OKLAHOMA GAS AND ELECTRIC CO. v. STATE ex rel. OKLAHOMA CORP. COMMISSION

2025 OK 15
CourtSupreme Court of Oklahoma
DecidedMarch 4, 2025
Docket118857
StatusPublished
Cited by1 cases

This text of 2025 OK 15 (OKLAHOMA GAS AND ELECTRIC CO. v. STATE ex rel. OKLAHOMA CORP. COMMISSION) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
OKLAHOMA GAS AND ELECTRIC CO. v. STATE ex rel. OKLAHOMA CORP. COMMISSION, 2025 OK 15 (Okla. 2025).

Opinion

OKLAHOMA GAS AND ELECTRIC CO. v. STATE ex rel. OKLAHOMA CORP. COMMISSION
2025 OK 15
Case Number: 118857
Decided: 03/04/2025
THE SUPREME COURT OF THE STATE OF OKLAHOMA


Cite as: 2025 OK 15, __ P.3d __

NOTICE: THIS OPINION HAS NOT BEEN RELEASED FOR PUBLICATION. UNTIL RELEASED, IT IS SUBJECT TO REVISION OR WITHDRAWAL.


OKLAHOMA GAS AND ELECTRIC COMPANY, Appellant,
v.
STATE OF OKLAHOMA EX REL. OKLAHOMA CORPORATION COMMISSION, and PEOPLE'S ELECTRIC COOPERATIVE, Appellees,
and
OKLAHOMA ASSOCIATION OF ELECTRIC COOPERATIVES, Intervenor.

APPEAL FROM OKLAHOMA CORPORATION COMMISSION,
CAUSE NO. PUD 201900026, ORDER NO. 711782

0 In the spring of 2018, People's Electric Cooperative, Inc., (People's) and Oklahoma Gas and Electric Company (OG&E) submitted competing bids to provide retail electric service to the Tall Oak Woodford Cryo Plant (Tall Oak or Plant) in Coal County, Oklahoma. The Plant is located in the certified territory of People's, which has exclusive rights to provide electricity to customers in the area pursuant to the Retail Electric Supplier Certified Territory Act (RESCTA). OG&E's successful proposal relied on the Large Load exception to RESCTA, which permits a supplier "extending its service" into another supplier's certified territory for qualifying large-load customers. To provide service to the Plant, OG&E did not extend its own retail distribution lines, but tapped into third-party transmission facilities. Upon People's application, the Oklahoma Corporation Commission enjoined OG&E from serving the Plant, finding that OG&E was not "extending its service" in a manner authorized by RESCTA. We retained OG&E's appeal. We hold that Article 9, Section 20 of the Oklahoma Constitution requires a limited review of the Commission's order, and we affirm the Commission's determination that a retail electric supplier may not use third-party transmission lines to extend its service into another supplier's certified territory under the Large Load exception of RESCTA.

AFFIRMED

Clyde A. Muchmore and Melanie Wilson Rughani, Crowe & Dunlevy, PC, Oklahoma City, Oklahoma, for Appellant Oklahoma Gas and Electric Company.

William L. Humes, Oklahoma Gas and Electric Company, Oklahoma City, Oklahoma, for Appellant Oklahoma Gas and Electric Company.

Patricia L. Franz and Daniel P. Boyle, Oklahoma Corporation Commission, Oklahoma City, Oklahoma, for Appellee Oklahoma Corporation Commission.

Pete G. Serrata III, Derryberry & Naifeh, LLP, Oklahoma City, Oklahoma, for Appellee People's Electric Cooperative, Inc.

Adam J. Singer and J. Eric Turner, Derryberry & Naifeh, LLP, Oklahoma City, Oklahoma, for Oklahoma Association of Electric Cooperatives.

OPINION

DARBY, J.

¶1 This case involves an order of the Oklahoma Corporation Commission (Commission) that enjoined Oklahoma Gas & Electric Company (OG&E) from providing retail electric service to a rural customer. The pivotal question before us is whether the Corporation Commission's decision interpreting the "Large Load" exception to the Retail Electric Supplier Certified Territory Act (RESCTA or the Act), 17 O.S. 2011, § 158.25et seq. is sustained by law and substantial evidence. We answer this question in the affirmative. Also at issue is what appellate standard of review does the Oklahoma Constitution demand. Article 9, Section 20 of the Oklahoma Constitution requires this Court's review extend no further than to determine whether the Corporation Commission has regularly pursued its authority, and whether the Commission's findings of fact and conclusions of law are sustained by the law and substantial evidence. We uphold the Commission's determination which restricted and enjoined OG&E from using third-party transmission lines to extend its service under the "Large Load" exception of the Act.

BACKGROUND AND PROCEDURAL HISTORY

A. The People's Case

¶2 The present case concerns People's Electric Cooperative, Inc., (People's) and OG&E competing to provide retail electric service to the Tall Oak Woodford Cryo Plant (Tall Oak or Plant) in Coal County, Oklahoma. The pertinent facts are not disputed and were stipulated by the parties in their filings with the Commission. Stipulated Facts, Oct. 18, 2019; Rec. at 144.

¶3 For purposes of RESCTA, the Plant is located in an unincorporated area within People's certified territory. Another supplier is not permitted to provide retail electric service to customers in People's certified territory unless an exception under RESCTA is applicable. 17 O.S. 2011, § 158.2517 O.S. 2011, § 158.25

¶4 In the spring of 2018, both People's and OG&E submitted proposals to provide retail electric service to the Plant. Tall Oak selected OG&E, and a contract for service was executed on June 28, 2018. At the time, OG&E did not have any retail distribution lines

¶5 To provide service to the Plant, People's would have simply tapped into its existing distribution line which runs a short distance of approximately 0.9 miles south of the primary meter location provided by OG&E for the Plant, at a total minimal project cost of approximately $193,500. To serve the Plant with distribution facilities extended from its own certified territory, OG&E would have needed to construct approximately 25 miles of distribution facilities along roadways to reach the Plant.

¶6 OG&E began engineering work on the design of the project and commenced construction on December 10, 2018. OG&E completed construction of its facilities on April 28, 2019, and thereafter began providing retail electric service to the Plant. Construction on the Plant was also completed in April of 2019, and OG&E is currently furnishing retail electric service to the Plant.

¶7 On April 19, 2019, only nine (9) days prior to OG&E completing construction of its facility, People's filed an Application with the Commission seeking an order enjoining and restraining OG&E from serving, furnishing, making available, rendering, or extending retail electric service to the Plant. People's asserted that by utilizing the third-party WFEC transmission facilities, OG&E was not extending its retail service as required by RESCTA. On June 20, 2019, the Oklahoma Association of Electric Cooperatives (OAEC) filed its entry of appearance and intervention in the lower case and has also filed an entry of appearance and brief in this appeal.

¶8 The case proceeded to a hearing on the merits before the Administrative Law Judge (ALJ) on January 23, 2020. The ALJ initially concluded that the Act did not prohibit OG&E from serving the Plant by connection with a third-party transmission line. But, the ALJ further acknowledged that the Commission had recently issued its order in CKenergy 1 enjoining OG&E from providing retail electric service under similar circumstances. Based upon the Commission's order in CKenergy 1, the ALJ ultimately recommended that OG&E was not lawfully extending service under the Large Load exception, and that People's request for injunctive relief should be granted. The Commission followed the ALJ's recommendation, and its final order dated May 26, 2020, states in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2025 OK 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-gas-and-electric-co-v-state-ex-rel-oklahoma-corp-commission-okla-2025.