Ohio v. Nuclear Regulatory Commission

814 F.2d 258, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 17, 1987
DocketNos. 86-4019, 86-4038 and 86-4037
StatusPublished
Cited by1 cases

This text of 814 F.2d 258 (Ohio v. Nuclear Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio v. Nuclear Regulatory Commission, 814 F.2d 258, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20 (6th Cir. 1987).

Opinions

RYAN, Circuit Judge.

Petitioners seek to overturn three orders of the Nuclear Regulatory Commission (the NRC):

1. Petitioner State of Ohio appeals an order of the NRC denying leave to intervene in licensing proceedings pertaining to the Perry Nuclear Power Plant (the plant);

2. Petitioner Ohio Citizens for Responsible Energy, Inc. (OCRE) appeals an order of the NRC denying its motion to reopen the record in the plant licensing proceedings; and

3. Both petitioners appeal the NRC’s order authorizing the plant’s full-power operating license.

The issue is whether the NRC reasonably exercised its discretion in making these determinations. We hold that it did, and affirm all three orders.

I

In 1980, intervenor Cleveland Electric Illuminating Company (CEI) and other public utilities applied to the NRC for a license to operate the Perry Nuclear Power Plant on the shore of Lake Erie in Northern Ohio. The NRC granted party status to OCRE and other interested parties in 1981. The State of Ohio did not seek to participate at that time.

Hearings were held pursuant to the Atomic Energy Act, 42 U.S.C. § 2239(a) (1973), in 1983 and 1985. No party to the proceedings raised the issue of the plant’s capacity to withstand earthquakes. The adequacy of emergency planning was challenged by Sunflower Alliance, an intervenor in the proceedings, and was ultimately approved by the NRC. The record was closed on May 3, 1985.

On January 31, 1986, an earthquake of magnitude 5.0 on the Richter scale occurred approximately ten miles away from the plant. On February 3, 1986, OCRF filed a motion to reopen the record to consider the capacity of the plant’s structures to resist seismic activity of this magnitude. In support of its motion, OCRE submitted a newspaper article reporting that vibratory ground motion at the plant during the earthquake had exceeded the peak acceleration for which the plant had been designed.

The NRC staff studied the available data and determined that, while the earthquake was severe and was different in some respects from the archetype of earthquake motion used in designing the plant structures, the high frequency energy levels that had exceeded the “design spectrum” for ground motion did not raise a serious safety concern. The plant had been designed to withstand earthquakes with magnitudes of 5.3 ± 0.5 because the most severe earthquake in the pertinent geographical zone, the 1937 Anna, Ohio, earthquake, had an estimated magnitude of 5.0-5.3.

The appeal panel to which OCRE’s contentions were submitted, recognizing the highly technical nature of the issue, scheduled an exploratory hearing in order to fully consider OCRE’s claims. The NRC, however, determined that such a hearing [261]*261was not appropriate and, because OCRE had failed to support its motion with evidence sufficient to merit reopening the record, ordered that the motion be denied. OCRE has appealed this denial.

The January, 1986, earthquake also stimulated new concerns on the part of the Governor of Ohio. These concerns were heightened by the April, 1986, nuclear accident at Chernobyl, in the Soviet Union, and eventually focused upon the adequacy of the emergency preparedness plans for Ohio’s commercial nuclear reactors. On August 15, 1986, the Governor appointed a cabinet-level task force to review the adequacy of the evacuation plan which had previously been prepared by Ohio authorities with a view to the eventual full-power operation of the plant. On the same day, the Governor informed the NRC that he was withdrawing his support for the plan. He requested that the NRC delay its vote on full-power licensing until after the task force report was complete. The task force was given a due date of December 31, 1986. We have not been advised at this writing whether the report has been completed or, if completed, released.

While maintaining informal communications with the NRC about its concerns and the progress of the task force’s investigation, Ohio also sought formal intervention in the proceedings on September 5,1986, as an “interested state” under 10 C.F.R. § 2.715 (1986). On October 29, Ohio submitted preliminary findings of the task force to the NRC, requesting that full-power licensing be delayed until the report was completed and the emergency plan could be revised accordingly. On October 30, the NRC denied Ohio’s motion to intervene. Ohio has appealed this denial.

Meanwhile, the NRC’s final vote on the plant’s full-power license, originally scheduled for September 4, was stayed by this court at the instance of OCRE, which contended that it had a right to appeal the denial of its motion to reopen the record prior to that vote. On October 14, this court rejected OCRE’s petition for review on the ground that the denial was not a final agency order. Ohio Citizens for Responsible Energy, Inc. v. NRC, 803 F.2d 258 (6th Cir.1986). Accordingly, the stay was lifted.

On November 7, as the NRC prepared to conduct the vote on full-power licensing, Ohio petitioned this court to review the NRC’s denial of Ohio’s motion to intervene and also sought an emergency stay of the vote pending review. The vote proceeded, and the license was granted. Ohio and OCRE both sought review in this court of the NRC’s final order granting the full-power operating license.

Although the license was issued on November 13, 1986, this court immediately ordered that implementation of full-power operation be stayed pending our review of these appeals. The plant thus continued operating at 5% capacity, as it had before the license was issued, rather than beginning the gradual escalation to 100% capacity authorized by the license.

On November 14, we consolidated and expedited the appeals of Ohio and OCRE. Oral argument was heard on December 3. On December 12, 1986, the five intervenor utilities moved the court to lift the stay, claiming that the “costs of delaying plant operations are accumulating at approximately $2.2 million per day or more than $40 million to date.” The motion was opposed by the State of Ohio. We lifted the stay on December 23, 1986, Judge Jones dissenting. An application to the United States Supreme Court by OCRE to stay the mandate of our order lifting the stay was denied on December 31, 1986, in an opinion of Justice Scalia.

II

OCRE contends that the NRC’s refusal to reopen the record in response to its request following the January, 1986, earthquake illustrates two chronic bureaucratic evils: first, the agency’s inclination to shut the public out of the decision-making process, confident in the sufficiency of its own knowledge and expertise; and second, the agency’s impatience with the pace of the democratic decision-making process im[262]*262posed upon it by statute, which inclines the NRC to dispense with any procedure, however well-founded, that threatens delay.

In this case, these contentions are without merit. The agency proceedings in this case do not suggest an intolerance for public participation on the part of the NRC. The statutory scheme requires hearings to be held only upon those issues interested parties raise before the NRC in a timely manner. In the absence of a request, no hearings need be held at all. 42 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
814 F.2d 258, 17 Envtl. L. Rep. (Envtl. Law Inst.) 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-v-nuclear-regulatory-commission-ca6-1987.