Odebrecht Construction, Inc. v. Louisiana Department of Revenue

182 So. 3d 132, 2015 La.App. 1 Cir. 0013, 2015 La. App. LEXIS 1732, 2015 WL 5474864
CourtLouisiana Court of Appeal
DecidedSeptember 18, 2015
DocketNo. 2015 CA 0013
StatusPublished
Cited by3 cases

This text of 182 So. 3d 132 (Odebrecht Construction, Inc. v. Louisiana Department of Revenue) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Odebrecht Construction, Inc. v. Louisiana Department of Revenue, 182 So. 3d 132, 2015 La.App. 1 Cir. 0013, 2015 La. App. LEXIS 1732, 2015 WL 5474864 (La. Ct. App. 2015).

Opinions

PETTIGREW, J.

lain this case, Odebrecht Construction Company, Inc. (“Odebrecht”) sought a refund of sales and use taxes paid to the State of Louisiana, Department of Revenue (“the Department”), in connection with purchases of clay deposits used to construct hurricane protection levees under Odebrecht’s contract with the United States Army Corps of Engineers (“COE”). The Department denied the refund claim, and Odebrecht appealed to the Louisiana Board of Tax Appeals (“the Board”). The Board ruled in favor of Odébrecht, and the Department appealed the ruling to the trial court. From a judgment upholding the ruling of the Board, the Department has appealed. For the reasons that follow, we affirm the November 5, '2014 judgment of the trial court and issue this memorandum opinion in compliance with Uniform Rules-Courts of Appeal,’Rule 2-16.1(B).

FACTS AND PROCEDURAL HISTORY

According to the record, Odebrecht entered into a contract with the COE on July 27, 2007, whereby Odebrecht was to acquire clay and deliver'it'to the Lake Ca-taouatche Project job site for subsequent incorporation into a hurricane protection levee. The contract was on a standard COE form, and the terms were dictated by the United States Government and nonnegotiable -for contract bidders. During the bid process, Odebrecht had been given a list of preapproved burrow pits from which to choose, and River Birch was selected. That same'month, Odebrecht entered into a contract with River Birch, which' specifically recognized that Ode-brecht’s purchase of the clay was for use in the COE project. Pursuant to the River Birch contract, title to the clay passed to Odebrecht when the clay was taken from the River Birch site. '

Gustavo Silveira, an Odebrecht project manager responsible for the Lake Ca-taouatche Project, testified at length concerning the scope of work Odebrecht performed in connection with the COE and River Birch contracts. According to Mr. Silyeira, Odebrecht was contracted,by the COE to enlarge the already existing hurricane levee by adding approximately 2 million cubic yards of clay Into the levee. Mr. Silveira explained the process as follows: .

|sWe excavated the material [from the River Birch site], we spread the material for processing, extracting the moisture, [making] it to the right moisture content. We load[ed] it into our trucks, transported] it about five, six miles to the job site,"-dumped in place, and then spread it and' then we surveyed- that material on a monthly base so'[as] to receive payment.

With regard to the surveying process, Mr. Silveira indicated that the survey would generate a volume of material in cubic yards and that the COE relied upon the survey amount to pay Odebrecht. Likewise, the survey amount controlled the amount paid to River Birch by Odebrecht. Mr. Silveira described the transaction as a “pass-through ... a transparent contract between [Odebrecht], the [COE]; and ... River Birch.”

[134]*134■ When asked about title to the clay once it was delivered to the job site, Mr. Sil-veira expressed that it was his understanding of the COE contract that once delivered to the job site, title to the clay passed to the COE before it was spread and compacted. In fact, Mr. Silveira explained that the COE bore the loss when clay, which had been delivered to the job site but not yet incorporated into the levee, was washed away by the rising tides of Hurricanes Ike and Gustav.

In connection with the River Birch contract, there were no sales and use taxes paid by Odebrecht to River Birch on the purchase of the clay. On May 3, 2010, Odebrecht was advised by the Department that it had been selected for an audit for January 1, 2007, through March 31, 2010. The audit revealed that no taxes had been paid by Odebrecht on the transactions between Odebrecht and River Birch. According to the record, the Department issued a Notice of Assessment dated December 15, 2010, notifying Ode-brecht that it owed $388,503.54. in sales taxes, and $174,673.87 in interest and penalties. Odebrecht requested and received a waiver of the delinquent penalty sum and subsequently paid $465,774.09 to the Department.1

Thereafter, on January 26, 2011, Ode-brecht filed a Claim for Refund of Taxes Paid with the Department, requesting a refund of the taxes paid based on what it believed was an erroneous assessment by the Department. By letter dated November 15, 2011, pOdebrecht received notice of the Department’s denial of same. Ode-brecht appealed the denial to the Board by filing a “Petition For Determination Of Overpayment And -Alternatively As Claim Against The State Of Louisiana.” Prior to answering the petition, the Department filed an exception raising the objection of lack of subject matter jurisdiction as to Odebrecht’s claim against the State. The Department also filed a separate motion to set aside the order previously granted by the Department approving the penalty waiver in favor of Odebrecht.

The matter was tried before the Board on May 14, 2013. Citing to La. R.S. 47:301(10)(g), Odebrecht argued that this situation fit exactly within the statute and that it was entitled to a refund of $387,544.22, plus interest and penalties paid.2 Odebrecht conceded to a small portion of its refund claim, $959.00, an amount related to aerial photographs. The Department countered that La. R.S. 47:301(10)(g) did not apply to the transaction at issue because there was not a sale to the United States government.and because the levee was not a final product. On June 20, 2013, the Board rendered judgment in favor of Odebrecht and ordered the refund.sought, with interest as provided by law. The Board denied the relief sought by the Department, including the exception raising the objection of lack of subject matter jurisdiction and the motion to set aside the order approving the penalty waiver.

The Board made the following findings:

Taxpayer seeks • a refund of • $465,774.09 in sales taxes that it paid to [135]*135the Secretary. Taxpayer entered into a contract with the United States Army Corp of Engineers (COE) to build levees. Taxpayer, in furtherance of the contract with the COE, entered into a contract with a company named River Birch Incorporated. The contract with River Birch provided that Taxpayer could mine (dig up) clay from River Birch’s premises and store and dry the mined clay on River Birch’s premises. Taxpayer’s Exhibit 7. Taxpayer’s contract with River Birch specifically stated that the purchased clay was for its project with the COE, and that it was “made conditional upon the approval of River Birch by the U.S. Army Corps of | ^Engineers.” Id. at p. 4.- The contract with River Birch further provided that the “stored clay will become the property of OCI-[Taxpayer] after it is removed from River Birch’s premises.” Id. at p: 2

The contract between Taxpayer and COE provided in paragraph 52.245-2Cc)(4)(J):

“Title to material purchased from a vendor shall pass to and vest in the Government upon delivery of such material.”

There was also undisputed testimony that the COE accepted the risk of loss prior to completion of construction. The witness testified that some of the dirt was washed away in the middle of construction by a hurricane, arid the COE actually paid the Taxpayer for that material anyway because title had already passed to the U.S. Government immediately upon the clay’s arrival on the work site.

• La. R.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
182 So. 3d 132, 2015 La.App. 1 Cir. 0013, 2015 La. App. LEXIS 1732, 2015 WL 5474864, Counsel Stack Legal Research, https://law.counselstack.com/opinion/odebrecht-construction-inc-v-louisiana-department-of-revenue-lactapp-2015.