Ohio Ex Rel. Brown v. Usepa

460 F. Supp. 248
CourtDistrict Court, S.D. Ohio
DecidedMarch 29, 1978
DocketC-2-76-704, C-2-76-780
StatusPublished
Cited by1 cases

This text of 460 F. Supp. 248 (Ohio Ex Rel. Brown v. Usepa) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Ex Rel. Brown v. Usepa, 460 F. Supp. 248 (S.D. Ohio 1978).

Opinion

460 F.Supp. 248 (1978)

STATE OF OHIO, ex rel. William J. BROWN, Attorney General of Ohio, Plaintiff,
v.
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY et al., Defendants.
William Leslie EVANS et al., Plaintiffs,
v.
Russell E. TRAIN, Administrator, United States Environmental Protection Agency et al., Defendants.

Nos. C-2-76-704, C-2-76-780.

United States District Court, S. D. Ohio, E. D.

March 29, 1978.

*249 David Northrop, Margaret Malone, Asst. Attys. Gen. of Ohio, Columbus, Ohio, for plaintiffs.

*250 James E. Rattan, Asst. U. S. Atty., Columbus, Ohio, for defendants.

OPINION AND ORDER

DUNCAN, District Judge.

The Olentangy Environmental Control Center and Interceptor System (OECC) is a proposed sewage treatment facility to be built in southern Delaware County between State Route 315 and the Olentangy River. Pursuant to the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. § 4321, et seq. the defendants caused an Environmental Impact Statement (EIS) to be prepared and circulated for this project. Thereafter, defendant United States Environmental Protection Agency, through its Regional Administrator, approved the OECC project for federal funding.

The plaintiffs in these consolidated cases allege that the EIS fails to comply with the requirements of NEPA and the regulations promulgated thereunder, and that the approval of the OECC for federal funding is arbitrary, capricious and contrary to law. These cases are before the Court for decision after a consolidated hearing on the plaintiffs' motions for preliminary injunction and trial on the merits pursuant to Fed.R.Civ.P. 65(a)(2). The Court's findings of fact and conclusions of law are set forth hereinbelow as required by Fed.R.Civ.P. 52(a).[1]

Scope of Review

The issues before the Court in this case are limited.

Our review of the adequacy of an EIS and of the merits of a decision reflected therein, while careful, has real limits. On the merits, "[t]he review should be limited to determining whether the agency's decision is arbitrary or capricious." Sierra Club v. Froehlke, 486 F.2d 946, 953 (7th Cir. 1973); and see Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416, 91 S.Ct. 814, 28 L.Ed.2d 136 (1971).

City of Des Plaines v. Metropolitan Sanitary District of Chicago, 552 F.2d 736, 737 (7th Cir. 1977). With respect to the adequacy of the EIS:

The only role for a court is to insure that the agency has taken a "hard look" at environmental consequences; it cannot "interject itself within the area of discretion of the executive as to the choice of the action to be taken." Natural Resources Defense Council v. Morton, 148 U.S.App.D.C. 5, 458 F.2d 827, 838 (1972).

Kleppe v. Sierra Club, 427 U.S. 390, 410 n. 21, 96 S.Ct. 2718, 2730, 49 L.Ed.2d 576 (1976).

Applying these standards, the Court finds that the plaintiffs have failed to meet their burden of proof and that the defendants are therefore entitled to judgment. The Court's specific findings with respect to the plaintiffs' contentions follow.

1. The EIS depicts the chosen alternative with reasonable accuracy. Page i of the EIS indicates that "[s]ub-alternative six, involving a local treatment plant for the Olentangy and Alum Creek basins, and regionalization of the Scioto flow, has been chosen . . ." Figure 3-17 depicts the proposed project with reasonable accuracy even though it shows construction of interceptor sewers further north along the Scioto River than is actually proposed. The proposed action is further described at pages 4-25 and 4-26 of the EIS.

2. Chapter 5 of the EIS describes the commitment of resources which would be involved in the proposed action if it is implemented together with the trade-offs between short-term and long-term environmental impacts. Although specific data is lacking for some factors (e. g. the amount of energy consumption for construction), the EIS contains sufficient information from which a responsible executive can arrive at a reasonably informed decision regarding the environmental benefits and detriments and the resource commitments *251 necessary to implement the project. See, Sierra Club v. Froehlke, 486 F.2d 946, 950 (7th Cir. 1973). Chapter 5 of the EIS is clearly indicative of a "hard look" at resource commitments and environmental trade-offs.

3. The regulations at 40 C.F.R. § 6.304(b) require that the analysis in the EIS "should be detailed enough to show EPA's comparative evaluation of the .. costs ... of the proposed action and each feasible alternative." Dr. Whitlatch testified, and the Court finds, that the EIS contains inadequate data from which a scientific cost-effectiveness analysis can be performed for each of the alternatives discussed. The Court does not believe, however, that the EIS is required to contain a cost-effectiveness analysis including each alternative; it need only "show EPA's comparative evaluation of the ... costs." The Court finds the cost-effectiveness discussion in the EIS adequate to comply with this requirement. At pages i and 3-58 the EIS indicates that sub-alternative six is not the least cost alternative. The EIS gives cost estimates for some force mains and lift stations which show that alternatives requiring such facilities have a higher capital and operation cost. In the comparison of alternatives the Court finds it unnecessary to prepare precise cost data for each alternative; the comparative cost of certain alternatives can be evaluated without resort to dollar figures.

4. The Court finds the discussion of alternatives in the EIS to be adequate to show a reasoned choice of alternatives. Although the alternative sites were not evaluated on each of the nine criteria identified in the EIS, "[t]he discussion of alternatives need not be exhaustive if the impact statement presents sufficient information for a reasoned choice of alternatives." Robinson v. Knebel, 550 F.2d 422, 425 (8th Cir. 1977). The Court finds that the factors which caused the report preparers to favor one alternative over another are sufficiently identified and considered. Chapters 3 and 4 and Appendix E provide an adequate explanation of the alternatives to form a basis for informed decision-making.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davison v. Department of Defense
560 F. Supp. 1019 (S.D. Ohio, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
460 F. Supp. 248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-ex-rel-brown-v-usepa-ohsd-1978.