O'Connor v. Metropolitan Casualty Ins. Co.

56 S.W.2d 686
CourtCourt of Appeals of Texas
DecidedJanuary 26, 1933
DocketNo. 2779.
StatusPublished
Cited by2 cases

This text of 56 S.W.2d 686 (O'Connor v. Metropolitan Casualty Ins. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Connor v. Metropolitan Casualty Ins. Co., 56 S.W.2d 686 (Tex. Ct. App. 1933).

Opinion

PELPHREY, C. J.

This suit was instituted January 15, 1931 by R. G. Davidson & Son against Eproson &. Co. and the Metropolitan Casualty Insurance Company, to recover the sum of $2,985.63 for labor performed in the building of highway No. 15 in Dallas county, Tex.

Appellant intervened seeking to recover from the same defendants the sum of $3,882.-72, which he claimed for labor performed on the same highway. It was agreed between the parties that Eproson & Co. entered into a contract with the state highway commission on May 14, 1929, to build the highway in question; that Eproson & Co. executed a bond for the faithful performance .of their contract to the state highway commission with the Metropolitan Casualty Insurance Company as surety; that Eproson & Co. sublet certain of the work to Davidson & Son and Jamesr O’Connor, agreeing to pay them 18 cents per cubic yard for excavating, 3 cents per cubic yard for overhauls, $18 per acre for clearing, and $26 per acre for grubbing; that the state highway commission had a local engineer in charge who super-1 vised and directed the work as it progressed; that O'Connor and Davidson & Son both completed the portion of the work allotted to them; that O’Connor excavated 54,345 yards of dirt that went into the roadway, cleared-3.55 acres of clearing, grubbed 3.55 acres of grubbing, and did 83.678 cubic yards of overhaul, amounting, under the prices agreed upon, to a total of $12,443.44; that each month, as the work progressed, the highway engineer furnished to Eproson & Co. and to the state highway commission an estimate of the amount of excavation, grubbing, clearing, and overhaul for the preceding month; that upon these estimates a total of $8,560.-74 was paid to O’Connor; that these monthly estimates were not made from actual measurements on the ground1, but were based upon the opinion of the engineer, and might have been more or might have been less than the actual amount of labor performed each month; that, after the road was completed, the engineer made actual measurements of the different kinds of work done, and furnished an estimate based thereon to Epro-son & Co. and to the state highway commission; that it was part of the duty of O’Con-nor to keep up the part of the road built by him until the engineer in charge should make his final estimate and accept the road as completed; that O’Connor finished his portion of the work about April 23, 1930; that the engineer’s final estimate on the road was made and the road accepted by the state on April 30, 1930; that thereafter, on May 6, 1930, the engineer made up an estimate as to the amount of work done by Davidson & Son and by O’Connor; that this estimate was the first practical means O’Connor had of knowing the amount of labor performed by him on the road; that the contractor and the subcontractor, as a practical matter, had to-depend upon the engineer in charge to furnish the final estimate in order to know the exact amount of work done on the highway; that it would have been highly impracticable to have measured the work done by cross-sectioning after each week’s or month’s work *687 was completed; and that the final estimate shows that there was due O’Connor the sum of $3,882.70. Appellant was awarded a Judgment against Eproson & Co., but was denied Judgment against Metropolitan Casualty Insurance Company, and from that action of the court he has perfected his appeal.

Opinion.

The trial court found in his findings of fact that O’Connor had a subcontract covering certain work; that he commenced said work about June 10, 1929, and finished it about April 23, 1930; that on August 1, 1930, he filed a claim with the county clerk of Dallas county showing a balance due of $3,882.70; that such claim was filed more than 90 days after the performance' of the last item of labor therein set out; that such claim covered labor performed from December 26, 1929, to February 25, 1930, amounting to $2,097.29, and for labor performed from February 25, 1930, to April 23, 1930, amounting to $1,795.41.

Among the conclusions of law filed by the court, we find: “I conclude as a matter of law that the failure of James O’Connor to-file an itemized, verified claim for his labor with the County Clerk of Dallas County, Texas, within ninety days from the performance of the last item of said labor precludes his recovery against said bond.”

It thus appears that the court’s refusal to award O’Connor a judgment against the surety wa§ based upon the fact that he had not filed his claim in accordance with the provisions of article 5160, R. S.

Appellant’s propositions are: (1) That article 5160, does not require a subcontractor, laborer, or materialman to file his claim within 90 days after the furnishing of labor or material in order to hold the surety; (2) that, where a contract on public work is a continuing one, and the contractor or laborer lias no means of knowing the exact amount of labor performed, and has to depend entirely upon the engineer in charge to furnish him with a full and complete statement thereof on final completion of the contract, then the time within which to file his claim with the county clerk under the statute does not commence to run until such statement is furnished to him; and (3) that, where the contract is a continuing one and the contractor or laborer has to depend entirely upon the engineer in charge to furnish him a full and complete statement of the amount of labor performed by him, then the time specified by the statute does not commence to run until, by the use of reasonable diligence, such laborer or contractor could acquire and know the exact amount of labor performed by him.

Article 5160, Revised Statutes 1928 (Vernon’s Ann. Civ. St. art. 5160, and note), reads:

“Any person, or persons, firm or corporation, entering into a formal contract with this State or its counties or school districts or other subdivisions thereof or any municipality therein for the construction of any public building, or the prosecution and completion of any public work shall be required, before commencing such work, to execute the usual Penal Bond, with the additional obligation that such contractor shall promptly make payments to all persons supplying him or them with labor and materials in the prosecution of the work provided for in such contract. Any person, company, or corporation who has furnished labor or materials used in the construction or repair of any public building or public work, and payment for which has not been made, shall have the right to intervene and be made a party to any action instituted by the State or any municipality on the bond of the contractor, and to have their rights and claims adjudicated in such action and judgment rendered thereon, subject, however, to the priority of the claims and judgment of the State or municipality. If the full amount of the liability of the surety on said bond is insufficient to pay the full amount of said claims and demands, then, after paying the full amount due the State or municipality, the remainder shall be distributed pro rata among- said in-tervenors. Provided* further, that no person or persons, firm or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Suggs v. Smithers
66 S.W.2d 750 (Court of Appeals of Texas, 1933)
Standard Sanitary Mfg. Co. v. Southern Surety Co. of New York
59 S.W.2d 291 (Court of Appeals of Texas, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
56 S.W.2d 686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oconnor-v-metropolitan-casualty-ins-co-texapp-1933.