Ohio Fabricators, Inc. v. Aster Elements, Inc.

2019 Ohio 3978
Ohio Court of Appeals·Decided September 30, 2019·No. 28934, 28911·Published

Opinion

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

OHIO FABRICATORS, INC. C.A. No. 28934 28911

Appellant

v. APPEAL FROM JUDGMENT ENTERED IN THE

ASTER ELEMENTS, INC., et al. COURT OF COMMON PLEAS COUNTY OF SUMMIT, OHIO

Appellees CASE No. CV-2016-04-1896

DECISION AND JOURNAL ENTRY Dated: September 30, 2019

TEODOSIO, Presiding Judge.

{¶1} Ohio Fabricators, Inc. (“Ohio Fabricators”) appeals the order of the Summit County Court of Common Pleas granting summary judgment in favor of Aster Elements, Inc. (“Aster”) and Travelers Casualty & Surety Company of America (“Travelers”). We reverse and remand.

I.

{¶2} In October 2013, Ohio Fabricators entered into a subcontract agreement with Aster for the installation of exterior panels on a construction project for Cincinnati Children’s Hospital. The hierarchy of contractors began with the general contractor, Messer Construction, which hired the exterior general contractor, Pioneer Cladding and Glazing (“Pioneer”), which hired Aster as an exterior subcontractor. Aster subsequently hired Ohio Fabricators. Travelers issued a payment bond and a performance bond for Aster’s scope of the project, with Pioneer as the obligee and Aster as the principal.

{¶3} In 2016, Ohio Fabricators commenced an action against Aster and Travelers, alleging multiple claims for breach of contract, detrimental reliance, and unjust enrichment. Both Aster and Travelers asserted several counterclaims against Ohio Fabricators. In November 2017, upon motions for summary judgment filed by all parties, the trial court granted summary judgment in favor of Aster and Travelers on all five counts of Ohio Fabricators’ amended complaint; denied Ohio Fabricators’ motion for summary judgment as to Aster’s amended counterclaim and as to counts one and two of Travelers’ amended counterclaim; and granted summary judgment in favor of Ohio Fabricators on the third count of Travelers’ amended counterclaim.

{¶4} Ohio Fabricators’ now appeals, raising six assignments of error, which we have reordered for the purposes of our analysis.

II.

{¶5} Appellate review of an award of summary judgment is de novo. Grafton v. Ohio Edison Co., 77 Ohio St.3d 102, 105 (1996). Summary judgment is appropriate under Civ.R. 56 when: (1) no genuine issue as to any material fact remains to be litigated; (2) the moving party is entitled to judgment as a matter of law; and (3) viewing the evidence most strongly in favor of the nonmoving party, reasonable minds can come to but one conclusion and that conclusion is adverse to the nonmoving party. Temple v. Wean United, Inc., 50 Ohio St.2d 317, 327 (1977), citing Civ.R. 56(C). A court must view the facts in the light most favorable to the non-moving party and must resolve any doubt in favor of the non-moving party. Murphy v. Reynoldsburg, 65 Ohio St.3d 356, 358–359 (1992). A trial court does not have the liberty to choose among reasonable inferences in the context of summary judgment, and all competing inferences and

questions of credibility must be resolved in the nonmoving party’s favor. Perez v. Scripps– Howard Broadcasting Co., 35 Ohio St.3d 215, 218 (1988).

{¶6} The Supreme Court of Ohio has set forth the nature of this burden-shifting paradigm:

[A] party seeking summary judgment, on the ground that the nonmoving party cannot prove its case, bears the initial burden of informing the trial court of the basis for the motion, and identifying those portions of the record that demonstrate the absence of a genuine issue of material fact on the essential element(s) of the nonmoving party’s claims. The moving party cannot discharge its initial burden under Civ.R. 56 simply by making a conclusory assertion that the nonmoving party has no evidence to prove its case. Rather, the moving party must be able to specifically point to some evidence of the type listed in Civ.R. 56(C) which affirmatively demonstrates that the nonmoving party has no evidence to support the nonmoving party’s claims. If the moving party fails to satisfy its initial burden, the motion for summary judgment must be denied. However, if the moving party has satisfied its initial burden, the nonmoving party then has a reciprocal burden outlined in Civ.R. 56(E) to set forth specific facts showing that there is a genuine issue for trial and, if the nonmovant does not so respond, summary judgment, if appropriate, shall be entered against the nonmoving party.

Dresher v. Burt, 75 Ohio St.3d 280, 293 (1996).

ASSIGNMENT OF ERROR TWO

THE TRIAL COURT ERRED IN FINDING A PAY-IF-PAID CLAUSE APPLIED[.]

{¶7} In its second assignment of error, Ohio Fabricators argues the trial court erred in finding that a pay-if-paid clause was applicable to the project. We agree.

{¶8} In granting summary judgment on the amended complaint in favor of Aster and Travelers, the trial court found that because final payment had not been made to Aster, Aster was under no obligation to pay Ohio Fabricators for any outstanding payments because of the application of a pay-if-paid provision in the subcontract.

{¶9} Generally, there are two types of contractual provisions that establish the manner of payment from a general contractor to a subcontractor: pay-when-paid and pay-if-paid.

Transtar Elec., Inc. v. A.E.M. Elec. Servs. Corp., 140 Ohio St.3d 193, 2014-Ohio-3095, ¶ 10. A pay-when-paid provision is an unconditional promise to pay the subcontractor that is not dependent upon the owner’s nonpayment. Id. Alternatively, a pay-if-paid provision is a conditional promise to pay the subcontractor that is enforceable only if a condition precedent, such as the payment by the owner to the general contractor, occurs. Id. at ¶ 11. Such a provision requires the general contractor to pay the subcontractor only if the general contractor is paid by the owner, therefore transferring the risk of nonpayment to the subcontractor. Id.

{¶10} In finding that a pay-if-paid clause was dispositive of Ohio Fabricators’ claims, the trial court relied upon Article 8.1.3 as contained in the General Conditions of the Subcontract, which provides:

It is specifically understood and agreed that payment to the Subcontractor including any retention shall be made only after receipt of payment by Aster Elements, Inc. from the Owner, and such payment by Owner to Aster Elements, Inc. is a condition precedent to Aster Elements, Inc.’s obligation to pay the Subcontractor.

Ohio Fabricators argue that the trial court erred in finding the pay-if-paid clause was applicable because it improperly interpreted the language of the provision in determining that it applied to Pioneer’s nonpayment of funds to Aster.

{¶11} “When confronted with an issue of contract interpretation, our role is to give effect to the intent of the parties. We will examine the contract as a whole and presume that the intent of the parties is reflected in the language of the contract.” Sunoco, Inc. (R & M) v. Toledo Edison Co., 129 Ohio St.3d 397, 2011–Ohio–2720, ¶ 37. “In addition, we will look to the plain and ordinary meaning of the language used in the contract unless another meaning is clearly apparent from the contents of the agreement. When the language of a written contract is clear, a court may look no further than the writing itself to find the intent of the parties.” Id. “Only when

the language of a contract is unclear or ambiguous, or when the circumstances surrounding the agreement invest the language of the contract with a special meaning will extrinsic evidence be considered in an effort to give effect to the parties’ intentions.” Shifrin v. Forest City Ents., 64 Ohio St.3d 635 (1992), syllabus. The determination of whether a contract is ambiguous is a question of law that this Court reviews de novo. Salter v. Salter, 9th Dist. Summit No. 26440, 2013–Ohio–559, ¶ 6, citing Hahn v. Hahn, 9th Dist. Medina No. 11CA0064–M, 2012–Ohio– 2001, ¶ 9. See also Denman v. State Farm Ins. Co., 9th Dist. Lorain No. 05CA008744, 2006– Ohio–1308, ¶ 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Ohio Fabricators, Inc. v. Aster Elements, Inc., 2019 Ohio 3978 (Ohio Ct. App. 2019).

2019 Ohio 3978 (Ohio Fabricators, Inc. v. Aster Elements, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sunoco, Inc. (R & M) v. Toledo Edison Co.
2011 Ohio 2720 (Ohio Supreme Court, 2011)
In Re Dissolution of Marriage of Seders
536 N.E.2d 1190 (Ohio Court of Appeals, 1987)
Temple v. Wean United, Inc.
364 N.E.2d 267 (Ohio Supreme Court, 1977)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Boulger v. Evans
377 N.E.2d 753 (Ohio Supreme Court, 1978)
Perez v. Scripps-Howard Broadcasting Co.
520 N.E.2d 198 (Ohio Supreme Court, 1988)
Chef Italiano Corp. v. Kent State Univ.
541 N.E.2d 64 (Ohio Supreme Court, 1989)
Noble v. Colwell
540 N.E.2d 1381 (Ohio Supreme Court, 1989)
Aultman Hospital Ass'n v. Community Mutual Insurance
544 N.E.2d 920 (Ohio Supreme Court, 1989)
Celebrezze v. Netzley
554 N.E.2d 1292 (Ohio Supreme Court, 1990)
Shifrin v. Forest City Enterprises, Inc.
597 N.E.2d 499 (Ohio Supreme Court, 1992)
Murphy v. City of Reynoldsburg
604 N.E.2d 138 (Ohio Supreme Court, 1992)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Graham v. Drydock Coal Co.
667 N.E.2d 949 (Ohio Supreme Court, 1996)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)