Ohio State Dep., Adm. v. moody/nolan, Unpublished Decision (12-12-2000)

CourtOhio Court of Appeals
DecidedDecember 12, 2000
DocketNo. 00AP-336, (REGULAR CALENDAR)
StatusUnpublished

This text of Ohio State Dep., Adm. v. moody/nolan, Unpublished Decision (12-12-2000) (Ohio State Dep., Adm. v. moody/nolan, Unpublished Decision (12-12-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio State Dep., Adm. v. moody/nolan, Unpublished Decision (12-12-2000), (Ohio Ct. App. 2000).

Opinion

DECISION
The Ohio Department of Administrative Services ("ODAS"), plaintiff-appellant, by and through its Director C. Scott Johnson, appeals a judgment of the Franklin County Court of Common Pleas denying its motion to stay its pending arbitration with Moody/Nolan Ltd., Inc. ("Moody") and Spencer Spencer, Inc. ("Spencer"), defendants-appellees.

On December 2, 1987, ODAS entered into a contract with Robert P. Madison, International, Inc. ("Madison"), an architectural firm, for the design of the State of Ohio Computer Center ("SOCC"). Madison served as the associate architect for the construction of SOCC. Madison contracted with Spencer, who was to serve as Madison's on-site field representative for the SOCC project. Madison also contracted with Moody, who was to prepare contract documents and plans relating to the project. The Spencer and Moody consultant agreements with Madison provided for the arbitration of claims between the parties relating to the agreements.

After completion of the SOCC project, several architectural and other problems arose with the SOCC building. As a result, ODAS filed a lawsuit against Madison and various contractors and suppliers involved in the construction project, alleging breach of contract and breach of express and implied warranties ("ODAS I"). Each of the defendants denied liability in ODAS I. Madison filed a third-party claim against Spencer and Moody, asserting that because it had contracted with Spencer and Moody for some of the architectural work, Spencer and Moody were liable to Madison if Madison were found liable to ODAS. Spencer and Moody raised several defenses to the third-party claim, in which they challenged the ability of Madison to raise the claims against them based upon the doctrine of laches and estoppel. Madison, Spencer, and Moody agreed to stay the court's determination of the third-party claims in ODAS I pending the outcome of arbitration, as provided by the contracts between them.

ODAS ultimately settled its claims with Madison and several other defendants in ODAS I. As part of the settlement, Madison assigned to ODAS all of Madison's rights, claims, demands, and causes of action it had with regard to the contract and litigation against Spencer and Moody. These rights also included ODAS's right to arbitrate Madison's third-party claims against Spencer and Moody.

On January 19, 1999, ODAS filed a demand for arbitration against Spencer and Moody with the American Arbitration Association ("arbitrators"). Spencer and Moody raised several defenses to ODAS's claims, including: (1) Madison's damages claims were not assignable to ODAS; (2) ODAS's arbitration claim is barred by the doctrine of laches; (3) the damages sought by ODAS violate the doctrine of economic waste; (4) ODAS is barred from bringing arbitration against Spencer and Moody in the same proceeding; (5) ODAS's claims are barred by the statute of limitations; (6) ODAS failed to join all necessary parties; (7) ODAS is not the real party in interest; and (8) the demand for arbitration constitutes champerty.

The arbitrators requested that the parties submit briefs on the issue of whether the arbitrators had the authority to decide Spencer and Moody's legal defenses. The arbitrators found that they did have such authority.

On November 29, 1999, ODAS filed an action in the Franklin County Court of Common Pleas seeking declaratory relief and requesting that the trial court decide the legal defenses raised by Spencer and Moody. Also on November 29, 1999, ODAS filed a motion to stay, requesting that the trial court stay presentation of the legal defenses to the arbitrators while the declaratory relief action was pending.

On February 23, 2000, the trial court issued an entry overruling ODAS's motion to stay and found that the arbitrators should determine the legal defenses raised by Spencer and Moody. ODAS appeals the trial court's decision, asserting the following assignments of error:

I. The trial court erred when it held that a panel of arbitrators, and not a court of law, should decide the validity of legal defenses raised by a party to the arbitration prior to the institution of the arbitration process itself.

II. The trial court erred when it sua sponte dismissed Plaintiff-Appellant's Complaint for Declaratory Judgment prior to proper review and discussion of the merits.

ODAS argues in its first assignment of error that the trial court erred when it denied its motion to stay arbitration and held that a panel of arbitrators, and not a court of law, should decide the validity of legal defenses raised by a party to the arbitration prior to the institution of the arbitration process. When addressing whether a trial court has properly granted or denied a motion to stay proceedings, the standard of review is an abuse of discretion. Carter Steel Fabricating Co. v. DanisBldg. Constr. Co. (1998), 126 Ohio App.3d 251, 254-255; Harsco Corp. v.Crane Carrier Co. (1997), 122 Ohio App.3d 406, 410. An abuse of discretion is more than an error of judgment but, instead, demonstrates "perversity of will, passion, prejudice, partiality, or moral delinquency," Pons v. Ohio State Med. Bd. (1993), 66 Ohio St.3d 619,621, or an arbitrary, unreasonable, or unconscionable attitude. Schaferv. Schafer (1996), 115 Ohio App.3d 639, 642.

In examining an arbitration clause, a court must be cognizant of the strong presumption in favor of arbitrability, and any doubts should be resolved in favor of coverage under the arbitration clause. Sasaki v.McKinnon (1997), 124 Ohio App.3d 613, 616-617, quoting Didado v. Lamson Sessions Co. (1992), 81 Ohio App.3d 302, 304. Ohio law encourages participation in arbitration over litigation. ABM Farms, Inc. v. Woods (1998), 81 Ohio St.3d 498, 500; Kelm v. Kelm (1993), 68 Ohio St.3d 26. R.C. 2711.01(A) provides that:

A provision in any written contract, except as provided in division (B) of this section, to settle by arbitration a controversy that subsequently arises out of the contract, or out of the refusal to perform the whole or any part of the contract, or any agreement in writing between two or more persons to submit to arbitration any controversy existing between them at the time of the agreement to submit, or arising after the agreement to submit, from a relationship then existing between them or that they simultaneously create, shall be valid, irrevocable, and enforceable, except upon grounds that exist at law or in equity for the revocation of any contract.

In the present case, we must determine whether the arbitration of legal defenses falls within the scope of the arbitration provisions. In PrimaPaint Corp. v. Flood Conklin Mfg. Co. (1967), 388 U.S. 395,87 S.Ct. 1801

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilko v. Swan
346 U.S. 427 (Supreme Court, 1953)
Prima Paint Corp. v. Flood & Conklin Mfg. Co.
388 U.S. 395 (Supreme Court, 1967)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Shearson/American Express Inc. v. McMahon
482 U.S. 220 (Supreme Court, 1987)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Didado v. Lamson & Sessions Co.
610 N.E.2d 1085 (Ohio Court of Appeals, 1992)
Sasaki v. McKinnon
707 N.E.2d 9 (Ohio Court of Appeals, 1997)
Harsco Corp. v. Crane Carrier Co.
701 N.E.2d 1040 (Ohio Court of Appeals, 1997)
Carter Steel & Fabricating Co. v. Danis Building Construction Co.
710 N.E.2d 299 (Ohio Court of Appeals, 1998)
Schafer v. Schafer
685 N.E.2d 1302 (Ohio Court of Appeals, 1996)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Pons v. Ohio State Medical Board
614 N.E.2d 748 (Ohio Supreme Court, 1993)
Kelm v. Kelm
623 N.E.2d 39 (Ohio Supreme Court, 1993)
State ex rel. Seikbert v. Wilkinson
633 N.E.2d 1128 (Ohio Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Ohio State Dep., Adm. v. moody/nolan, Unpublished Decision (12-12-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-state-dep-adm-v-moodynolan-unpublished-decision-12-12-2000-ohioctapp-2000.