O'Donnell v. Henry, Forrest & Co.

44 La. Ann. 845
CourtSupreme Court of Louisiana
DecidedJune 15, 1892
DocketNo. 1255
StatusPublished
Cited by4 cases

This text of 44 La. Ann. 845 (O'Donnell v. Henry, Forrest & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Donnell v. Henry, Forrest & Co., 44 La. Ann. 845 (La. 1892).

Opinion

The opinion of the court .was delivered by

Breaux, J.

Jay Gould entered into a contract with I. A. Henry to construct the extension of the Houston Central, Arkansas & Northern Railroad Company from Riverton station, on said road, in the parish of Caldwell, to Alexandria, La.

For the work, when completed and accepted by the engineer of the road, the contractor was to receive, under the terms of the contract, as follows:

In earth, per cubic yard of work, 16 cents; in loose rock, per cubic yard of work, 45 cents; in solid rock, per cubic yard of work, 85 cents; for clearing and grubbing, per acre, $60.

The firm of which Henry was a member undertook to carry out this contract.

Plaintiff became a sub-contractor on grade work, under the firm of Henry, Forrest & Go., to grade section 6 of the railway, for the price just mentioned, per cubic yard for earth work, and 85 cents for loose rock work, and 75 cents for solid rock, per cubic yard.

The contract provided for estimates, under the direction of the railway engineer, at the close of each month, of the amount and value, as near as practicable, of work done, and within thirty days the defendant was to pay the amount of said estimates, less 10 per cent.; the commission was withheld to enforce compliance with the contract.

Upon completion of all the work in the time and manner agreed upon, it was agreed that the engineer should make a final statement of all the work done.

It was also stipulated in the contract that in case any dispute or difference arose as to the construction to be placed upon the agreement as to the sufficiency of the work to be performed, or the price to be paid, it was to be referred to the engineer of the H. 0., A. & [847]*847N. R. R. Co., who was selected by both parties to consider and decide all such disputes and differences.

It was agreed that his decision should be final and binding.

A difference arose during the progress of the work, as to whether the work was to be classed as earth work or as work in solid or in loose rock.

Pleadings.

The plaintiff alleges as clue him on earth work, 67,884 yards at 16 cents ...$10,861 44
Loose rock, 25,000 yards at 85 cents......................................................... 8,750 00
Solid rock, 17,400 yards at 75 cents................................................... 18,050 00
Total....................................................................................$82,661 44
On which he admits to have received...............................................$22,186 051-8
Balance.......................................................... $10,524 98

The plaintiff further alleges that the difference was referred to the engineer of the company, who decided that the work should be classed as “solid rock,” under the specifications forming part of the contract.

The defendant called the H. O., A. & N. R. R. Oo. in warranty.

The railway company excepted to the call in warranty on the ground that the answer of the defendant showed no cause of action; that neither the petition in the suit nor the answer alleges any parity of contract between the plaintiff and said company, nor other reason justifying a call in warranty.

The District Court maintained the exception and dismissed the call in warranty.

The ruling maintaining the exception is correct, for the records do not disclose that the H. C., A. & N. R. R. Co. was'a party to the contract between the plaintiff and the defendant, or that it ever received its approval.

It is not shown that the consent to transfer, or sub-contract, required by one of the articles of the agreement, was ever obtained.

Plaintiff does not allege any indebtedness on the part of the warrantor, nor does it appear that there was any privity between them.

The defendants do not] resist, in argument, the dismissal of the call in warranty.

They do not set forth in their answer any right under the contract.

They do not pretend, that the railway company is liable to them for the amount claimed in case judgment be rendered against them. C. P. 378, 379 and 384; Hackett vs. Schiele & York, 19 An. 67; DeGreck vs. Murphy & Gains et al., 22 An. 297.

[848]*848 Bill of Exception.

The defendants applied to the court for the appointment of experts, alleging that the accounts between plaintiff and defendants were numerous, extensive and intricate; that intelligent classification and estimate of plaintiff’s work was a matter peculiarly within the knowledge of civil engineers.

The application was granted, and experts were appointed over the opposition of plaintiff.

The bill of exception retained to the ruling of the court sets forth that “there is no issue in the case, nor disputed facts which can “ legally be referred to experts for a report, and that the classifiea- “ tion of the work must, under the contract, have been settled by “ the railroad company’s engineers at the time the dispute arose.”

The court a qua did not exceed the discretion with which it is vested in.making the appointment.

Experts may be appointed when necessary to obtain information. C. P. 442.

The attention of the court is invited by the plaintiff to his opposition to the report of the experts.

The opposition reiterates the grounds incorporated in the bill of exception reserved to the appointment of experts, and further sets forth:

“That the engineer of the railroad company under the contract “ was the proper and only person who could classify the work done, “ or material removed, and that this must have been made and de- termined at the time the dispute arose.”

These and other-grounds of opposition alleged would not have justified the excluding of the report. They present questions to be considered on the merits, in determining the weight to be given to the report.

Statement of Facts.

Plaintiff’s witnesses testify that he suspended work on section 6 on account of the before mentioned difference and dispute about the classification given, and that he only resumed when the engineer pronounced the material “solid rock” and promised plaintiff compensation on that basis for its removal.

It is not disputed that in setting slopes the constructor is guided by the material to be removed in a cut, also that in an embankment [849]*849•ordinarily, ordinary earth will hold a slope one foot vertical to one foot horizontal, while slopes for rocks or hard material are one quarter of a foot to one foot.

Plaintiff’s witnesses testify that the slopes were drawn from one foot horizontal to one foot vertical, to one fourth horizontal, to one foot vertical, and that after the slope had been changed the material, less a small proportion, should have been classified as rock under the terms of the contract.

Two civil engineers employed by the railroad company are plaintiff’s witnesses; also plaintiff’s foreman, and the plaintiff himself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JH Jenkins Contractor, Inc. v. City of Denham Springs
216 So. 2d 549 (Louisiana Court of Appeal, 1968)
Caulfield v. Yazoo & M. v. R. Co.
127 So. 585 (Supreme Court of Louisiana, 1930)
Fritz Jahncke, Inc. v. Fidelity & Deposit Co.
117 So. 729 (Supreme Court of Louisiana, 1927)
Christina v. Cusimano
52 So. 157 (Supreme Court of Louisiana, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
44 La. Ann. 845, Counsel Stack Legal Research, https://law.counselstack.com/opinion/odonnell-v-henry-forrest-co-la-1892.