DANAHER, Senior Circuit Judge:
The appellants
(herein Ogden/ Dwight, a joint venture), sued on an obligation in which Charles Pankow, Inc. (herein Pankow)
a competing contracting company, was principal, and appellee,
Federal Insurance Company (herein Federal) was surety. Ogden/Dwight relying upon Rule 56(c), had sought summary judgment, interlocutory in character, on the issue of liability, or, in the alternative, pointing to Rule 56(d), had moved for an order specifying facts appearing to be without substantial controversy. Federal cross-moved for summary judgment dismissing the complaint. District Judge Tenney concluded that the bond in suit had prescribed a penalty rather than a legally enforceable provision for liquidated damages. Accordingly he ruled as a matter of law that a complete legal defense had been presented, and so Ogden/Dwight’s motion was denied in its entirety. Thereupon Federal’s motion was granted and the complaint was dismissed.
We affirm.
The University of Vermont
in 1971 inaugurated a contest among selected contracting firms who were invited to submit proposals for the design and construction of a residential and educational complex on University property in Vermont. Over the period pertinent to our consideration Mr. Melvin A. Dyson was Chief Financial Officer of the University. His letter in the front of a pre-qualification “Brochure” had notified the prospective contestants that the University ultimately would select a single proposal according to quality and design, with the project cost fixed in the neighborhood of $5,750,000. A “Request” for proposals would be issued on June 21, 1971, only to those who had qualified in all respects. Each Design/Build Team, so-called, was informed further that the posting of an acceptable Proposal Performance Bond was a prerequisite to establishing eligibility for further consideration.
As of June 18, 1971, Pankow as Princi-. pal and Federal as Surety had entered into and forwarded to the University the required Proposal Performance Bond in the penal sum of $20,000 in favor of the University of Vermont as promisee. The obligation submitted by Pankow was expressly subject to the following condition:
Now, Therefore, if the said Principal shall notify the University in writing before July 2, 1971, that they [sic] cannot prepare an adequate proposal or shall submit on or before 2 o’clock p. m., August 23, 1971, a complete Design/Build Proposal, then this obligation shall be void; otherwise the bond will be forfeited unto the University of Vermont as liquidated damages.
Pankow was later to be informed by Mr. Dyson’s letter dated July 7, 1971, that the Pankow firm and two other qualified contestants, Ogden/Dwight and The Carlson Corporation, had been chosen to proceed, and that the University would look forward to receipt of their Design/Build Proposals not later than September 6, 1971 (a date later extended to September 13, 1971).
All three Design/Build Teams submitted their respective proposals on the due date. Pankow had tendered a cost overrun of $392,000. Where the University had contemplated five housing clusters, Pankow had proposed to design and to construct only four. Pankow planned an average of 150 students to each cluster which, according to Mr. Dyson’s affidavit, would have permitted the housing of too few students at the Center. Yet other variances were the subject of controversy, apparently unresolved by exchanges of correspondence and telegraphic communications. Mr. Dyson’s affidavit of record further attested his meeting with the Chairman of the Evaluation Committee, the University’s counsel and three professional architects in whose opinion the Pankow proposal as amended could not be evaluated and was deemed not in compliance with the specifications in the Request. Without our enumeration of yet other aspects of dissatisfaction,
Mr. Dyson as of September 23, 1971, wrote Pankow demanding payment under the bond. Receiving no response, then or thereafter, the University, acting by its board of trustees, on October 7, 1972, assigned to Odgen/ Dwight any claim
the University might have against Pankow and Federal. This action was thereafter instituted by complaint dated December 6, 1972.
I.
Against the background of the foregoing facts, we must discern applicable law in this diversity case
under New York choice of law rules, pursuant to which New York courts would probably look to Vermont law. The briefs of the parties in this court ignored Vermont law entirely. In our own analysis, and since we have found no contrary authority, we will assume that Vermont law does not differ from New York law on the issues before us. Accordingly we have here relied almost completely on general authorities and on decisions construing New York law.
Turning now to the contract in suit,
supra,
there was to be no liability if before July 2, 1971, the University should receive written notice from Pankow that Pankow could not prepare an adequate proposal. However, we also may perceive that Pankow agreed that its bond (with Federal as surety) would be forfeited to the University as “liquidated damages” unless performance was accomplished by the dates the University prescribed.
It seems beyond peradventure that the University desired specifically to know by July 2, 1971, just exactly what Design/Build Teams were to continue in the competition. Additionally, the University had prescribed a time schedule as it sought assurance of being able to evaluate completed Design/Build Proposals from each of the respective contestants.
The performance sought clearly was intended for the benefit of the Uni
versity, and the
promise
of Pankow and Federal ran directly to the University alone.
The University had disavowed in advance any intention to profit from a possible forfeiture, indeed the University envisioned only slight damage if a participant should submit an incomplete proposal.
Assuming a forfeiture, had the University itself instituted action on that bond, Federal would have been entitled to judgment unless the University could have shown that the penal sum of $20,-000 represented a reasonable forecast of just compensation because of Pankow’s alleged failure to submit a complete proposal. ' Under such circumstances, the agreement before us is not enforceable as a contract,
What we have here is an agreement which constitutes a “penalty.”
Perhaps even though the Court had before it a government contract, we may profitably consider the general principles discussed in Priebe & Sons v.
Free access — add to your briefcase to read the full text and ask questions with AI
DANAHER, Senior Circuit Judge:
The appellants
(herein Ogden/ Dwight, a joint venture), sued on an obligation in which Charles Pankow, Inc. (herein Pankow)
a competing contracting company, was principal, and appellee,
Federal Insurance Company (herein Federal) was surety. Ogden/Dwight relying upon Rule 56(c), had sought summary judgment, interlocutory in character, on the issue of liability, or, in the alternative, pointing to Rule 56(d), had moved for an order specifying facts appearing to be without substantial controversy. Federal cross-moved for summary judgment dismissing the complaint. District Judge Tenney concluded that the bond in suit had prescribed a penalty rather than a legally enforceable provision for liquidated damages. Accordingly he ruled as a matter of law that a complete legal defense had been presented, and so Ogden/Dwight’s motion was denied in its entirety. Thereupon Federal’s motion was granted and the complaint was dismissed.
We affirm.
The University of Vermont
in 1971 inaugurated a contest among selected contracting firms who were invited to submit proposals for the design and construction of a residential and educational complex on University property in Vermont. Over the period pertinent to our consideration Mr. Melvin A. Dyson was Chief Financial Officer of the University. His letter in the front of a pre-qualification “Brochure” had notified the prospective contestants that the University ultimately would select a single proposal according to quality and design, with the project cost fixed in the neighborhood of $5,750,000. A “Request” for proposals would be issued on June 21, 1971, only to those who had qualified in all respects. Each Design/Build Team, so-called, was informed further that the posting of an acceptable Proposal Performance Bond was a prerequisite to establishing eligibility for further consideration.
As of June 18, 1971, Pankow as Princi-. pal and Federal as Surety had entered into and forwarded to the University the required Proposal Performance Bond in the penal sum of $20,000 in favor of the University of Vermont as promisee. The obligation submitted by Pankow was expressly subject to the following condition:
Now, Therefore, if the said Principal shall notify the University in writing before July 2, 1971, that they [sic] cannot prepare an adequate proposal or shall submit on or before 2 o’clock p. m., August 23, 1971, a complete Design/Build Proposal, then this obligation shall be void; otherwise the bond will be forfeited unto the University of Vermont as liquidated damages.
Pankow was later to be informed by Mr. Dyson’s letter dated July 7, 1971, that the Pankow firm and two other qualified contestants, Ogden/Dwight and The Carlson Corporation, had been chosen to proceed, and that the University would look forward to receipt of their Design/Build Proposals not later than September 6, 1971 (a date later extended to September 13, 1971).
All three Design/Build Teams submitted their respective proposals on the due date. Pankow had tendered a cost overrun of $392,000. Where the University had contemplated five housing clusters, Pankow had proposed to design and to construct only four. Pankow planned an average of 150 students to each cluster which, according to Mr. Dyson’s affidavit, would have permitted the housing of too few students at the Center. Yet other variances were the subject of controversy, apparently unresolved by exchanges of correspondence and telegraphic communications. Mr. Dyson’s affidavit of record further attested his meeting with the Chairman of the Evaluation Committee, the University’s counsel and three professional architects in whose opinion the Pankow proposal as amended could not be evaluated and was deemed not in compliance with the specifications in the Request. Without our enumeration of yet other aspects of dissatisfaction,
Mr. Dyson as of September 23, 1971, wrote Pankow demanding payment under the bond. Receiving no response, then or thereafter, the University, acting by its board of trustees, on October 7, 1972, assigned to Odgen/ Dwight any claim
the University might have against Pankow and Federal. This action was thereafter instituted by complaint dated December 6, 1972.
I.
Against the background of the foregoing facts, we must discern applicable law in this diversity case
under New York choice of law rules, pursuant to which New York courts would probably look to Vermont law. The briefs of the parties in this court ignored Vermont law entirely. In our own analysis, and since we have found no contrary authority, we will assume that Vermont law does not differ from New York law on the issues before us. Accordingly we have here relied almost completely on general authorities and on decisions construing New York law.
Turning now to the contract in suit,
supra,
there was to be no liability if before July 2, 1971, the University should receive written notice from Pankow that Pankow could not prepare an adequate proposal. However, we also may perceive that Pankow agreed that its bond (with Federal as surety) would be forfeited to the University as “liquidated damages” unless performance was accomplished by the dates the University prescribed.
It seems beyond peradventure that the University desired specifically to know by July 2, 1971, just exactly what Design/Build Teams were to continue in the competition. Additionally, the University had prescribed a time schedule as it sought assurance of being able to evaluate completed Design/Build Proposals from each of the respective contestants.
The performance sought clearly was intended for the benefit of the Uni
versity, and the
promise
of Pankow and Federal ran directly to the University alone.
The University had disavowed in advance any intention to profit from a possible forfeiture, indeed the University envisioned only slight damage if a participant should submit an incomplete proposal.
Assuming a forfeiture, had the University itself instituted action on that bond, Federal would have been entitled to judgment unless the University could have shown that the penal sum of $20,-000 represented a reasonable forecast of just compensation because of Pankow’s alleged failure to submit a complete proposal. ' Under such circumstances, the agreement before us is not enforceable as a contract,
What we have here is an agreement which constitutes a “penalty.”
Perhaps even though the Court had before it a government contract, we may profitably consider the general principles discussed in Priebe & Sons v. United States, 332 U.S. 407, 68 S.Ct. 123, 92 L.Ed. 32 (1947). There Mr. Justice Douglas identified the question of whether a provision for “liquidated damages” should be denied enforcement on the ground that it constitutes a “penalty.” There had been a failure of promised performance by a date certain whereupon “liquidated damages” had been sought.
The opinion speaks of delays by contractors creating no damaging interference with continuance of the procurement program, and then goes on to say:
Under these circumstances this provision for “liquidated damages” could not possibly be a reasonable forecast of just compensation for the damage caused by a breach of contract. It might, as respondent suggests, have an
in terrorem
effect of encouraging prompt preparation for delivery. But the argument is a tacit admission that the provision was included not to make a fair estimate of damages to be suffered
but to serve only as an added spur to performance.
It is well-settled contract law that courts do not give their imprimatur to such arrangements. See Kothe v. R. C. Taylor Trust [280 U.S. 224, 226, 50 S.Ct. 142, 74 L.Ed. 382]; Restatement, Contracts § 339. All provisions for damages, are, of course, deterrents of default. But an exaction of punishment for a breach which could produce no possible damage has long been deemed oppressive and unjust. 332 U.S. at 413, 68
S.Ct. at 126. (Citations omitted.) (Emphasis added.)
It fairly may be observed that there is no suggestion that Ogden/Dwight suffered in any way or changed its position on any account because of anything Pan-kow did or failed to do. The same is true of the University itself.
Thus the specification of the penal sum of $20,000 seems so disproportionate to any damage reasonably to have been anticipated, that the provision under consideration must be viewed as one for an unenforceable penalty. We do not here see a situation where the parties really meant to treat that sum as the equivalent of “estimated and ascertained” damages.
Judge Tenney so interpreted the language of the instrument before him and correctly applied the law.
II.
It may well seem that we are not called upon to go further but in view of the earnestness with which Ogden/ Dwight has advanced its claim, we will consider its status. Judge Anderson points out in Hylte Bruks Aktiebolag v. Babcock & Wilcox Co., 399 F.2d 289, 292 (2 CA 1968), quoting from 10 N.Y.Jur., Contracts, § 239, at 162:
“It is essential not merely that the contract shall operate for the benefit of the third person but that it shall have been so intended.”
Restatement, Contracts, Section 133, delineates third-party beneficiaries as of three classes, (1) the donee beneficiary and (2) the creditor beneficiary but then in (3) defines as an incidental beneficiary a party which does not come within classifications (1) or (2). Illustration 9, applicable here, may be transposed to read:
We see no basis on the present record for our going further than did the Court in Tomaso, Feitner & Lane, Inc. v. Brown, 4 N.Y.2d 391, 175 N.Y.S.2d 73, 74-75, 151 N.E.2d 221 (1958)
(per
curiam) and authorities cited therein.
If B, Pankow, promises to pay A, the University, in order that the University may be provided with money to pay C, D, and E, the latter “are at most incidental beneficiaries.”
It was the University which here proffered its own undertaking to qualifying contestants who failed to receive the contract.
The University had represented its intention to cover its own expenses and thereafter to distribute the remaining balance to qualifying contestants such as Ogden/Dwight. What the University might have chosen to do following a forfeiture represented in no way a promise by Pankow to confer a direct benefit upon Ogden/Dwight or to the six other contestants who originally had submitted parallel obligations and who likewise might have qualified had they not withdrawn. The instant contract contained no promise to make such contestants direct beneficiaries of Pan-kow’s obligation.
In sum, the law of New York contemplates that suit may not be maintained by those who are merely incidental beneficiaries. Rather, a contract is to be enforced only by those who are parties to it and by those. who are its direct beneficiaries.
Thus is reflected the general law discussed in Ger. Alliance Ins. Co. v. Home Water Co., 226 U.S. 220, 230, 33 S.Ct. 32, 57 L.Ed. 195 (1912):
Before a stranger can avail himself of the exceptional privilege of suing for a breach of an agreement, to which he is not a party, he must, at least show that it was intended for his direct benefit. For, as said by this court, speaking of the right of bondholders to sue a third party who had made an agreement with the obligor to discharge the bonds, they “may have had. an indirect interest in the performance of the undertakings, but that is a very different thing from the privity necessary to enable them to enforce the contract by suits in their own names.” (Citations omitted.)
We are satisfied that Judge Tenney correctly discerned the problem herein presented.
The judgment is affirmed.