O'Heron v. American Bridge Co. of New York

177 Ill. App. 405, 1913 Ill. App. LEXIS 1202
CourtAppellate Court of Illinois
DecidedDecember 19, 1912
DocketGen. No. 17,490
StatusPublished
Cited by9 cases

This text of 177 Ill. App. 405 (O'Heron v. American Bridge Co. of New York) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Heron v. American Bridge Co. of New York, 177 Ill. App. 405, 1913 Ill. App. LEXIS 1202 (Ill. Ct. App. 1912).

Opinion

Mr. Justice McSurely

delivered the opinion of the court.

This is an appeal from a judgment rendered against the American Bridge Company of New York, hereinafter called defendant, in an action of assumpsit brought by John J. O’Heron and T. Frank Quilty, co-partners as John J. O’Heron & Company, hereinafter called plaintiff.

Plaintiff’s declaration claimed damages for alleged breaches of a contract, and also claimed under the common counts. In December, 1904, the defendant entered into, a contract with the Louisville & Nashville Railroad Company for the erection of the steel work of a ten-story office building in Louisville, Kentucky. This work was sublet by defendant to plaintiff under a contract dated May 24, 1905, which contract is the foundation of the controversy before us. Under this contract the defendant was to furnish and deliver to the site of the work all of the structural steel required. Plaintiff claims that the actual manner and times of deliveries of this material were so different from those contemplated by the contract as to make it impossible to trace the contract in the course of the work. Hence it is claimed that plaintiff, ignoring the contract price, may recover upon its quantum meruit count for the reasonable value of the services rendered. The fact of delays in the delivery of material is conceded by the defendant, but it is contended that such delays were contemplated and provided for by certain provisions of the contract, which are as follows:

“The contractor agrees:
“To entirely complete work on or before August 10, 1905, except for such extension of time as will be granted in writing by the Company (defendant) (a) because of failure on part of owner to complete necessary foundations in time; (b) because of failure on part of the Company to deliver the fitted steel work as before stated.”
“That the Company shall retain the right to suspend operations under this agreement without becoming liable to him (plaintiff) for any claims for damages or additional compensation but in case of such suspension the Company will grant to him additional time to carry out this agreement equal to the time operations are suspended.”

These terms of the contract are said to provide that failure to deliver at the times provided for in the contract results only in an extension, by so much, of the time for the completion of plaintiff’s work.

There are several considerations which lead us to the . conclusion that this construction does not control: (1) Any extension of the time limit for the completion of plaintiff’s work was to be “in writing,” and no formal extension ‘ ‘ in writing ’ ’ was made. (2) We are inclined to hold that the provision for the extension of time was for the avoidance of a penalty the plaintiff might incur if it did not complete its work on time, and not as a privilege to the defendant to disregard its obligation for deliveries of materials (Nelson v. Pickwick Associated Co., 30 Ill. App. 333). (3) The contract undertook not only to regulate the time but also the order of deliveries of materials. This provision is that the defendant agrees “to ship the finished structural steel required in complete shipments of two floors, with necessary supporting columns each in man-' ner as follows: First shipment June 16th; second shipment June 23rd; third shipment June 29th; fourth shipment July 6th; fifth shipment July 13th.” It is obviously reasonable to provide that shipments of the many pieces of steel should be in some orderly relation to the course of erection of the structure. The construction contended for by the defendant would permit defendant to ship materials in the most extreme, chaotic tangle possible,—a condition which might occupy more of the time of plaintiff in disentangling than would be occupied in the actual work of construction,— and the only recompense to plaintiff for this extra work would be relief from a penalty for failure to complete the work on time. We cannot give assent to this construction of the contract.

The claim of plaintiff was that the defendant so violated its obligation not only with respect to the time but also the order of deliveries of materials, that it was impossible to trace the contract in this regard in the performance of the work. As we shall remand this case for reasons hereinafter indicated, we shall not narrate the testimony upon this point. However, for the guidance of counsel we are inclined to say that if the only question before us concerned the conclusion of the jury on this question of fact, upon the record before us and under proper instructions, we should not feel justified in disturbing the verdict.

It is urged that reversible error was committed by the court in permitting the introduction of certain books of account by plaintiff. We shall not detail the character of these books, but, briefly described, they were books kept by plaintiff’s bookkeeper in Chicago, into which were entered items taken from various and numerous memoranda made by many people; for example, the entry of items of “labor” came from hundreds of “time slips,” each slip signed by a laborer, upon which were the “0. Ks.” of the foremen and superintendents. These time slips were produced in court and tendered, together with the books of account, to counsel for defendant for inspection. No claim is made that the account appearing in the books is incorrect. Under such circumstances the court was justified in following the conclusion reached by the learned author, as stated in Wigmore on Evidence, vol. 2, section 1530: “Where an entry is made by one person in the regular course of business, recording an oral or written report, made to him by one or more other persons in the regular course of business, of a transaction lying in the personal knowledge of the latter, there is no objection to receiving that entry provided the practical inconvenience of producing on the stand the numerous persons thus concerned would in the particular case outweigh the probable utility of doing so.”

It is urged that the court erred in permitting the jury to allow interest to the plaintiff. The court refused the request of the defendant to instruct the jury that interest should not be allowed, and at the instance of the plaintiff gave an instruction touching the allowance of interest, substantially in the language of the statute. The only ground upon which plaintiff could recover interest was that there had been unreasonable and vexatious delay in payment; but there is no evidence in the record of such delay. The amount due plaintiff depended largely upon the construction of the terms of the contract, and upon certain questions of fact and of opinion, upon all of which men might disagree without being unreasonable. Furthermore, this dispute arose from an honest and genuine difference of opinion, and delay in payment arising from such a cause is not unreasonable within the meaning of the statute. “To authorize a recovery for interest the debtor must in some way throw obstacles in the way of collection, by some circumvention, contrivance or management of his own, which induces the court to withhold proceedings against him longer than it would otherwise have done.” Imperial Hotel Co. v. Claflin Co., 175 Ill. 119, 124. Moreover, plaintiff claimed $30,000 from defendant; the jury allowed plaintiff $19,500. Therefore, refusal by defendant to pay plaintiff’s demand could hardly be called unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Dynamics Corp. v. Zion State Bank & Trust Co.
427 N.E.2d 131 (Illinois Supreme Court, 1981)
Haas v. Cravatta
389 N.E.2d 226 (Appellate Court of Illinois, 1979)
J. F. Edwards Construction Co. v. Illinois State Toll Highway Authority
340 N.E.2d 572 (Appellate Court of Illinois, 1975)
Kramlich v. Home Federal Savings & Loan Ass'n
325 N.E.2d 657 (Appellate Court of Illinois, 1974)
Kramlich v. HOME FED. SAV. & LOAN ASS'N
325 N.E.2d 657 (Appellate Court of Illinois, 1974)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
Ladd v. Cochran & McCluer Co.
274 Ill. App. 427 (Appellate Court of Illinois, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
177 Ill. App. 405, 1913 Ill. App. LEXIS 1202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oheron-v-american-bridge-co-of-new-york-illappct-1912.