Oberer Construction Co. v. Park Plaza, Inc.

179 N.E.2d 168, 88 Ohio Law. Abs. 152, 18 Ohio Op. 2d 198, 1961 Ohio Misc. LEXIS 272
CourtMontgomery County Court of Common Pleas
DecidedSeptember 18, 1961
DocketNo. 117476
StatusPublished
Cited by5 cases

This text of 179 N.E.2d 168 (Oberer Construction Co. v. Park Plaza, Inc.) is published on Counsel Stack Legal Research, covering Montgomery County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oberer Construction Co. v. Park Plaza, Inc., 179 N.E.2d 168, 88 Ohio Law. Abs. 152, 18 Ohio Op. 2d 198, 1961 Ohio Misc. LEXIS 272 (Ohio Super. Ct. 1961).

Opinion

Baynes, J.

This case was submitted to a three-judge' trial court upon the waiving of a jury and request for trial before a panel; (Section 2315.21, Revised Code.)

Plaintiff is engaged primarily as an earth-moving contractor. Its first cause of action makes two claims. It seeks a recovery of the reasonable value of the benefit to the defendant’s premises performed under a contract between the parties and for services performed under an alleged supplemental agreement. The total of the claims is $17,210.75 with interest from February 3, 1960. The second cause of action seeks foreclosure of an alleged mechanic’s lien for total claim amount. The third cause of action seeks damages of $25,000 for breach of the original and supplemental contracts.

The answer of defendant Park Plaza, Inc., admits status and capacity of the parties and that the Casualty Company defendant has executed a bond to secure any judgment recovered by plaintiff from defendant in substitution of any rights of plaintiff under the alleged mechanic’s lien.

Park Plaza, Inc., filed a cross-petition. The first cause of action seeks damages of $66,500 for plaintiff’s alleged breach of contract being the difference between plaintiff’s bid for the work and defendants’ cost of completing the work. An additional claim for alleged loss of rentals of $15,305 is made. The second, cause of action seeks damages of $8,000 for the alleged “improper and malicious mechanic’s lien filed.”

The answer of plaintiff to the cross-petition is in form of a general denial. Prior to resting its case, plaintiff moved to dismiss its third cause of action.

The testimony and argument consumed thirteen (13) trial days. The record discloses much conflict and contradiction and little agreement. The questions necessary to be determined are these:

(1) Was there a written contract between the parties dated January 9, 1960?
(2) Was there an enforcible oral supplemental agreement subsequently entered into by the parties?
(3) Was there a breach of either or both of the claimed written contract or claimed supplemental agreement?
(a) Did plaintiff breach, or
(b) Did defendant breach? And if it did,
[155]*155(4) Under either or both the claimed contract or claimed oral agreement, what work or services did plaintiff perform?
(5) (a) Under the claimed contract:
A. The reasonable value of his performance;
B. The benefit of the improvements, if any, which defendant derived from the work performed by plaintiff.
(b) Under the claimed oral agreement:
A. The contract price value.

It is not in controversy that plaintiff’s president, after discussion of terms and contents, drafted and submitted on January 9, 1960, in Dayton, Ohio, a letter of offer. This letter of offer was signed that day and place by defendant’s authorized representative, one Howard Silverberg. This, representative had also represented defendant in its lease and other property acquisitions negotiations antedating the January 9, 1960, offer and acceptance. The president and vice president of plaintiff as part owners of the fee of the leasehold were familiar with these negotiations. In addition plaintiff had submitted a bid for work on the same area to Howard Silver-berg on October 1, 1959, which had not been accepted.

It might have been that neither the controversies subsequent to January 9, 1960, and this action would have remained unresolved except for the fact that Howard Silverberg was killed, together with all other occupants of an airplane, in a crash on January 18, 1960. Thereafter, according to his religious custom, Akiba Zilberberg, brother of Howard Silverburg and president of defendant, was in mourning until January 29, 1960. The death of Howard Silverberg handicapped defendant’s evidence in the case as to the surrounding circumstances and meaning of various terms in the offer and acceptance and otherwise.

The offer and acceptance provided (plaintiff’s exhibit 1):

“1) All machine excavation necessary to prepare proposed grades as shown on the Ralph L. Woolpert drawing issued September 10, 1959. This will include site excavation; building excavation and footer excavation. Fills in the building area will be made to 95% compaction.
“And qualified tests will be, made and reports given to the Owner verifying the compaction. Construction operations will be conducted in such a way as to maintain the Bingo Operation.
[156]*156“We will furnish the completed building site (with 3" gravel on the suface) within 30 days from the starting date providing weather will allow. We understand the Owner will furnish the necessary stakes for excavation. Providing the Owner has the stakes in place we will start the excavation Monday, January 11th.
“2).......
ct
“We understand time is of the essence and we will prosecute the above described work with all the diligence which weather conditions will allow.”

One Donovan was in charge of the work for defendant. He had been in Dayton since January 3, 1960, and had been hired by Howard Silverberg. Several controversies arose between plaintiff and Donovan. The primary one and the one which, as we find, resulted in a breach by the defendant of the accepted offer was Donovan’s insistence that plaintiff proceed on establishing building grades under the Orgler plan rather than the Woolpert plan stated in the accepted offer.

The Woolpert plan essentially contemplated a balanced amount of excavation and fill to be obtained from the 43-acre Shopping Center site. It is not controverted that this contemplated the transferral of about 190,000 cubic yards. The Orgler plan was to require between 35 and 40,000 more cubic yards of excavation. There was testimony that Donovan told plaintiff that he wanted the building site graded to the Orgler plan elevations and it didn’t make any difference as to the grade elevation of the parking areas. There is creditable testimony that this was not possible without the redrafting of an entirely new grade plan taking into account an underlying rock formation and sub surface drainage system.

The accepted law is that:

“An owner commits a breach of a construction contract by changing plans and specifications otherwise than the contract permits and ordering substituted performance. * * * A change that is wrongfully required may involve so great delay or expense as to amount to a total breach as a practical repudiation of the construction contract. An assent by the contractor and proceeding with the work as demanded, without reservation of rights, will operate as a variation of the original [157]*157contract leaving no claim for damages.” Corbin on Contracts v. 4, 815, See. 947; See also 11 Ohio Jurisprudence (2d), 510, 511, Secs. 250, 252; CJS Contracts v. 17, 969, Sec. 468; Restatement of Contract, 468, Sec. 315.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
179 N.E.2d 168, 88 Ohio Law. Abs. 152, 18 Ohio Op. 2d 198, 1961 Ohio Misc. LEXIS 272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oberer-construction-co-v-park-plaza-inc-ohctcomplmontgo-1961.