Oles v. Plummer

444 N.E.2d 879, 1983 Ind. App. LEXIS 2562
CourtIndiana Court of Appeals
DecidedJanuary 27, 1983
Docket1-682A123
StatusPublished
Cited by8 cases

This text of 444 N.E.2d 879 (Oles v. Plummer) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oles v. Plummer, 444 N.E.2d 879, 1983 Ind. App. LEXIS 2562 (Ind. Ct. App. 1983).

Opinions

NEAL, Judge.

STATEMENT OF THE CASE

Defendants-Appellants Michael L. Oles and Florence M. Oles (Oles) appeal a judgment entered in the Montgomery Circuit Court in which the court granted plaintiffs-appellees Gerald G. Plummer’s and Janet Dee Plummer’s (Plummers) suit for specific performance on a conditional land sales contract and denied Oles’ counterclaim seeking forfeiture of the contract.

We affirm.

STATEMENT OF THE FACTS

The facts most favorable to the decision show that on May 1,1972, Oles entered into a contract to sell 14.5 acres of farm land in Boone County to Plummers. The sale price was $11,600, $1,000 down payment and monthly payments of $100, which payments apparently included 7% interest which was computed semi-annually. The contract was a conditional sale contract printed on an “approved Standard Form” Land Contract adopted by the Indiana Real Estate Association, Inc., and it contained the usual clauses requiring the buyer to pay the taxes, insurance, assessments, to make repairs, forbidding assignment, and prohibiting the commission of waste. Also, it contained a forfeiture clause and a “time is of the essence” payment clause. The payments, which commenced in June, 1972, were met by Plummers, more or less, but irregularly, and at the end of three years they were in arrears only $400. By October 3, 1978, the date of the last payment, they were in arrears only $200. At that point Plummers [881]*881had paid $8,500 on the contract and the unpaid balance on the principal was $8,056.15. There was evidence that Plum-mers demanded a statement of a payoff balance, but Oles refused to give one. In any event, no further payments were made until November, 1980, and the contract was in default by Plummers.

On November 3,1980, Oles’ attorney sent Plummers a letter to which he attached a schedule of the payments made, and demanded the payoff balance of $9,431.96. This amount included the $8,056.15 plus subsequently accrued taxes, ditch assessments and interest. The letter also included a demand for payment of $440 for personal property allegedly damaged or taken by Plummers and not connected with the real estate contract. The letter concluded with the statement, “We are giving you until November 15, 1980, to pay the contract in full. If we do not hear from you within the ten (10) day period we will institute our suit to cancel and terminate the contract to purchase this real estate.”

Plummers called the attorney the next day and after making and cancelling meetings, the parties met on December 3, 1980. Plummers tendered Oles a certified check for $9,431.96, which they had obtained by financing, but Oles refused to accept it. Plummers refused to pay the $440 demand. Oles testified that they refused to accept the check because Plummers had voided the contract. There was contradictory evidence about payment of taxes and the commission of waste. There was evidence that Plum-mers had agreed to resell the property but only on condition they could get a deed from Oles.

Although the contract was in default, and demands were made by Oles for payment, no evidence exists of any effort by Oles to terminate the contract until the November 3,1980 letter. Oles’ own witnesses testified that both parties wanted the property paid off, and Oles merely demanded that Plum-mers comply with the contract. Further evidence disclosed that there was a rapid rise in farm prices, rental, and interest rates in Boone County during the eight years the contract was in effect.

Upon Oles’ refusal to accept the check, Plummers brought suit for specific performance on January 7,1981, and deposited with the court the sum of $9,431.96. Oles filed their answer alleging breach of contract, and further filed a counterclaim seeking forfeiture of the contract; damages for occupancy; $200 for limestone and fertilizer; $200 for a wagon; $240 for equipment and attorney fees.

The trial court, in lengthy findings of fact and conclusions of law, granted specific performance to Plummers under the doctrine of Skendzel v. Marshall, (1973) 261 Ind. 226, 301 N.E.2d 641, and denied Oles’ counterclaim in its entirety.

ISSUES

The issues which Oles present for review consist of challenges that certain findings of fact and conclusions of law are not supported by the evidence or are contrary to the evidence. We shall group them for discussion as follows:

Issue I. Findings of fact Nos. 17,18, and conclusions of law No. 1 and 2, which concern the applicability of Skendzel v. Marshall. They are as follows:
Finding No. 17. That of the sum of $8,500 plaintiffs have paid, approximately $4,500 has been applied to interest and approximately $4,000 to principal as of the date of the last payment. Finding No. 18. That the payments of such amounts constitute substantial payment.
Conclusion No. 1. That the remedy of forfeiture is too harsh a remedy to be applied against the plaintiff on the above facts.
Conclusion No. 2. That the case of Skendzel v. Marshall applies to these above facts and governs this case.
Issue II. Findings of fact Nos. 8, 19, and 20 relate to waiver and laches. They are as follows:
Finding No. 8. That defendants failed to take any affirmative steps to declare the contract forfeited or to foreclose or [882]*882to otherwise terminate or cancel that contract for more than two years after the date of the last payment.
Finding No. 19. That defendants failed to take action to minimize their damages and the Court does not believe all the testimony supporting the proposition that the fair rental value of the land during plaintiffs’ possession amounted to $12,000.
Finding No. 20. That while plaintiffs breached their side of the contract defendants at least tacitly consented to such breaches, went along with plaintiffs’ delays in payments and failure to pay taxes and assessments and cannot now be heard to complain of plaintiffs and take advantage of a default they allowed to continue for such a long time.
Issue III. Findings of fact No. 22 and conclusion of law No. 5.
Both finding No. 22 and conclusion No. 5 found that in view of the disposition of the case the issue of whether plaintiffs committed waste was moot, and if not moot, the defendants had not carried their burden of proof.
Issue IV. Conclusion of law No. 6 is as follows:
That defendants are not entitled to attorneys fees because, although plaintiffs were in default, they were required to bring suit on the contract to obtain delivery of the deed.

DISCUSSION AND DECISION

Issue I. Skendzel v. Marshall

At the onset we find that the trial court’s finding No. 17 is supported by the evidence. As of October 8, 1978, the date of the last payment, our calculation reveals that $3,543.85 was applied to principal. Such amount is within the broad connotation of the term “approximately” when the trial court found that approximately $4,000 had been applied to principal. In finding No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McLemore v. McLemore
827 N.E.2d 1135 (Indiana Court of Appeals, 2005)
Parker v. Camp
656 N.E.2d 882 (Indiana Court of Appeals, 1995)
S.B.D., Inc. v. Sai Mahen, Inc.
560 N.E.2d 86 (Indiana Court of Appeals, 1990)
In Re Kerns
111 B.R. 777 (S.D. Indiana, 1990)
Oles v. Plummer
444 N.E.2d 879 (Indiana Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
444 N.E.2d 879, 1983 Ind. App. LEXIS 2562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oles-v-plummer-indctapp-1983.