Ohio Fabricators, Inc. v. Aster Elements, Inc.

2019 Ohio 3978
CourtOhio Court of Appeals
DecidedSeptember 30, 2019
Docket28934, 28911
StatusPublished

This text of 2019 Ohio 3978 (Ohio Fabricators, Inc. v. Aster Elements, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Fabricators, Inc. v. Aster Elements, Inc., 2019 Ohio 3978 (Ohio Ct. App. 2019).

Opinion

[Cite as Ohio Fabricators, Inc. v. Aster Elements, Inc., 2019-Ohio-3978.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

OHIO FABRICATORS, INC. C.A. No. 28934 28911 Appellant

v. APPEAL FROM JUDGMENT ENTERED IN THE ASTER ELEMENTS, INC., et al. COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO Appellees CASE No. CV-2016-04-1896

DECISION AND JOURNAL ENTRY

Dated: September 30, 2019

TEODOSIO, Presiding Judge.

{¶1} Ohio Fabricators, Inc. (“Ohio Fabricators”) appeals the order of the Summit

County Court of Common Pleas granting summary judgment in favor of Aster Elements, Inc.

(“Aster”) and Travelers Casualty & Surety Company of America (“Travelers”). We reverse and

remand.

I.

{¶2} In October 2013, Ohio Fabricators entered into a subcontract agreement with

Aster for the installation of exterior panels on a construction project for Cincinnati Children’s

Hospital. The hierarchy of contractors began with the general contractor, Messer Construction,

which hired the exterior general contractor, Pioneer Cladding and Glazing (“Pioneer”), which

hired Aster as an exterior subcontractor. Aster subsequently hired Ohio Fabricators. Travelers

issued a payment bond and a performance bond for Aster’s scope of the project, with Pioneer as

the obligee and Aster as the principal. 2

{¶3} In 2016, Ohio Fabricators commenced an action against Aster and Travelers,

alleging multiple claims for breach of contract, detrimental reliance, and unjust enrichment.

Both Aster and Travelers asserted several counterclaims against Ohio Fabricators. In November

2017, upon motions for summary judgment filed by all parties, the trial court granted summary

judgment in favor of Aster and Travelers on all five counts of Ohio Fabricators’ amended

complaint; denied Ohio Fabricators’ motion for summary judgment as to Aster’s amended

counterclaim and as to counts one and two of Travelers’ amended counterclaim; and granted

summary judgment in favor of Ohio Fabricators on the third count of Travelers’ amended

counterclaim.

{¶4} Ohio Fabricators’ now appeals, raising six assignments of error, which we have

reordered for the purposes of our analysis.

II.

{¶5} Appellate review of an award of summary judgment is de novo. Grafton v. Ohio

Edison Co., 77 Ohio St.3d 102, 105 (1996). Summary judgment is appropriate under Civ.R. 56

when: (1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is

entitled to judgment as a matter of law; and (3) viewing the evidence most strongly in favor of

the nonmoving party, reasonable minds can come to but one conclusion and that conclusion is

adverse to the nonmoving party. Temple v. Wean United, Inc., 50 Ohio St.2d 317, 327 (1977),

citing Civ.R. 56(C). A court must view the facts in the light most favorable to the non-moving

party and must resolve any doubt in favor of the non-moving party. Murphy v. Reynoldsburg, 65

Ohio St.3d 356, 358–359 (1992). A trial court does not have the liberty to choose among

reasonable inferences in the context of summary judgment, and all competing inferences and 3

questions of credibility must be resolved in the nonmoving party’s favor. Perez v. Scripps–

Howard Broadcasting Co., 35 Ohio St.3d 215, 218 (1988).

{¶6} The Supreme Court of Ohio has set forth the nature of this burden-shifting

paradigm:

[A] party seeking summary judgment, on the ground that the nonmoving party cannot prove its case, bears the initial burden of informing the trial court of the basis for the motion, and identifying those portions of the record that demonstrate the absence of a genuine issue of material fact on the essential element(s) of the nonmoving party’s claims. The moving party cannot discharge its initial burden under Civ.R. 56 simply by making a conclusory assertion that the nonmoving party has no evidence to prove its case. Rather, the moving party must be able to specifically point to some evidence of the type listed in Civ.R. 56(C) which affirmatively demonstrates that the nonmoving party has no evidence to support the nonmoving party’s claims. If the moving party fails to satisfy its initial burden, the motion for summary judgment must be denied. However, if the moving party has satisfied its initial burden, the nonmoving party then has a reciprocal burden outlined in Civ.R. 56(E) to set forth specific facts showing that there is a genuine issue for trial and, if the nonmovant does not so respond, summary judgment, if appropriate, shall be entered against the nonmoving party.

Dresher v. Burt, 75 Ohio St.3d 280, 293 (1996).

ASSIGNMENT OF ERROR TWO

THE TRIAL COURT ERRED IN FINDING A PAY-IF-PAID CLAUSE APPLIED[.]

{¶7} In its second assignment of error, Ohio Fabricators argues the trial court erred in

finding that a pay-if-paid clause was applicable to the project. We agree.

{¶8} In granting summary judgment on the amended complaint in favor of Aster and

Travelers, the trial court found that because final payment had not been made to Aster, Aster was

under no obligation to pay Ohio Fabricators for any outstanding payments because of the

application of a pay-if-paid provision in the subcontract.

{¶9} Generally, there are two types of contractual provisions that establish the manner

of payment from a general contractor to a subcontractor: pay-when-paid and pay-if-paid. 4

Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp., 140 Ohio St.3d 193, 2014-Ohio-3095, ¶ 10. A

pay-when-paid provision is an unconditional promise to pay the subcontractor that is not

dependent upon the owner’s nonpayment. Id. Alternatively, a pay-if-paid provision is a

conditional promise to pay the subcontractor that is enforceable only if a condition precedent,

such as the payment by the owner to the general contractor, occurs. Id. at ¶ 11. Such a provision

requires the general contractor to pay the subcontractor only if the general contractor is paid by

the owner, therefore transferring the risk of nonpayment to the subcontractor. Id.

{¶10} In finding that a pay-if-paid clause was dispositive of Ohio Fabricators’ claims,

the trial court relied upon Article 8.1.3 as contained in the General Conditions of the

Subcontract, which provides:

It is specifically understood and agreed that payment to the Subcontractor including any retention shall be made only after receipt of payment by Aster Elements, Inc. from the Owner, and such payment by Owner to Aster Elements, Inc. is a condition precedent to Aster Elements, Inc.’s obligation to pay the Subcontractor.

Ohio Fabricators argue that the trial court erred in finding the pay-if-paid clause was applicable

because it improperly interpreted the language of the provision in determining that it applied to

Pioneer’s nonpayment of funds to Aster.

{¶11} “When confronted with an issue of contract interpretation, our role is to give

effect to the intent of the parties. We will examine the contract as a whole and presume that the

intent of the parties is reflected in the language of the contract.” Sunoco, Inc. (R & M) v. Toledo

Edison Co., 129 Ohio St.3d 397, 2011–Ohio–2720, ¶ 37. “In addition, we will look to the plain

and ordinary meaning of the language used in the contract unless another meaning is clearly

apparent from the contents of the agreement. When the language of a written contract is clear, a

court may look no further than the writing itself to find the intent of the parties.” Id. “Only when 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sunoco, Inc. (R & M) v. Toledo Edison Co.
2011 Ohio 2720 (Ohio Supreme Court, 2011)
In Re Dissolution of Marriage of Seders
536 N.E.2d 1190 (Ohio Court of Appeals, 1987)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Boulger v. Evans
377 N.E.2d 753 (Ohio Supreme Court, 1978)
Perez v. Scripps-Howard Broadcasting Co.
520 N.E.2d 198 (Ohio Supreme Court, 1988)
Chef Italiano Corp. v. Kent State Univ.
541 N.E.2d 64 (Ohio Supreme Court, 1989)
Noble v. Colwell
540 N.E.2d 1381 (Ohio Supreme Court, 1989)
Aultman Hospital Ass'n v. Community Mutual Insurance
544 N.E.2d 920 (Ohio Supreme Court, 1989)
Celebrezze v. Netzley
554 N.E.2d 1292 (Ohio Supreme Court, 1990)
Shifrin v. Forest City Enterprises, Inc.
597 N.E.2d 499 (Ohio Supreme Court, 1992)
Murphy v. City of Reynoldsburg
604 N.E.2d 138 (Ohio Supreme Court, 1992)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Graham v. Drydock Coal Co.
667 N.E.2d 949 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 3978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-fabricators-inc-v-aster-elements-inc-ohioctapp-2019.