Ohio Valley Contractors, Inc. v. Board of Education

391 S.E.2d 891, 182 W. Va. 741, 1990 W. Va. LEXIS 37
CourtWest Virginia Supreme Court
DecidedMarch 29, 1990
Docket19044
StatusPublished
Cited by5 cases

This text of 391 S.E.2d 891 (Ohio Valley Contractors, Inc. v. Board of Education) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Valley Contractors, Inc. v. Board of Education, 391 S.E.2d 891, 182 W. Va. 741, 1990 W. Va. LEXIS 37 (W. Va. 1990).

Opinion

PER CURIAM:

This is an appeal by Ohio Valley Contractors, Inc. from a summary judgment order entered by the Circuit Court of Wetzel County in a contract case. The principal issue in the case below was whether the Board of Education of Wetzel County was liable to Ohio Valley for some excavation they performed. The circuit court concluded that there was “no genuine issue as to any material fact” and awarded summary judgment and costs to the Board of Education. On appeal, Ohio Valley claims that there are questions of material fact: namely, (1) what was the reason for excavating the site to bedrock; (2) did the architect direct Ohio Valley to perform the additional excavation; and (3) did the Board of Education, either by contract or subsequent agreement, authorize the additional excavation.

In 1976, the Board of Education, as part of construction of a new elementary school, invited bids for site development and preparation work. Ohio Valley’s bid of $140,000 was accepted and the Board of Education and Ohio Valley entered into an agreement dated October 4, 1976 (hereinafter, the contract). Under the contract the entire building area was to be excavated to an elevation of 1002.0' and filled with approximately six feet of appropriate material. To reach the specified elevation an excavation of six feet was required. However, an additional six feet of excavation was done. Ohio Valley sought payment of $98,674.15 over the bid price for the additional excavation and back fill. The Board of Education refused. There is no dispute concerning the quality of the work. However, the Board of Education, by counterclaim, sought $3,425.00 ($25 per day) in liquidated damages for Ohio Valley’s failure to complete timely the contract work. Both parties cite different sections of the contract as justification for their respective positions concerning who should bear the cost of the additional work. 1

Ohio Valley argues that the contract gave the architect, Joseph H. Baker & Associates, authority to order excavation to a lower level without any additional requirement of notice to or approval by the Board *743 of Education. The contract, Division 2, Section 2A, subsection 5 d) 1) provides:

Entire building area to be excavated to contract elevation of 1002.0'. Bottom of excavation shall extend beyond (outside of) exterior building lines eighteen feet (18'). If excavation to this dept results in bottom of excavation being in unsuitable layer, architect may direct that excavation be extended to a lower elevation. Compensation for such extension will be computed from unit price quoted for added excavation.

According to a letter dated January 18, 1977 from Ohio Valley to the architect, Ohio Valley was directed on October 7, 1976 by Mr. Swank of the architect’s firm to excavate the area to bedrock, because of poor subsoil conditions. Ohio Valley argues that because the architect directed the additional excavation and the contract specifically granted that authority to the architect, Ohio Valley should be paid for the additional work. In addition, Ohio Valley notes that the Board of Education was informed of the architect’s decision and allowed the excavation to continue.

The Board of Education argues that Ohio Valley’s bid application acknowledged familiarity with the site and soil conditions. The Board of Education points out that the contract in the General Conditions section requires that all changes in work or contract amount be made by a written change order. 2 The Board of Education claims there was no change order for the additional work. The contract makes the architect the interpreter of requirements of the contract and limits the authority of the architect to make changes that require additional payment by the owner. 3 Finally the Board of Education claims that Ohio Valley elected, at its own option and without additional cost to the Board of Education, to perform the additional excavation work as an alternative to dewatering the site under Division 2, Section 2A, subsection 5 d) 2) of the contract. That section provides:

Excavation of soft subsoils will extend below ground water level (see boring logs). The entire area which is to be excavated and filled must be dewatered by any method elected by contractor. It must be made water-free and maintained so until controlled fill is completed and accepted. As alternative to dewatering, contractor may excavate material underwater to bedrock, and replace with large rock fragments, such as broken sandstone, to one foot above the ground water line by end dumping. Above this level the fill shall consist of material from site, properly mixed, dried and compacted as specified. If contractor elects this alternative, cost of same shall be included in the base bid sum.

In response, Ohio Valley maintains that it did not elect to perform the additional excavation as an alternative to dewatering, but was directed to perform the additional excavation by the architect — excavation covered by a specific contract provision giving the architect authority independent of the General Conditions section of the contract, to order additional excavation. Ohio *744 Valley points to a change order dated March 4, 1977 indicating additional charges for the lower excavation. 4 We note that according to correspondence dated December 6, 1976, January 7, 1977 and January 18, 1977, the Board of Education was advised immediately of the additional work. The architect by letter dated January 7, 1977 acknowledges that they conferred with Ohio Valley concerning the additional excavation but believed “it was determined that ... [Ohio Valley would] employ ‘the alternative method’ ” rather than dewater-ing.

I

On appeal the issue is whether the trial court erred in holding there was “no genuine issue as to any material fact.” We noted that the parties cite different sections of the contract to justify their positions concerning financially responsible for the additional excavation.

Although the contract, in general, limits the architect’s authority, it also seems to enlarge the architect’s authority to authorize additional excavation because of poor soil conditions. Taken as a whole the contract is ambiguous concerning the authorization of the architect to authorize additional excavation and that ambiguity will permit the use of parol evidence to explain the contract terms and to determine the intention of the parties. Glenmark Associates v. Americare of W. Va., 179 W.Va. 632, 371 S.E.2d 353 (1988); Holiday Plaza, Inc. v. First Federal Sav. and Loan Ass’n of Clarksburg, 168 W. Va. 356, 285 S.E.2d 131 (1981); Syllabus Point 4, Watson v. Buckhannon River Coal Co., 95 W. Va. 164, 120 S.E. 390 (1923).

“ ‘Where a contract is ambiguous then issues of fact arise and summary judgment is ordinarily not proper.’ Syl. Pt. 2, Lee Enterprises, Inc. v. Twentieth Century-Fox Film Corp., 172 W.Va.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frederick Management Co. v. City National Bank
723 S.E.2d 277 (West Virginia Supreme Court, 2010)
Jochum v. Waste Management of West Virginia, Inc.
680 S.E.2d 59 (West Virginia Supreme Court, 2009)
Laramie County School District No. One ex rel. Brown v. Muir
808 P.2d 797 (Wyoming Supreme Court, 1991)
LARAMIE COUNTY SCH. DIST. 1 v. Muir
808 P.2d 797 (Wyoming Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
391 S.E.2d 891, 182 W. Va. 741, 1990 W. Va. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-valley-contractors-inc-v-board-of-education-wva-1990.