Olinkraft, Inc. v. Gerard

364 So. 2d 639
CourtLouisiana Court of Appeal
DecidedOctober 30, 1978
Docket13658
StatusPublished
Cited by3 cases

This text of 364 So. 2d 639 (Olinkraft, Inc. v. Gerard) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olinkraft, Inc. v. Gerard, 364 So. 2d 639 (La. Ct. App. 1978).

Opinion

364 So.2d 639 (1978)

OLINKRAFT, INC., Plaintiff-Appellee,
v.
Charles H. Coster GERARD, Defendant-Appellant.

No. 13658.

Court of Appeal of Louisiana, Second Circuit.

October 30, 1978.

*640 Shotwell, Brown & Sperry by Burt W. Sperry and George Wear, Jr., Monroe, for plaintiff-appellee.

Bodenheimer, Jones, Klotz & Simmons by David B. Klotz, Shreveport, for defendant-appellant.

Before BOLIN, HALL and JONES, JJ.

JONES, Judge.

Defendant, Charles H. Gerard, appeals a judgment rendered in this declaratory judgment proceedings which (1) denied the cancellation, insofar as it was applicable to gas produced from Section 35, of a Gas Sale and Purchase Contract between Franks Petroleum, Inc. and Olinkraft, Inc. (2) denied him an increase in the price of the gas above that provided for in the Franks-Olin contract and (3) denied payment for all gas not taken, based upon deliverability of 2000 MCF per day between the period of August 20, 1975 and January 29, 1976. We affirm.

Defendant acquired by assignment from Franks leases in Section 35 subject to the Gas Sale and Purchase Contract between Franks and Olin. The contract provided Olin was entitled to receive 33.3975% of all gas produced in Section 35.

Defendant also owned approximately 21% of the leases on adjacent Section 36, however, none of any production which he might receive from these leases was dedicated to the Franks-Olin contract. Approximately 50% of the leases in Section 36, owned by others, was subject to the Franks-Olin contract and from which Olin was entitled to the gas production.

In the fall of 1974, Olin was interested in securing at the earliest possible date, gas production in Sections 35 and 36 in order to provide gas for the operation of its papermill in Ouachita Parish, Louisiana. As an incentive to encourage the defendant to *641 diligently seek production in Sections 35 and 36 Olin, on October 21, 1974[1] offered defendant an increase in the price from $.435 MCF provided for in the Franks-Olin contract to $.57 MCF for all gas it purchased produced from Section 35. The price increase was conditioned upon defendant advising Olin before November 11, that he was committed to the drilling and participation in a well in Section 35 (Sanford well) and a well in Section 36 (Browder well) and upon both wells being commenced (spudded) before December 31, 1974.

The defendant by letter to Olin on November 5, 1974 accepted the terms and conditions of Olin's letter of October 21, 1974. Defendant spudded the Sanford well in Section 35 on November 22, 1974 and had prior to that date entered into an agreement with all other lease owners in Section 36 designating Tensas Delta Land Company as an operator to secure the drilling of the Browder well. On November 12, 1974, Tensas Delta contracted with Garrett and Starkey to drill the Browder well with a contemplated spudding date of on or before December 31, 1974.

On December 19, 1974, Tensas Delta requested permission of all working interest owners to change the starting date of the Browder well to January 31, 1975 and the defendant agreed to this change on December 20, 1974. All other working interest owners agreed to the change in the drilling contract and it was changed. The change in the starting date of the Browder well was requested because Sawyer Drilling and Service, Inc., who had subcontracted the drilling of the well from Garrett and Starkey, did not have a rig available to commence the well until the latter part of January 1975.

Because defendant would not be entitled to the increase in the gas price for his production in Section 35 if the Browder well in Section 36 was not spudded by December 31, 1974, he sought an extension of the required spudding date from Olin. Olin denied the extension. Defendant then, with the permission of Tensas Delta, Garrett and Starkey, and Sawyer, had an 18 inch diameter, 22 foot hole drilled by a water well drilling rig at the Browder well site and inserted in the hole a conductor pipe on December 31, 1974 in an attempt to comply with the spudding requirements of his Olin agreement. The pipe was not cemented into place in accord with the practice usually followed in connection with the installation of conductor pipes. The actual arrangements for the drilling of the 22 foot hole and the installation of the conductor pipe were made with the water well drilling company by Sawyer at the request of the defendant. The specifications of the drilling contract for the Browder well did not provide for the installation of a conductor *642 pipe. The installation of the conductor pipe, which cost approximately $1,000, was billed to and paid for by the defendant.

In the latter part of December 1974, there was some preliminary dirt work on the Browder location, however, Sawyer did not bring the deep well drilling rig to the Browder location until January 22, 1975, and the actual drilling of the well was not commenced until January 24, 1975.

The Sanford well was completed as a producer and Olin received its first delivery from it September 27, 1975. Olin considered the Browder well to have been spudded on January 24, 1975 and rejected defendant's contention that the well was spudded by the drilling of the 22 foot hole and installation of the conductor pipe on December 31, 1974. Olin paid for the Sanford gas at the rate of $.435 MCF as provided for in the Franks-Olin contract, rather than at the rate of $.57 MCF which it had offered in its letter of October 21, 1974.

In addition to the price issue, the parties have an unrelated dispute with regard to Olin's obligation to pay under the "take or pay" provision of the Franks-Olin contract on the gas produced from the Sanford well. Defendant contends that deliverability of the Sanford well was established by the Louisiana Department of Conservation test at 2000 MCF per day and that under the terms of the contract, Olin was required to take 33.3975% of a minimum of 2000 MCF per day whether or not this volume of gas was actually produced. Defendant contends Olin was required to pay for all gas not taken by it up to the minimum amount calculated upon 2000 MCF per day for each day commencing the day of the first production, August 20, 1975, until January 29, 1976 (excluding the last 17 days of October when the well was admitted to be out of production) after which date Olin was taking more than it was required to take based upon this formula. The applicable provisions of the contract are:

"The term `Minimum Quantity' shall mean an average daily quantity of gas in each Contract year, determined as provided in Article IV of this contract, which Buyer is obligated to take or pay for if available to Buyer and not taken. (Article I)
2. Subject to the other provisions hereof, Buyer agrees to purchase and receive from Seller, on as nearly a uniform daily basis as the operation of Buyer's pipeline and manufacturing plants will permit, a quantity of gas each day during the term hereof which will average in each calendar month not less than the greater of (i) the sum of: (a) Seller's interest in two and one-half million (2,500,000) cubic feet of gas for each well completion capable of delivering two and one-half million (2,500,000) cubic feet of gas per day or more (b) Seller's interest in the total deliverability of each well completion capable of delivering less than two and one-half million (2,500,000) cubic feet of gas per day . . . . (Article IV(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Succession of Larmore
527 So. 2d 978 (Louisiana Court of Appeal, 1988)
Succession of Larmore
518 So. 2d 1085 (Louisiana Court of Appeal, 1987)
Mitchell's Refrigeration, Inc. v. Bana Commercial Kitchen Parts, Inc.
465 So. 2d 892 (Louisiana Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
364 So. 2d 639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olinkraft-inc-v-gerard-lactapp-1978.