O'Hehir v. Central New England Railway Co.

152 A.D. 677, 137 N.Y.S. 627, 1912 N.Y. App. Div. LEXIS 8605
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 4, 1912
StatusPublished
Cited by5 cases

This text of 152 A.D. 677 (O'Hehir v. Central New England Railway Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Hehir v. Central New England Railway Co., 152 A.D. 677, 137 N.Y.S. 627, 1912 N.Y. App. Div. LEXIS 8605 (N.Y. Ct. App. 1912).

Opinion

Woodward, J.:

The complaint in this action attempts to set forth eight causes of action growing out of two contracts for the elimination of grade crossings in the State of Connecticut, and the action, being tried before á referee, has resulted in a judgment for the plaintiffs based upon first, third, fourth and eighth causes set forth. The first cause of action is based on the allegations that the plaintiffs are copartners, doing business at Warwick, N. Y.; that the defendant is a corporation organized under the laws of the State of New York, and that on the 17th day of September, 1906, the plaintiffs and defendant entered into a contract in writing for the elimination of a certain grade cross[679]*679ing at West Norfolk in the State of Connecticut; that the plaintiffs should perform said work and furnish materials therefor in accordance therewith and the specifications thereto attached and the plans accompanying said contract at certain unit prices set forth in detail; that the defendant agreed to pay such prices therefor; that the time of performance was subsequently postponed from time to time and that the contract also provided that when such contract should have been completely performed the chief engineer should so certify in writing and give a final estimate of the work done by the contractor and a statement of the amount due and unpaid him therefor, and the defendant should within thirty days thereafter pay the full amount which should be so found due, including the percentages retained on former estimates; that on or before the 21st day of August, 1907, the plaintiffs duly performed all the conditions thereof on their part and fully completed the same, and also performed extra work and furnished extra material therefor as ordered and directed by said defendant under the terms of said contract; that upon completion of said work the plaintiffs requested the defendant to furnish the final estimate, but that said defendant has unreasonably neglected and refused to furnish the same; that the agreed price and value thereof was the sum of $5,672 and that $1,676.11 has been paid thereon and no more, though demand therefor has been made.

The second cause of action realleges the formal matters of copartnership and incorporation and alleges that “between the twenty-first day of August, 1907, and the eleventh day of November, 1907, plaintiffs performed work, labor and services for and furnished materials to the defendant at West Norfolk, Connecticut, at its request of the value of ,$1,669.96,” and that no part thereof has been paid.

This second cause of action is entirely ignored by the learned referee, who treats all of the work and materials as having been furnished under the contract above alleged, although it is apparent from the pleadings and the proofs that the work at West Norfolk was not completed at the time the creditors of the plaintiffs placed attachments upon the plant, tools and work on the 26th day of October, 1907, at which time the plaintiffs [680]*680.abandoned the work, and it was completed'by other contractors. The plaintiffs’ theory of this second cause of action is that the original contract was completed on the twenty-first day of August, as alleged in the pleadings, or on the first day of September, as testified to by one of the plaintiffs (which appears to be the only evidence in support of the allegation of the complaint), and dhat the further work and materials were furnished under a verbal agreement that the cost of labor and materials should be repaid to the plaintiffs, plus ten per cent for superintendence, etc., and this claim having been wholly disregarded, and the plaintiffs having been permitted to recover for all of the work, labor and materials on the basis of the original contract, it seems entirely clear to us that the finding that the contract was completed on the twenty-first day of August, or on the first day of September, is wholly without evidence to support it'. The learned referee found as a fact that “for the excavation and concrete work performed by plaintiffs at West Norfolk during the months of September and October, '1907, they were paid, as in preceding months, for the value of the work then performed as the same was ascertained by computing the quantity of work in cubic yards and paying therefor the respective unit prices named in said written contract.” If the contract was completed at the date mentioned in the complaint, or at the date testified to by the plaintiffs, then the plaintiffs could not, under the bill of particulars, be entitled to have their compensation fixed upon the basis of the contract, but upon the basis of the alleged oral agreement, and the findings of the referee are entirely inconsistent. Either the contract was not completed up to the time of the abandonment of the work on the twenty-sixth day of October, or the plaintiffs were entitled to have their second cause of action sustained, and upon the basis of the verbal contract, and yet the learned referee, finding that the contract was fully performed, we must assume as of the only date as to which there is any evidence of its full performance on the 1st day of September, 1907, finds at the request of the defendant that the plaintiffs were paid for the excavation and concrete work upon this job, completed on the first of September, for the months of September and October of- the same year at the rates fixed by [681]*681the contract. It seems to ns that the finding that the contract was fully, performed (and such finding must be in harmony with the pleadings as modified by the evidence without objection) must relate to the twenty-first day of August or the first of September, and that a finding that the plaintiffs were paid for this same class of work, at the same rates as fixed by the contract, for the months of September and October, negatives the finding that the contract was performed at the time alleged and, we may assume, supported by some evidence. If the contract was not performed at the date fixed by the plaintiffs, and was not substantially completed until the twenty-sixth day of October when the work was concededly suspended, then the findings of the referee are not in harmony with the pleadings or the proofs, and the rule still prevails that “ judgment should be rendered in conformity with the allegations and proofs of the parties, secundum allegata etprobata.” (Wright v. Delafield, 25 N. Y. 266, 268.) Here the plaintiffs, under an allegation that the contract was performed on the twenty-first day of August, have been permitted to recover for work performed subsequent to that time under the terms of the contract alleged to have been fully performed,- while claiming for such work tinder an oral contract upon different terms. We think this is not warranted, and that the learned referee erred in his findings and in his conclusions of law in reference to the first and second causes of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michaud v. Steckino
390 A.2d 524 (Supreme Judicial Court of Maine, 1978)
U. S. F. & G. Co. v. Attala County Drainage Dist. No. 2
146 So. 460 (Mississippi Supreme Court, 1933)
McNeil v. Cobb
186 A.D. 177 (Appellate Division of the Supreme Court of New York, 1919)
Stewart v. Sulger
174 A.D. 838 (Appellate Division of the Supreme Court of New York, 1916)
O'Hehir v. Central New England Railway Co.
138 N.Y.S. 1132 (Appellate Division of the Supreme Court of New York, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
152 A.D. 677, 137 N.Y.S. 627, 1912 N.Y. App. Div. LEXIS 8605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohehir-v-central-new-england-railway-co-nyappdiv-1912.