OLD TOWN UTILITY & TECHNOLOGY PARK LLC v. CONSOLIDATED EDISON SOLUTIONS INC

District Court, D. Maine·Decided December 30, 2019·No. 2:19-cv-00029·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MAINE

OLD TOWN UTILITY & ) TECHNOLOGY PARK, LLC, et al., ) ) Plaintiffs, ) ) v. ) 2:19-cv-00029-JDL ) CONSOLIDATED EDISON, ) SOLUTIONS, INC., et al., ) ) Defendants. )

ORDER ON PLAINTIFFS’ MOTIONS TO REMAND AND TO FILE AMENDED COMPLAINTS

The Plaintiffs’ complaint asserts a variety of claims arising out of their allegedly wrongful exclusion from business opportunities associated with a long-term energy supply contract with the University of Maine System. The Plaintiffs have moved to remand the case to state court (ECF No. 45), and have filed two successive motions for leave to amend their complaint (ECF Nos. 78, 91). Because the resolution of these motions turns largely on this case’s procedural history, I address that history in some detail. I. RELEVANT PROCEDURAL HISTORY This action was removed from the Maine Superior Court to this Court in January 2019. Federal jurisdiction was premised on the presence of a federal question, namely two counts in the 127-page complaint alleging violations of the Racketeer Influenced and Corrupt Organization Act (“RICO”), with supplemental federal jurisdiction over the 12 state-law claims. See 28 U.S.C.A. §§ 1331, 1367 (West 2019). In February, I granted the parties’ Joint Proposed Briefing Schedule, which required the Defendants to file their motions to dismiss at the end of the month and the Plaintiffs to file their responses in opposition by April 15. The Plaintiffs also filed

a Motion to Remand to State Court, asserting that the case should be remanded primarily on abstention grounds. On April 8, after the Defendants filed their motions to dismiss, and one week before the Plaintiffs’ responses were due, the Plaintiffs filed a Motion for Leave to File First Amended Complaint (ECF No. 54) but failed to submit a draft of the proposed amended complaint. The next day, Magistrate Judge John H. Rich III

ordered the Plaintiffs to file the proposed First Amended Complaint within seven days, explaining that it was needed “to provide the defendants with a fair opportunity to respond to the plaintiffs’ motion” and “to provide the court with a meaningful opportunity to adjudicate the merits of the plaintiffs’ motion.” ECF No. 55. The following day, on April 10, the Plaintiffs moved to amend Magistrate Judge Rich’s scheduling order to extend the period for the filing of the proposed First Amended Complaint from April 15, 2019 to May 3, 2019. The motion asserted that the

Plaintiffs’ attorney was “leaving on an international family vacation the morning of Saturday, April 13, 2019” without indicating his scheduled return date. ECF No. 56 at 1. The motion further asserted that the Plaintiffs’ attorney had to prepare the Plaintiffs’ response to the Defendants’ motions to dismiss due April 15, in addition to performing work required on other cases. On April 12, 2019, the Court denied the Plaintiffs’ Motion to Amend the Procedural Order, noting that the Plaintiffs had not made a “particularized showing” as to the need for an extension beyond “a busy April 12 and a vacation starting April 13 prior to multiple April 15 deadlines.” ECF No. 59. In addition, the Order noted that the motion failed to explain why the Plaintiffs

“waited more than five weeks after the filing of the defendants’ motions to dismiss and just one week before the deadline for their responses to file their motion to amend, without the proposed amended complaint.” Id. (emphasis in original). On April 16, 2019, one day after the Court’s deadline for the Plaintiffs to file the proposed First Amended Complaint, the Plaintiffs filed a notice with the Court “voluntarily withdraw[ing] their Motion for Leave to Amend, without prejudice to or waiver of

their right to file such a motion at a later time.” ECF No. 63. On May 28, 2019, the Court scheduled a hearing to be held on the motions to dismiss and the motion to remand for June 18. Nearly two weeks later, Plaintiffs filed a motion to continue the hearing, which stated that their attorney had a “long- scheduled family vacation” out of state. ECF. No. 73. The Defendants opposed the motion, arguing that the Plaintiffs’ counsel delayed in alerting the Court to his vacation and that the Plaintiffs’ counsel had previously “attempt[ed] to alter settled

schedules with untimely assertions of vacation.” ECF No. 74 at 1. In the Plaintiffs’ reply, counsel asserted that he “misread his calendar when the hearing was originally scheduled, but immediately notified the Court as soon as he saw the conflict.” ECF No. 75 at 1. The Court granted the continuance on June 11, 2019, setting the hearing for the following month. On June 13, 2019, the Plaintiffs filed a second Motion for Leave to File First Amended Complaint, this time attaching a 99-page amended complaint with exhibits. A hearing on that motion, the motion to remand, and the Defendants’ motions to

dismiss was held on July 18, 2019. At the hearing, the Plaintiffs’ attorney offered the following explanation as to why, when the Plaintiffs filed their motion to continue the June hearing, he had not alerted the Defendants or the Court that the Plaintiffs would again seek to amend their complaint: I didn’t deem it pertinent to the request to continue frankly. The sole reason I was seeking continuance was to go on vacation with my family, a long-scheduled vacation. I noted that I had misread my calendar in my motion and apologized for that inadvertent mistake; but as stated in the motion, as this Court is well aware, that there isn’t necessarily even a need to file a motion for leave to amend before motions to dismiss are heard. ECF No. 84 at 37. On September 30, 2019, I issued my decision on the Defendant’s motions to dismiss, granting them in part and denying them in part. See ECF No. 86. Pertinent to the issue of remand, the order dismissed the complaint’s two RICO counts, which were the sole basis for the Court’s federal question subject-matter jurisdiction. Id. at 15. In light of that decision, the Court scheduled a hearing for November 4, 2019, on the Plaintiffs’ motion to remand and motion for leave to file a First Amended Complaint. On the morning of the hearing, the Plaintiffs filed their Motion for Leave to File Second Amended Complaint, attaching a proposed 112-page complaint and exhibits.1

1 I indicated at the hearing that the Defendants should not file any opposition to the motion pending my issuance of this Order. II. MOTIONS FOR LEAVE TO AMEND In some circumstances, a party may amend its pleading as a matter of course. See Fed. R. Civ. P. 15(a)(1). Otherwise, “a party may amend its pleading only with the opposing party’s written consent or the court’s leave.” Fed. R. Civ. P. 15(a)(2).

“The court should freely give leave when justice so requires.” Id. “[T]he ‘spirit of the rule’ dictates a preference for decisions ‘on the merits, not because of missteps by counsel in pleading.’” J.S. McCarthy, Co. v. Brausse Diecutting & Converting Equip., Inc., 226 F.R.D. 14, 17 (D. Me. 2005) (quoting Allendale Mut. Ins. Co. v. Rutherford, 178 F.R.D. 1, 3 (D. Me. 1998)); see also 6 Charles Wright & Arthur R. Miller, Federal Practice and Procedure § 1474 (3d ed. 2019). But Rule 15(a)(2) “does not mean . . . that a trial court must mindlessly grant every request for leave to amend.” Aponte-

Torres v. Univ. of P.R., 445 F.3d 50, 58 (1st Cir. 2006). “Rather, a district court may deny leave to amend when the request is characterized by ‘undue delay, bad faith, futility, [or] the absence of due diligence on the movant’s part.’” Nikitine v. Wilmington Tr. Co., 715 F.3d 388

Free access — add to your briefcase to read the full text and ask questions with AI