contract price and the cost of performance. [47]*47Hinckley v. Pittsburgh Bessemer Steel Co. 121 U. S. 264, 30 L. ed. 967, 7 Sup. Ct. Rep. 875. Even if, in such cases, the manufacturer actually obtains his profits before the time fixed for performance, and recovers on a basis of cost which might have been increased or diminished by subsequent events, the party who broke the contract before the time for complete performance cannot complain, for he took the risk involved in such anticipation. If the vendor has to buy instead of to manufacture, the same principle prevails, and he may show what was the value of the contract by showing for what price he could have made subcontracts, just as the cost of manufacture in the case of a manufacturer may be shown. Although he may receive his money earlier in this way, and may gain or lose by the estimation of his damages in advance of the time for performance, still, as we have seen, he has the right to accept the situation tendered him, and the other party cannot complain.

“In this case, plaintiffs showed at what prices they could have made subcontracts for forward deliveries according to the contracts in suit, and the difference between the prices fixed by the contracts sued on and those was correctly allowed.”

In the recent case of River Spinning Co. v. Atlantic Mills, 155 Fed. 466, the plaintiff contracted to sell, and the defendant to buy, a quantity of wool. It was contemplated that plaintiff would manufacture same at its mills, but there was no limitation to that effect, and the court found that “its [plaintiff’s] obligation would have been fully performed by the tender of yarn of like quality, spun at other mills.” When the breach took place, the plaintiff had manufactured and had on hand but a portion of the undelivered yarn. As to this yarn, the court held that the measure of damages “should he the difference between the contract price and the value of the yarn in plaintiff’s hands.” But, as to yarn not manufactured and on hand, the court said: “While this is a just rule to determine a loss of profits on goods ready for delivery at the time of the breach, as was pointed out in Kingman & Co. v. Western Mfg. Co. 34 C. C. A. 489, 92 Fed. 486, 490, it is not the true rule as to goods not then made and ready for delivery. It is a just rule [48]*48for the buyer in a suit by him, because, on the breach, having the money in hand, he may procure the goods on the market, and charge the seller- with the difference. But to measure the damages of a seller who has not the goods on hand by the difference between the contract price and the market price is often impractical, and would often be unjust. ■ It would be equally unjust in a case where the seller was to make the goods himself, and in a case where he was to procure the goods from other manufactures or jobbers. If the vendor can make his goods for less than the market price, he is entitled to his actual profit. If his goods are to be bought, or to be made for him by other contractors, above the market price, then his profit would be smaller than the difference between the contract price and the market price. Only if the cost of production and the market price at the breach were the same would the rule be just, and this is practically to say that the rule would seldom be a just mode of determining the loss of profits.

“That there is in a suit by the seller no proper basis for a distinction between goods which he is to manufacture (whether bound to manufacture or-not) and goods which he is to buy, instead of to manufacture, is apparent from the reasoning of the Supreme Court in Roehm v. Horst, 178 U. S. 1, 21, 44 L. ed. 953, 961, 20 Sup. Ct. Rep. 780.” See also: Tufts v. Weinfeld, 88 Wis. 647, 60 N. W. 992; Olyphant v. St. Louis Ore Steel Co. 28 Fed. 729; Eckenrode v. Chemical Co. 55 Md. 51.

The decisions cited leave no room for doubt as to the rule to be applied here in determining damages. We therefore hold that the contractor is entitled to recover the difference between the contract price of the ties which the company refused to take, but which the contractor .did not have on hand when the breach occurred, and the amount which it would have cost the contractor to supply them. As to the ties actually on hand at the date of the breach, we have already stated that the measure of damages should be the difference between the contract price and the market value.

The unjustness of the rule contended for by appellee is obvi[49]*49ous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hinckley v. Pittsburgh Bessemer Steel Co.
121 U.S. 264 (Supreme Court, 1887)
Roehm v. Horst
178 U.S. 1 (Supreme Court, 1900)
Eckenrode v. Chemical Co.
55 Md. 51 (Court of Appeals of Maryland, 1880)
Tufts v. Weinfeld
60 N.W. 992 (Wisconsin Supreme Court, 1894)
Olyphant v. St. Louis Ore & Steel Co.
28 F. 729 (U.S. Circuit Court for the District of Eastern Missouri, 1886)
River Spinning Co. v. Atlantic Mills
155 F. 466 (U.S. Circuit Court for the District of Rhode Island, 1907)
Yellow Poplar Lumber Co. v. Chapman
74 F. 444 (Fourth Circuit, 1896)
Kingman & Co. v. Western Mfg. Co.
92 F. 486 (Eighth Circuit, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
35 App. D.C. 41, 1910 U.S. App. LEXIS 5863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-v-washington-baltimore-annapolis-electric-railway-co-dc-1910.